CERC rejects Avaada Energy plea for MTOA extension
POWER & RENEWABLE ENERGY

CERC rejects Avaada Energy plea for MTOA extension

The Central Electricity Regulatory Commission (CERC) recently rejected a solar generator鈥檚 plea seeking an extension of the start date of medium-term open access (MTOA). It said that the transmission charges towards MTOA should be billed to the buyer only after the generating station鈥檚 commercial operation date.

The Commission added that the bills corresponding to the capacity not commissioned, raised to the Haryana Power Purchase Centre (HPPC) by the Central Transmission Utility (CTU), were contrary to the provision of the 鈥楽haring Regulations.鈥� Accordingly, it directed CTU to revise the bills and raise them on the petitioner.

Avaada Energy and Avaada RJHN had filed a petition seeking an extension of the start date of MTOA and restraining the CTU from taking any coercive measures for the non-operationalisation of 114.25 MW out of the total 240 MW on the premise that the start date of MTOA was February 1, 2022.

Since the solar generator achieved the commercial operation of only 125.75 MW by the end of January 2022, it requested CTU for an extension of time for the part operationalization of MTOA for the balance of 114.25 MW up to May 23, 2022.

Avaada Energy submitted that the MTOA of the contracted capacity being 240 MW (out of which 125.75 MW capacity has already been commissioned), had been delayed due to the outbreak of Covid-19 and resultant lockdown, which were considered 鈥榝orce majeure鈥� events.

See also:
JSL seeking partners to build 300 MW solar & wind capacities
Indore forced to drop solar plants from VCS programme


The Central Electricity Regulatory Commission (CERC) recently rejected a solar generator鈥檚 plea seeking an extension of the start date of medium-term open access (MTOA). It said that the transmission charges towards MTOA should be billed to the buyer only after the generating station鈥檚 commercial operation date. The Commission added that the bills corresponding to the capacity not commissioned, raised to the Haryana Power Purchase Centre (HPPC) by the Central Transmission Utility (CTU), were contrary to the provision of the 鈥楽haring Regulations.鈥� Accordingly, it directed CTU to revise the bills and raise them on the petitioner. Avaada Energy and Avaada RJHN had filed a petition seeking an extension of the start date of MTOA and restraining the CTU from taking any coercive measures for the non-operationalisation of 114.25 MW out of the total 240 MW on the premise that the start date of MTOA was February 1, 2022. Since the solar generator achieved the commercial operation of only 125.75 MW by the end of January 2022, it requested CTU for an extension of time for the part operationalization of MTOA for the balance of 114.25 MW up to May 23, 2022. Avaada Energy submitted that the MTOA of the contracted capacity being 240 MW (out of which 125.75 MW capacity has already been commissioned), had been delayed due to the outbreak of Covid-19 and resultant lockdown, which were considered 鈥榝orce majeure鈥� events. See also: JSL seeking partners to build 300 MW solar & wind capacitiesIndore forced to drop solar plants from VCS programme

Next Story
Infrastructure Urban

ClickPost Launches Atlas to Benchmark E-commerce Logistics

ClickPost, a leading logistics intelligence platform, has launched Atlas, a subscription-based benchmarking tool designed to transform how e-commerce brands strategise logistics. Powered by ClickPost鈥檚 proprietary network, which processes over 50 million shipments each month, Atlas enables brands to benchmark key operational metrics in real time against industry peers and standards.Unlike traditional dashboards, Atlas delivers comparative insights鈥攆rom fulfilment speeds, RTO rates and average order values to city-level delivery times and sales data鈥攁llowing brands to identify operational..

Next Story
Real Estate

Kalyani Launches Two New LivingTree Towers in Bengaluru

Bengaluru-based Kalyani Developers has announced the launch of Towers 3 and 4 at its flagship residential project, Kalyani LivingTree, located in KIADB Aerospace Park. The expansion adds 525 premium 3BHK apartments, ranging from 1300 to 1600 sq ft, and over 7.5 lakh sq ft of built-up area. Prices start from Rs 1.2 crore.These towers, the most exclusive in Phase 1, offer uninterrupted pool and landscape views, and access to over 60 lifestyle amenities, two clubhouses totalling 1 lakh sq ft, and more than 80 per cent open space.LivingTree spans 25 acres and will comprise ten towers of 23鈥�24 fl..

Next Story
Infrastructure Urban

Blue Water Logistics IPO opens May 27

Hyderabad-based Blue Water Logistics is launching its Rs 40.5 crore IPO on May 27, 2025, which will remain open for subscription until May 29. The price band has been set at Rs 132 to Rs 135 per share, with a lot size of 1,000 shares. This is a book-built issue entirely comprising a fresh issue of 30 lakh equity shares. The IPO will be listed on the NSE Emerge platform.Smart Horizon Capital Advisors is the sole book-running lead manager, while Maashitla Securities will act as the registrar. The anchor book will open on May 26, 2025. The IPO allocates 8,35,000 shares to anchor investors, 1,56,0..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement