Solar costs soar, completion rates slow down
POWER & RENEWABLE ENERGY

Solar costs soar, completion rates slow down

As per the reports submitted by the Investment Information and Credit Rating Agency of India Limited (ICRA), the completion pace of solar energy projects has slowed down. Developers are grappling with a shortage of workers and restrictions on the import of solar cells and modules.

(MNRE) has granted a six-month extension to developers for finishing under-construction projects affected by the national lockdown. The industry experts predict that this six-month grant might extend further.

One sign of this slowing pace is seen in the . The data shows that project completion is taking more time this year as compared to last year. In the third quarter, the country's solar imports stood at around $140 million. This was 77% less than the $598 million imported in the previous year.

In the second quarter, a fall of 83% was recorded. This year the industry imported only $69.2 million as compared to $399 million in the preceding year. As per the data collected by pandemic restrictions have reduced the mobility of both goods and people, domestically and globally. This delay has considerable damaging repercussions on the developers.

Vinay Rastogi, Managing Director of Bridge to India, a renewable energy consultancy, said, "The government has been accommodating with time extensions; however, the developers are still bearing extra expenses arising from delays. The deadline extension guards the developers against delay penalties, although all other costs still have to be borne."

He further added, "There is also a higher risk of increases in module costs, adverse changes in the exchange rates etc. The developers have been granted a six-month extension, but given the continuous execution constraints and challenges in getting the workforce mobilized, the deadlines may have to be extended further".

India is driving one of the biggest renewable capacity extension programmes in the world., It is targeting to reach 175 gigawatts (GW) capacity by 2022. Out of this 175 GW, 100 GW will come from solar energy.

At present, India continues to depend heavily on China for the imports of solar cells and modules to accomplish these targets. According to the trade data, imports from China is estimated for 88% of the total imports.

The government has decided to reduce the dependence on China for solar imports. To encourage domestic manufacturers, a basic customs duty was planned to be introduced, although that did not happen yet.

Vikram Solar CEO Saibaba Vutukuri asserted that the decrease in imports has not led to an augmented demand for modules built in India. Vikram Solar is currently providing capital expenditure to increase its manufacturing capacity from 1.2 GW to 3-4GW capacity in the next 3-4 years.

Vutukuri said, "We are moving ahead with our expansion plans, although other manufacturers are still waiting for the government to give clarity on whether it will support the domestic industry through a customs duty."

Due to covid restrictions, domestic manufacturers are striving to get raw materials, and the costs of inputs are increasing. Developers are not executing projects completely, leading to cost overruns on these projects.

The current pandemic can act as a trigger for the government, the solar industry and associated stakeholders to chart the right roadmap for achieving India's solar energy targets.

As per the reports submitted by the Investment Information and Credit Rating Agency of India Limited (ICRA), the completion pace of solar energy projects has slowed down. Developers are grappling with a shortage of workers and restrictions on the import of solar cells and modules. Ministry of New and Renewable Energy (MNRE) has granted a six-month extension to developers for finishing under-construction projects affected by the national lockdown. The industry experts predict that this six-month grant might extend further. One sign of this slowing pace is seen in the trade data of solar imports. The data shows that project completion is taking more time this year as compared to last year. In the third quarter, the country's solar imports stood at around $140 million. This was 77% less than the $598 million imported in the previous year. In the second quarter, a fall of 83% was recorded. This year the industry imported only $69.2 million as compared to $399 million in the preceding year. As per the data collected by Mercom India Research, pandemic restrictions have reduced the mobility of both goods and people, domestically and globally. This delay has considerable damaging repercussions on the developers. Vinay Rastogi, Managing Director of Bridge to India, a renewable energy consultancy, said, The government has been accommodating with time extensions; however, the developers are still bearing extra expenses arising from delays. The deadline extension guards the developers against delay penalties, although all other costs still have to be borne. He further added, There is also a higher risk of increases in module costs, adverse changes in the exchange rates etc. The developers have been granted a six-month extension, but given the continuous execution constraints and challenges in getting the workforce mobilized, the deadlines may have to be extended further. India is driving one of the biggest renewable capacity extension programmes in the world., It is targeting to reach 175 gigawatts (GW) capacity by 2022. Out of this 175 GW, 100 GW will come from solar energy. At present, India continues to depend heavily on China for the imports of solar cells and modules to accomplish these targets. According to the trade data, imports from China is estimated for 88% of the total imports. The government has decided to reduce the dependence on China for solar imports. To encourage domestic manufacturers, a basic customs duty was planned to be introduced, although that did not happen yet. Vikram Solar CEO Saibaba Vutukuri asserted that the decrease in imports has not led to an augmented demand for modules built in India. Vikram Solar is currently providing capital expenditure to increase its manufacturing capacity from 1.2 GW to 3-4GW capacity in the next 3-4 years. Vutukuri said, We are moving ahead with our expansion plans, although other manufacturers are still waiting for the government to give clarity on whether it will support the domestic industry through a customs duty. Due to covid restrictions, domestic manufacturers are striving to get raw materials, and the costs of inputs are increasing. Developers are not executing projects completely, leading to cost overruns on these projects. The current pandemic can act as a trigger for the government, the solar industry and associated stakeholders to chart the right roadmap for achieving India's solar energy targets.

Next Story
Infrastructure Energy

GAIL, Karnataka to Jointly Develop One GW Green Energy Capacity

GAIL (India) Limited has signed a memorandum of understanding with the Government of Karnataka to develop renewable energy projects with a combined capacity of up to one gigawatt over the next five years. Signed in Bengaluru on 9 May 2025, the agreement aligns with GAIL鈥檚 goal to achieve net-zero emissions by 2035.The Karnataka government will assist in approvals, clearances, and incentives as per current policies. Planned projects include ground-mounted, rooftop and floating solar systems, wind energy, and battery storage solutions. The initiative aims to boost Karnataka鈥檚 clean energy ca..

Next Story
Infrastructure Energy

Lakhanpur to Get 10 MW Solar Plant by APM Projects

APM Projects has been awarded a contract by the Central Mine Planning and Design Institute (CMPDI) to develop a 10 megawatt grid-connected solar power plant in Lakhanpur, Odisha. The project, valued at Rs 487.33 Mn, will be located on 15 hectares of land in Kirarama village, Jharsuguda district.The plant will support the energy needs of the Mahanadi Coalfields region. APM Projects will be responsible for engineering, procurement, construction, and operation and maintenance of the plant for a period of ten years.The solar facility will utilise high-efficiency modules rated at a minimum of 550 w..

Next Story
Real Estate

UP RERA Warns Builders Against Handing Over Incomplete Flats

The Uttar Pradesh Real Estate Regulatory Authority (UP RERA) has directed developers to stop handing over incomplete flats, also called bare shell or canvas units, warning that such violations may attract penalties of up to five per cent of a project鈥檚 total cost.The order, issued on 8 May 2025 under Section 37 of the Real Estate (Regulation and Development) Act, 2016, states that possession can only be offered after full completion of the apartment, with all amenities in place, and a registered sale or lease deed executed.UP RERA observed that some developers were inserting conditions in sa..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement