Pugalur-Madakkathara power corridor is finally reaching completion
04 Nov 2020
3 Min Read
CW Team
The
Pugalur-Madakkathara power corridor is set to go live this month. Covering a distance of 165 km, the line begins at Pugalur, Tamil Nadu, and ends at Madakkathara, Kerala. The line is the first High Voltage Direct Current Technology (HVDC) system that is the first transmission network in the country to be established on the latest voltage source converter based system that minimizes any loss of transmission.
The line has been designed to increase the power importing potential of the state and will be bringing in 360 KV 2,000 MW electricity from Chattisgarh to Tamil Nadu. Also at the Kerala state government鈥檚 request, this line acts as a continuation of the 800 KV 6000 MW, 1,765 km long Raigarh to Pugalur DC line.
The project was (PGCIL), which is part of the central public sector. The main idea of the project was to help neutralise the high increase of power shortage within the southern hemisphere of the country due to the peak load of power. The project includes both 138 km of an overhead line and the remaining 27 km of the line underground. The project was only possible after ensuring that adequate compensation was made towards the owners of the land the line runs through. This was to avoid any impediments that may have been caused.
According to a press release given, The project began in 2005, but due to many protests that occurred in regards to placing the line between Nedumon to Kochi in Kerala, the projects were dragged out. However, after reaching a mutual decision, the state鈥檚 Chief Minister Pinarayi Vijayan had announced the completion of the line on the Kerala side in November 2019.
Many residential and commercial users will stand to benefit from this new arrangement, as there will be an increase in the flow of power supply. This will help avoid any disruption that they may face in their daily lives. Among further news, the government had stated that they are facilitating 鈥渦ninterrupted power supply to industrial ventures鈥� that are being set up as part of the They went on to add that the project had entered the final stage and will soon be completed. Using the restrictions that were placed on travel and traffic during the lockdown, cables were laid along the side of the national highway of Thrissur, including the Kuthiran tunnel.
The Kerala State Electricity Board (KSEB) had designated a special task force to ensure the completion of the project on time in May 2018. The State government had also announced a special package to purchase the lands required to prevent any more delays. The Pugalur鈥揗adakkathara power corridor line will create and increase the usage of power as well as help prevent any loss of transfer from one place to another.
The Pugalur-Madakkathara power corridor is set to go live this month. Covering a distance of 165 km, the line begins at Pugalur, Tamil Nadu, and ends at Madakkathara, Kerala. The line is the first High Voltage Direct Current Technology (HVDC) system that is the first transmission network in the country to be established on the latest voltage source converter based system that minimizes any loss of transmission.
The line has been designed to increase the power importing potential of the state and will be bringing in 360 KV 2,000 MW electricity from Chattisgarh to Tamil Nadu. Also at the Kerala state government鈥檚 request, this line acts as a continuation of the 800 KV 6000 MW, 1,765 km long Raigarh to Pugalur DC line.
The project was initiated by the Power Grid Corporation of India (PGCIL), which is part of the central public sector. The main idea of the project was to help neutralise the high increase of power shortage within the southern hemisphere of the country due to the peak load of power. The project includes both 138 km of an overhead line and the remaining 27 km of the line underground. The project was only possible after ensuring that adequate compensation was made towards the owners of the land the line runs through. This was to avoid any impediments that may have been caused.
According to a press release given, a total of Rs.1,474 crore was provided to cover the entire cost of the project. The project began in 2005, but due to many protests that occurred in regards to placing the line between Nedumon to Kochi in Kerala, the projects were dragged out. However, after reaching a mutual decision, the state鈥檚 Chief Minister Pinarayi Vijayan had announced the completion of the line on the Kerala side in November 2019.
Many residential and commercial users will stand to benefit from this new arrangement, as there will be an increase in the flow of power supply. This will help avoid any disruption that they may face in their daily lives. Among further news, the government had stated that they are facilitating 鈥渦ninterrupted power supply to industrial ventures鈥� that are being set up as part of the Kochi-Bengaluru industrial corridor. They went on to add that the project had entered the final stage and will soon be completed. Using the restrictions that were placed on travel and traffic during the lockdown, cables were laid along the side of the national highway of Thrissur, including the Kuthiran tunnel.
The Kerala State Electricity Board (KSEB) had designated a special task force to ensure the completion of the project on time in May 2018. The State government had also announced a special package to purchase the lands required to prevent any more delays. The Pugalur鈥揗adakkathara power corridor line will create and increase the usage of power as well as help prevent any loss of transfer from one place to another.
Next Story
HCL-Foxconn to invest Rs 37 billion in chip plant near Jewar airport
The Union Cabinet has approved the establishment of a new semiconductor unit near Jewar airport in Uttar Pradesh under the India Semiconductor Mission. This sixth plant, a joint venture between HCL and Foxconn, marks further progress in India鈥檚 semiconductor journey. The project will see an investment of Rs 37 billion.The facility will produce display driver chips for mobile phones, laptops, automobiles, PCs, and other digital devices. It is designed for a monthly capacity of 20,000 wafers and an output of 36 million units.Five semiconductor units are already in advanced stages of constructi..
Next Story
Brigade acquires Velachery land for Rs 16-billion project
Brigade Enterprises has acquired a 5.41-acre land parcel on Velachery Road, Chennai, through an outright purchase for Rs 4.417 billion. Located next to Phoenix Market City, the site will be developed into a premium residential project with a gross development value of approximately Rs 16 billion and a development potential of 0.8 million square feet.The project offers strategic access to both the OMR IT Corridor and Chennai鈥檚 Central Business District, promising strong connectivity and premium lifestyle offerings. Brigade plans to create signature residences focused on aesthetics, functional..
Next Story
Liebherr marks 10,000th XPower wheel loader milestone
Liebherr-Werk Bischofshofen has rolled out its 10,000th XPower wheel loader, marking a major production milestone. The anniversary L 580 XPower model, featuring a power-split travel drive developed with ZF Friedrichshafen AG, was handed over to the BERGER Group in Passau.鈥淭he transmission from our partner ZF is a key component of the drivetrain in our XPower wheel loaders,鈥� said Gerhard Pirnbacher, Head of Quality Management at Liebherr. 鈥淲ith an impressive total of around 64 million operating hours already clocked up by XPower models, this transmission has proven its exceptional robustn..