Government Increases BESS Target to 14,000 MWh Amid Falling Prices
20 Mar 2025
2 Min Read
CW Team
The Ministry of Power (MoP) has raised the Battery Energy Storage System (BESS) capacity target under the Viability Gap Funding (VGF) program from 4,000 MWh to 13,200 MWh, citing a decline in storage costs. All states and implementing agencies have been directed to award BESS contracts by June 2025, ensuring program completion by May 2027.
The expanded target includes allocations under three components:
Market Component: NTPC Vidyut Vyapar Nigam (NVVN) has been allocated 1,000 MWh under the first tranche, with a VGF of Rs 4.6 million/MWh. SECI will manage an additional 1,200 MWh under Market Mechanism Tranche-II, with a VGF of Rs 2.7 million/MWh.
State Component: 6,000 MWh has been allocated to Rajasthan, Tamil Nadu, Karnataka, Gujarat, Maharashtra, Telangana, Bihar, and Kerala, with a VGF of Rs 2.7 million (~$31,150)/MWh.
Central PSU Component: 5,000 MWh has been assigned to NVVN, NHPC, and SJVN, also with a VGF of Rs 2.7 million/MWh.
Bidding for 500 MW/1,000 MWh under Tranche-I was completed in October 2024, and NVVN signed the Battery Energy Storage Purchase Agreement in December. Under the State Component, awards have been issued for 2,500 MWh, covering 1,000 MWh in Gujarat, 500 MWh in Maharashtra, and 1,000 MWh in Rajasthan.
Initially, the VGF program aimed to support at least 4,000 MWh of BESS by 2028 with a capital subsidy of Rs 37.6 billion. Approved in September 2023 with a total allocation of Rs 94 billion, the program's operational guidelines were released in March 2024. VGF disbursement follows a structured five-tranche model, with 10% at financial closure, 45% at the commercial operation date (COD), and the remaining 45% distributed over three years post-COD.
(MERCOM)
The Ministry of Power (MoP) has raised the Battery Energy Storage System (BESS) capacity target under the Viability Gap Funding (VGF) program from 4,000 MWh to 13,200 MWh, citing a decline in storage costs. All states and implementing agencies have been directed to award BESS contracts by June 2025, ensuring program completion by May 2027.
The expanded target includes allocations under three components:
Market Component: NTPC Vidyut Vyapar Nigam (NVVN) has been allocated 1,000 MWh under the first tranche, with a VGF of Rs 4.6 million/MWh. SECI will manage an additional 1,200 MWh under Market Mechanism Tranche-II, with a VGF of Rs 2.7 million/MWh.
State Component: 6,000 MWh has been allocated to Rajasthan, Tamil Nadu, Karnataka, Gujarat, Maharashtra, Telangana, Bihar, and Kerala, with a VGF of Rs 2.7 million (~$31,150)/MWh.
Central PSU Component: 5,000 MWh has been assigned to NVVN, NHPC, and SJVN, also with a VGF of Rs 2.7 million/MWh.
Bidding for 500 MW/1,000 MWh under Tranche-I was completed in October 2024, and NVVN signed the Battery Energy Storage Purchase Agreement in December. Under the State Component, awards have been issued for 2,500 MWh, covering 1,000 MWh in Gujarat, 500 MWh in Maharashtra, and 1,000 MWh in Rajasthan.
Initially, the VGF program aimed to support at least 4,000 MWh of BESS by 2028 with a capital subsidy of Rs 37.6 billion. Approved in September 2023 with a total allocation of Rs 94 billion, the program's operational guidelines were released in March 2024. VGF disbursement follows a structured five-tranche model, with 10% at financial closure, 45% at the commercial operation date (COD), and the remaining 45% distributed over three years post-COD.
(MERCOM)
Next Story
HCL-Foxconn to invest Rs 37 billion in chip plant near Jewar airport
The Union Cabinet has approved the establishment of a new semiconductor unit near Jewar airport in Uttar Pradesh under the India Semiconductor Mission. This sixth plant, a joint venture between HCL and Foxconn, marks further progress in India鈥檚 semiconductor journey. The project will see an investment of Rs 37 billion.The facility will produce display driver chips for mobile phones, laptops, automobiles, PCs, and other digital devices. It is designed for a monthly capacity of 20,000 wafers and an output of 36 million units.Five semiconductor units are already in advanced stages of constructi..
Next Story
Brigade acquires Velachery land for Rs 16-billion project
Brigade Enterprises has acquired a 5.41-acre land parcel on Velachery Road, Chennai, through an outright purchase for Rs 4.417 billion. Located next to Phoenix Market City, the site will be developed into a premium residential project with a gross development value of approximately Rs 16 billion and a development potential of 0.8 million square feet.The project offers strategic access to both the OMR IT Corridor and Chennai鈥檚 Central Business District, promising strong connectivity and premium lifestyle offerings. Brigade plans to create signature residences focused on aesthetics, functional..
Next Story
Liebherr marks 10,000th XPower wheel loader milestone
Liebherr-Werk Bischofshofen has rolled out its 10,000th XPower wheel loader, marking a major production milestone. The anniversary L 580 XPower model, featuring a power-split travel drive developed with ZF Friedrichshafen AG, was handed over to the BERGER Group in Passau.鈥淭he transmission from our partner ZF is a key component of the drivetrain in our XPower wheel loaders,鈥� said Gerhard Pirnbacher, Head of Quality Management at Liebherr. 鈥淲ith an impressive total of around 64 million operating hours already clocked up by XPower models, this transmission has proven its exceptional robustn..