1 GW of pumped storage projects in Karnataka won by JSW and Greenko
POWER & RENEWABLE ENERGY

1 GW of pumped storage projects in Karnataka won by JSW and Greenko

The Power Company of Karnataka (PCKL) has awarded contracts to JSW Neo Energy (JSW Energy) and Greenko KA 01 IREP (Greenko) for the provision of 1 GW of electricity supply of 8 hours per day from pumped hydro storage projects that offer continuous 5-hour discharge. By the bucket-filling process, JSW Neo Energy won 300 MW by quoting Rs 14.75 million, while Greenko got 700 MW by quoting Rs 14.76 million. 960 MW was quoted by Greenko. The e-reverse auction's opening bid was set at Rs 14.88 million. Earlier this month, the tender was floated.

The successful bidders and PCKL will sign power purchase agreements (PPAs) that are valid for 40 years. The PPA must be signed and the projects must be started within 36 months anywhere in Karnataka. The first phase of commissioning at each project site will require a minimum capacity of 100 MW or 50% of the total project capacity, whichever is lower. If part of the project is completed early, PCKL may purchase the electricity on a pro-rata basis at 75% of the annual fixed cost.

The performance bank guarantee for the project will be cashed in proportion to the remaining capacity that isn't commissioned if commissioning is delayed. The cost of setting up connectivity to the closest state transmission utility substation is on the developer. The Ministry of Electricity suggested last month that pumped storage projects be funded with favourable climate money.

These projects, which use renewable energy for charging, may be developed using sovereign green bonds issued to mobilise funding for green infrastructure.

Draft regulations for pumped storage projects in the nation have been released by the ministry. The rules aim to make use of pumped storage projects' enormous potential for grid stabilisation and peak power demand filling.

The Power Company of Karnataka (PCKL) has awarded contracts to JSW Neo Energy (JSW Energy) and Greenko KA 01 IREP (Greenko) for the provision of 1 GW of electricity supply of 8 hours per day from pumped hydro storage projects that offer continuous 5-hour discharge. By the bucket-filling process, JSW Neo Energy won 300 MW by quoting Rs 14.75 million, while Greenko got 700 MW by quoting Rs 14.76 million. 960 MW was quoted by Greenko. The e-reverse auction's opening bid was set at Rs 14.88 million. Earlier this month, the tender was floated. The successful bidders and PCKL will sign power purchase agreements (PPAs) that are valid for 40 years. The PPA must be signed and the projects must be started within 36 months anywhere in Karnataka. The first phase of commissioning at each project site will require a minimum capacity of 100 MW or 50% of the total project capacity, whichever is lower. If part of the project is completed early, PCKL may purchase the electricity on a pro-rata basis at 75% of the annual fixed cost. The performance bank guarantee for the project will be cashed in proportion to the remaining capacity that isn't commissioned if commissioning is delayed. The cost of setting up connectivity to the closest state transmission utility substation is on the developer. The Ministry of Electricity suggested last month that pumped storage projects be funded with favourable climate money. These projects, which use renewable energy for charging, may be developed using sovereign green bonds issued to mobilise funding for green infrastructure. Draft regulations for pumped storage projects in the nation have been released by the ministry. The rules aim to make use of pumped storage projects' enormous potential for grid stabilisation and peak power demand filling.

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train Set to Launch by 2028

India鈥檚 first bullet train is set to revolutionize high-speed travel along the western corridor, with the Mumbai-Ahmedabad high-speed rail project aiming for a 2028 launch. This announcement marks a major milestone in India鈥檚 infrastructure goals, as it promises to reduce travel time between the two economic hubs from eight hours to just three.Spanning a planned 508-kilometre stretch, the corridor stands as a flagship example of Indo-Japanese collaboration in technology and engineering. Once operational, the train is expected to transform intercity mobility and place India among the select..

Next Story
Infrastructure Transport

Mumbai-Gandhinagar Train Service Enhances Passenger Capacity

The Mumbai Central鈥揋andhinagar Capital Vande Bharat Express has increased its passenger capacity by adding four additional AC chair car coaches to meet the growing commuter demand on one of India鈥檚 busiest business corridors. This upgrade, effective from 11 May, raised the train鈥檚 seating capacity from 1,128 to 1,440 passengers, allowing it to serve 936 more passengers daily in both directions. The increase was described as a practical measure to accommodate the surging demand on the busy Mumbai鈥揂hmedabad鈥揋andhinagar route, which regularly operates at over 150 percent seat occupancy...

Next Story
Infrastructure Urban

Delhi Plans 12 Sewage Plants to Clean Najafgarh Drain Efficiently

Delhi鈥檚 ambitious plan to improve the water quality of the Yamuna River has gained significant momentum as the Delhi Jal Board (DJB) has begun work on 12 new sewage treatment plants (STPs) aimed at reducing the volume of untreated sewage being discharged from the Najafgarh Drain.This initiative forms part of the ongoing efforts to clean the Yamuna and restore the river鈥檚 health, which has long been a critical environmental issue for the national capital. Given the alarming pollution levels in the Yamuna, experts and officials consider this project a vital step toward addressing the persist..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement