GERC Announces Rs 2.76/kWh Tariff for Solar Projects Under 5 MW
POWER & RENEWABLE ENERGY

GERC Announces Rs 2.76/kWh Tariff for Solar Projects Under 5 MW

The tariff concerning the procurement of power by distribution licensees and others from solar projects in Gujarat has been established for a project life of 25 years. The Commission has introduced an accelerated depreciation benefit of Rs 0.28/kWh and a net tariff of Rs 2.48/kWh.

The benchmark normative capital cost for solar projects below the eligibility threshold for the bidding process has been set at Rs 30.5 million/MW. This determination followed the observation that the tariff discovered in competitive bidding by the Gujarat Urja Vikas Nigam ranged between Rs 2.30/kWh and Rs 2.66/kWh, alongside a decrease in solar module prices during the first quarter of the financial year 2024-25.

The Commission has chosen to maintain operation and maintenance (O&M) expenses at Rs 300,000/MW for the first operational year, with an annual escalation of 3.84% for tariff determination purposes.

The normative Capacity Utilization Factor has been set at 19% for the 25-year project life. A debt-equity ratio of 70:30 will be used for tariff determination. The normative interest rate for term loans is set at 10.15%, with a 15-year loan repayment period.

Depreciation rates are established at 4.67% per annum for the first 15 years and 2% from the 16th to the 25th year.

The working capital requirements for solar projects will include O&M expenses for one month, receivables for one month of electricity sales, and maintenance spares at 1% of the capital cost, escalating to 5% per annum. The normative interest on working capital is set at 10.65%.

In accordance with the GERC Multi-year Tariff Regulations 2024, the Commission has set the return on equity at 15.5% for projects below the eligibility threshold. Additionally, the Minimum Alternate Tax has been set at 17.47% per annum for the first ten years, with a Corporate Tax rate of 34.94% for the subsequent 15 years.

The Commission has considered a discount rate of 9.77% for levelised tariff calculations, reflecting the interest rate on term loans and return on equity. Should project developers receive financial assistance, incentives, subsidies, or other benefits from the Central or State Government, the tariff will be determined accordingly by the Commission.

The tariff concerning the procurement of power by distribution licensees and others from solar projects in Gujarat has been established for a project life of 25 years. The Commission has introduced an accelerated depreciation benefit of Rs 0.28/kWh and a net tariff of Rs 2.48/kWh. The benchmark normative capital cost for solar projects below the eligibility threshold for the bidding process has been set at Rs 30.5 million/MW. This determination followed the observation that the tariff discovered in competitive bidding by the Gujarat Urja Vikas Nigam ranged between Rs 2.30/kWh and Rs 2.66/kWh, alongside a decrease in solar module prices during the first quarter of the financial year 2024-25. The Commission has chosen to maintain operation and maintenance (O&M) expenses at Rs 300,000/MW for the first operational year, with an annual escalation of 3.84% for tariff determination purposes. The normative Capacity Utilization Factor has been set at 19% for the 25-year project life. A debt-equity ratio of 70:30 will be used for tariff determination. The normative interest rate for term loans is set at 10.15%, with a 15-year loan repayment period. Depreciation rates are established at 4.67% per annum for the first 15 years and 2% from the 16th to the 25th year. The working capital requirements for solar projects will include O&M expenses for one month, receivables for one month of electricity sales, and maintenance spares at 1% of the capital cost, escalating to 5% per annum. The normative interest on working capital is set at 10.65%. In accordance with the GERC Multi-year Tariff Regulations 2024, the Commission has set the return on equity at 15.5% for projects below the eligibility threshold. Additionally, the Minimum Alternate Tax has been set at 17.47% per annum for the first ten years, with a Corporate Tax rate of 34.94% for the subsequent 15 years. The Commission has considered a discount rate of 9.77% for levelised tariff calculations, reflecting the interest rate on term loans and return on equity. Should project developers receive financial assistance, incentives, subsidies, or other benefits from the Central or State Government, the tariff will be determined accordingly by the Commission.

Next Story
Infrastructure Urban

ClickPost Launches Atlas to Benchmark E-commerce Logistics

ClickPost, a leading logistics intelligence platform, has launched Atlas, a subscription-based benchmarking tool designed to transform how e-commerce brands strategise logistics. Powered by ClickPost鈥檚 proprietary network, which processes over 50 million shipments each month, Atlas enables brands to benchmark key operational metrics in real time against industry peers and standards.Unlike traditional dashboards, Atlas delivers comparative insights鈥攆rom fulfilment speeds, RTO rates and average order values to city-level delivery times and sales data鈥攁llowing brands to identify operational..

Next Story
Real Estate

Kalyani Launches Two New LivingTree Towers in Bengaluru

Bengaluru-based Kalyani Developers has announced the launch of Towers 3 and 4 at its flagship residential project, Kalyani LivingTree, located in KIADB Aerospace Park. The expansion adds 525 premium 3BHK apartments, ranging from 1300 to 1600 sq ft, and over 7.5 lakh sq ft of built-up area. Prices start from Rs 1.2 crore.These towers, the most exclusive in Phase 1, offer uninterrupted pool and landscape views, and access to over 60 lifestyle amenities, two clubhouses totalling 1 lakh sq ft, and more than 80 per cent open space.LivingTree spans 25 acres and will comprise ten towers of 23鈥�24 fl..

Next Story
Infrastructure Urban

Blue Water Logistics IPO opens May 27

Hyderabad-based Blue Water Logistics is launching its Rs 40.5 crore IPO on May 27, 2025, which will remain open for subscription until May 29. The price band has been set at Rs 132 to Rs 135 per share, with a lot size of 1,000 shares. This is a book-built issue entirely comprising a fresh issue of 30 lakh equity shares. The IPO will be listed on the NSE Emerge platform.Smart Horizon Capital Advisors is the sole book-running lead manager, while Maashitla Securities will act as the registrar. The anchor book will open on May 26, 2025. The IPO allocates 8,35,000 shares to anchor investors, 1,56,0..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement