Power crisis looms over Odisha
03 Dec 2020
2 Min Read
CW Team
As the 460 MW Talcher Thermal Power Station (TTPS) of NTPC faces shutdown from 1 January 2021 for failing to follow the environmental standards set down by the Central Pollution Control Board (CPCB), Odisha could be moving towards a big power crisis from the beginning of 2021.
An ultimatum was given by the CPCB to the old power plants to take appropriate measures to reform themselves and comply with emission standards, including solid particulate matter (SPM), sulphur and nitrogen content. Power plants unable to fulfil these criteria would be closed as of December 31 this year.
The cost of fulfilling these requirements set by CPCB is around Rs 50 lakh per MW. Hence, fixing the deficiencies would have cost TTPS a considerable amount of Rs 23,000 crore. Therefore in 2018, it decided to replace its old plant with two new plants of 660 MW each. But the state government has remained a huge obstacle.
While the contract for the Rs 9,000 crore project was given the same year, the project approval was postponed by the state government until February of this year. Sources said that now it is too late for TTPS to introduce the programme, and disinterest from NTPC in the project has only made the situation worse.
Development of TTPS happened in two phases. Four units of 60 MW each were established in 1968, and two additional 110 MW units followed in 1982. Initially, the plant was operated by the former Orissa State Electricity Board.
Later, it was sold to NTPC in 1995, when Biju Patnaik was the CM, due less than 15 per cent load factor and losses. In 2000, NTPC invested extensively in the plant for reconstruction and modernisation, and its life was set by the Central Electricity Authority up to March 2021.
Although in the meantime, CPCB came up with new regulations that have put TTPS in a problematic situation. A top TTPS official, however, sounded optimistic. He said there is an ultimatum, but they are hopeful of its extension beyond the end of the current year.
Source-
As the 460 MW Talcher Thermal Power Station (TTPS) of NTPC faces shutdown from 1 January 2021 for failing to follow the environmental standards set down by the Central Pollution Control Board (CPCB), Odisha could be moving towards a big power crisis from the beginning of 2021.An ultimatum was given by the CPCB to the old power plants to take appropriate measures to reform themselves and comply with emission standards, including solid particulate matter (SPM), sulphur and nitrogen content. Power plants unable to fulfil these criteria would be closed as of December 31 this year.
The cost of fulfilling these requirements set by CPCB is around Rs 50 lakh per MW. Hence, fixing the deficiencies would have cost TTPS a considerable amount of Rs 23,000 crore. Therefore in 2018, it decided to replace its old plant with two new plants of 660 MW each. But the state government has remained a huge obstacle.
While the contract for the Rs 9,000 crore project was given the same year, the project approval was postponed by the state government until February of this year. Sources said that now it is too late for TTPS to introduce the programme, and disinterest from NTPC in the project has only made the situation worse.
Development of TTPS happened in two phases. Four units of 60 MW each were established in 1968, and two additional 110 MW units followed in 1982. Initially, the plant was operated by the former Orissa State Electricity Board.Later, it was sold to NTPC in 1995, when Biju Patnaik was the CM, due less than 15 per cent load factor and losses. In 2000, NTPC invested extensively in the plant for reconstruction and modernisation, and its life was set by the Central Electricity Authority up to March 2021.
Although in the meantime, CPCB came up with new regulations that have put TTPS in a problematic situation. A top TTPS official, however, sounded optimistic. He said there is an ultimatum, but they are hopeful of its extension beyond the end of the current year.
Source- New Indian Express
Next Story
Haver & Boecker Extends Packing Equipment Life with Upgrades
Haver & Boecker, a global leader in packing and bagging systems, is boosting equipment lifespan and plant efficiency through rebuilds and upgrades. As an Original Equipment Manufacturer, it provides tailored solutions to modernise systems without requiring full replacements.The company鈥檚 Performance+ Kits enable updates to assemblies with advanced tech, like ROTO-LOCK庐 dosing systems, which cut dust and spillage. These kits integrate across machines such as ROTO-PACKER庐, INTEGRA庐, and ADAMS庐. Over 121 upgrade kits are available, including sealing and drive tech.Performance+ Rebuilds ..
Next Story
Rosatom and Vietnam Sign Roadmap to Advance Nuclear Cooperation
Rosatom State Corporation and the Ministry of Science and Technology of Vietnam have signed an interdepartmental roadmap for the development of nuclear technologies through to 2030. The agreement, formalised by Rosatom Director General Alexey Likhachev and Vietnamese Minister Nguyen Manh Hung, outlines key collaborative efforts in nuclear research, infrastructure and energy development.The roadmap includes the construction of a new nuclear science and technology centre in Dong Nai province near Ho Chi Minh City, fuel supply for the Da Lat research reactor, and Vietnam鈥檚 participation in the ..
Next Story
Enlight Metals Expands to Karnataka and Gujarat to Serve OEMs
Enlight Metals Private Limited, a Pune-based metal aggregator established in twenty twenty-four, has announced its expansion into Karnataka and Gujarat to better serve Original Equipment Manufacturers (OEMs). The company will leverage its Mumbai service centre and new partnerships with regional centres to meet increasing demand in southern and western India.Already supplying over two hundred OEMs, including Tata Motors, Eicher, and JCB, Enlight Metals will now cater to industrial clusters in Bengaluru, Hubli, Ahmedabad, and Vadodara. This move aims to enhance delivery timelines and fortify its..