Ramco Cements has announced the completion and commissioning of the second phase of 9 MW capacity installation at its Jayanthipuram plant in Andhra Pradesh.
The cement manufacturer aims to install a total of 27 MW of waste heat recovery plants in all three lines of clinker manufacturing, including a proposed third line, which is nearing completion.
Ramco had already commissioned phase 1 in September last year and is producing its full capacity. Phase 2 of 9 MW capacity was completed and commissioned on 28 February 2021, and is now producing at full capacity.
4th Indian Cement Review Conference 2021
17-18 March
With the commissioning of phase 2 of the waste heat recovery plant, 60% of the existing power requirement up to clinkerisation will be met from waste heat recovery plants, an environment-friendly source of power. The project cost for all three phases of waste heat recovery plants is estimated at Rs 220 crore.
To access current cement prices click here
The Jayanthipuram Cement Plant, located in the Krishna District of Andhra Pradesh, was commissioned in 1986 and has a capacity of 3.65 MTPA. The plant is equipped with SF Cooler, Vertical Pre-grinding mill with a 3-way separator, Ramco Fuzzy Logic System, Rotoscale for Kiln feed weighing system. It also has a slag mill for the manufacture of Portland Slag Cement.
The plant was also the first in the cement industry to instal the online Continuous Ambient Air Quality Monitoring Station (CAAQM) and to interlink and upload the online data with the Andhra Pradesh Pollution Control Board (APPCB) website.
Update: Meanwhile, Ramco also announced its expansion plans: its16 mt/year installed production capacity will increase to 20 mt/year during FY 2021-22, aides by the completion of its Kurnool, Andhra Pradesh, plant and a third production line at its Jayanthipuram plant.
: Ramco Cements Jayanthipuram plant
Also read:
Also read: Ramco Cements records highest ever quarterly profit
Ramco Cements has announced the completion and commissioning of the second phase of 9 MW capacity installation at its Jayanthipuram plant in Andhra Pradesh.
The cement manufacturer aims to install a total of 27 MW of waste heat recovery plants in all three lines of clinker manufacturing, including a proposed third line, which is nearing completion.
Ramco had already commissioned phase 1 in September last year and is producing its full capacity. Phase 2 of 9 MW capacity was completed and commissioned on 28 February 2021, and is now producing at full capacity.4th Indian Cement Review Conference 202117-18 March Click for event info
With the commissioning of phase 2 of the waste heat recovery plant, 60% of the existing power requirement up to clinkerisation will be met from waste heat recovery plants, an environment-friendly source of power. The project cost for all three phases of waste heat recovery plants is estimated at Rs 220 crore.
To access current cement prices click here
The Jayanthipuram Cement Plant, located in the Krishna District of Andhra Pradesh, was commissioned in 1986 and has a capacity of 3.65 MTPA. The plant is equipped with SF Cooler, Vertical Pre-grinding mill with a 3-way separator, Ramco Fuzzy Logic System, Rotoscale for Kiln feed weighing system. It also has a slag mill for the manufacture of Portland Slag Cement.
The plant was also the first in the cement industry to instal the online Continuous Ambient Air Quality Monitoring Station (CAAQM) and to interlink and upload the online data with the Andhra Pradesh Pollution Control Board (APPCB) website.Update: Meanwhile, Ramco also announced its expansion plans: its16 mt/year installed production capacity will increase to 20 mt/year during FY 2021-22, aides by the completion of its Kurnool, Andhra Pradesh, plant and a third production line at its Jayanthipuram plant.
Image: Ramco Cements Jayanthipuram plantAlso read: Ramco Cements commissions 9 MW waste heat recovery power plant
Also read: Ramco Cements records highest ever quarterly profit
Next Story
3i Infotech Reports Rs 7.25 Bn Revenue for FY25
3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..
Next Story
Emerald Finance Joins Baya PTE to Boost SME Bill Discounting
Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..
Next Story
BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25
BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..