Kerala鈥檚 ambitious Kochi Green Hydrogen Valley project is set to receive a total capital expenditure of ?185.42 billion. This investment aims to establish green hydrogen and ammonia plants, along with renewable energy infrastructure.
The project roadmap outlines ?41.66 billion for electrolyser and ammonia plants, and ?126.87 billion for renewable energy development. Additional funding of ?6.69 billion will be allocated for pilot projects, with an extra ?51.30 billion required during the scale-up phase.
The government is expected to contribute ?7.31 billion for various infrastructure needs, including ?450 million for techno-commercial assessments, ?3.51 billion for transmission infrastructure, ?2.64 billion for pipeline and refueling infrastructure, and ?700 million for offtake infrastructure.
The total green hydrogen subsidy needed to bridge the viability gap ranges from ?10.55 billion to ?29.08 billion in phases II and III, respectively. Investments required for hydrogen production, infrastructure development, and transmission grid are pegged at ?560 million, ?6.69 billion, and ?51.30 billion across the three phases.
Capex required for renewable energy development is ?9.03 billion in phase I and ?8.36 billion in phase II. For these two phases, renewable energy can be developed in Kerala or imported from other Indian sites, with ?109.48 billion needed for phase III additions utilizing Indian renewable energy resources.
Phase I, scheduled from 2024-25, focuses on preparing green hydrogen clusters, while phase II (2026-2030) will involve deploying technologies for green hydrogen. Phase III (2030-2040) will upscale the use of green hydrogen in various industries. The document highlights that phase I will include developing renewable energy for industrial electrification, phase II will focus on renewable energy development in the state and deploying electrolysers, and phase III will cover electrolyser scaling, ammonia plants, and hydrogen and ammonia infrastructure.
The project is expected to create approximately 3,600 jobs and abate 0.49 million tonnes of CO2 equivalent emissions in Kerala, reducing total emissions by about 2%.
The roadmap states that ANERT (the Agency for New and Renewable Energy Research and Technology) will act as the nodal agency for the hydrogen valley in Kerala, managing roles from stakeholder engagement to implementation. ANERT will also establish the Kerala Hydrogen Council and a subsidiary company, Kerala Green Hydrogen Hub.
Kochi Green Hydrogen Valley is geared towards the end-use of green ammonia, anticipating a demand of 40 kilotonnes per annum (ktpa) of green hydrogen and 260 ktpa of green ammonia under baseline scenarios, and 71 ktpa of green hydrogen and 625 ktpa of green ammonia in aggressive cases by 2040.
Green hydrogen demand is projected across 10-12 sectors, all present in Kerala, creating a total potential of 120 ktpa, with an additional demand of 40-100 ktpa through exports. Within this potential demand, over 100 ktpa will be concentrated in Kochi, encompassing refineries, fertilizers, chemicals, and transport hubs.
The document notes that for the Kochi Valley, India鈥檚 best renewable energy resources, centralized hydrogen production, and refueling infrastructure will be estimated, along with hydrogen and ammonia transportation through pipelines. Key offtakers include BPCL, FACT, HOCL, KSRTC, KWML, KSINC, and various export opportunities.
Kerala鈥檚 ambitious Kochi Green Hydrogen Valley project is set to receive a total capital expenditure of ?185.42 billion. This investment aims to establish green hydrogen and ammonia plants, along with renewable energy infrastructure.
The project roadmap outlines ?41.66 billion for electrolyser and ammonia plants, and ?126.87 billion for renewable energy development. Additional funding of ?6.69 billion will be allocated for pilot projects, with an extra ?51.30 billion required during the scale-up phase.
The government is expected to contribute ?7.31 billion for various infrastructure needs, including ?450 million for techno-commercial assessments, ?3.51 billion for transmission infrastructure, ?2.64 billion for pipeline and refueling infrastructure, and ?700 million for offtake infrastructure.
The total green hydrogen subsidy needed to bridge the viability gap ranges from ?10.55 billion to ?29.08 billion in phases II and III, respectively. Investments required for hydrogen production, infrastructure development, and transmission grid are pegged at ?560 million, ?6.69 billion, and ?51.30 billion across the three phases.
Capex required for renewable energy development is ?9.03 billion in phase I and ?8.36 billion in phase II. For these two phases, renewable energy can be developed in Kerala or imported from other Indian sites, with ?109.48 billion needed for phase III additions utilizing Indian renewable energy resources.
Phase I, scheduled from 2024-25, focuses on preparing green hydrogen clusters, while phase II (2026-2030) will involve deploying technologies for green hydrogen. Phase III (2030-2040) will upscale the use of green hydrogen in various industries. The document highlights that phase I will include developing renewable energy for industrial electrification, phase II will focus on renewable energy development in the state and deploying electrolysers, and phase III will cover electrolyser scaling, ammonia plants, and hydrogen and ammonia infrastructure.
The project is expected to create approximately 3,600 jobs and abate 0.49 million tonnes of CO2 equivalent emissions in Kerala, reducing total emissions by about 2%.
The roadmap states that ANERT (the Agency for New and Renewable Energy Research and Technology) will act as the nodal agency for the hydrogen valley in Kerala, managing roles from stakeholder engagement to implementation. ANERT will also establish the Kerala Hydrogen Council and a subsidiary company, Kerala Green Hydrogen Hub.
Kochi Green Hydrogen Valley is geared towards the end-use of green ammonia, anticipating a demand of 40 kilotonnes per annum (ktpa) of green hydrogen and 260 ktpa of green ammonia under baseline scenarios, and 71 ktpa of green hydrogen and 625 ktpa of green ammonia in aggressive cases by 2040.
Green hydrogen demand is projected across 10-12 sectors, all present in Kerala, creating a total potential of 120 ktpa, with an additional demand of 40-100 ktpa through exports. Within this potential demand, over 100 ktpa will be concentrated in Kochi, encompassing refineries, fertilizers, chemicals, and transport hubs.
The document notes that for the Kochi Valley, India鈥檚 best renewable energy resources, centralized hydrogen production, and refueling infrastructure will be estimated, along with hydrogen and ammonia transportation through pipelines. Key offtakers include BPCL, FACT, HOCL, KSRTC, KWML, KSINC, and various export opportunities.
Next Story
India Eyes $3 Trn Industry Growth by 2035
India鈥檚 industry sector is poised for a transformative leap, targeting a contribution of up to thirty-two per cent of Gross Domestic Product by year twenty thirty-five, according to Omniscience Capital. Driven largely by manufacturing, the sector is set to overtake agriculture鈥檚 GDP share, fuelled by rising domestic consumption, a growing middle class, and targeted government interventions.To achieve the ambitious USD one trillion merchandise export target by year twenty thirty, annual export growth must average twelve per cent. India鈥檚 merchandise exports stood at USD four hundred fifty..
Next Story
New Mall Supply to Touch 1.54 Bn Sq. Ft. by 2026 in Top Cities
India's top seven cities are set to receive 1.54 billion square feet of new Grade A mall space in calendar years 2025 and 2026, according to ANAROCK Research. Hyderabad and Delhi-National Capital Region will account for around sixty-five per cent of this supply, marking them as key retail hubs.Leasing activity is forecast to exceed 1.17 billion square feet over the same period, driven by rising consumer demand and the entry of over sixty international retail brands across fashion, electronics, lifestyle, and food and beverage categories.This robust leasing has helped reduce the supply-demand g..
Next Story
PG Electro Plast Posts Over 100% Profit Growth in FY25
PG Electroplast Limited (PGEL), a leading player in Electronic Manufacturing Services and plastic moulding, reported robust growth in its audited results for FY25. Consolidated revenues rose to Rs 48.70 billion, growing seventy-seven per cent year-on-year. Net profit surged one hundred and twelve per cent to Rs 2.91 billion, while EBITDA rose nearly eighty-nine per cent to Rs 5.19 billion.In Q4FY25, revenue touched Rs 19.10 billion, with net profit doubling to Rs 1.46 billion. The Board approved a final dividend of Rs 0.25 per share.PGEL鈥檚 product business recorded Rs 35.26 billion in r..