Telangana Seeks Bids for 250 MW/500 MWh Standalone Battery Storage
28 Jan 2025
2 Min Read
CW Team
Telangana Power Generation Corporation (TGGENCO) has issued a tender for establishing a 250 MW/500 MWh standalone battery energy storage system (BESS) pilot project in Telangana.
Developers will be eligible to receive viability gap funding of Rs 2.7 million per MWh or 30 per cent of the project鈥檚 capital cost, whichever is lower.
The deadline for bid submission is February 21, 2025, with bids scheduled to be opened on February 25. Applicants are required to pay a document fee of Rs 29,500 and a document processing fee of Rs 10,000/MW. Additionally, they must provide an earnest money deposit of Rs 432,000 per MW and a performance bank guarantee of Rs 1.08 million per MW.
The minimum bid size has been set at 100 MWh, equivalent to 50 MW for two hours. Successful developers must commission the project within 18 months of signing the battery energy storage purchase agreement, which will remain valid for 12 years from the project's full commissioning date.
Developers will be responsible for selecting the battery technology and connecting the system to the state transmission network. The project will rely on power supplied by the state distribution companies (DISCOMs) for charging and will dispatch power to the DISCOM network as instructed by the state load dispatch center. DISCOMs will ensure the required charging power is provided.
The BESS must support two operational cycles per day with an annual system availability of at least 95 per cent. Developers are also required to maintain a monthly AC-to-AC roundtrip efficiency of 85 per cent.
TGGENCO will facilitate the project by providing land on lease at no cost through a suitable agreement. Developers are required to use commercially established technologies to mitigate risks and ensure timely commissioning.
To qualify, bidders must have a net worth of at least Rs 4.32 million per MW of the quoted capacity as of the last financial year or seven days prior to the bid submission deadline.
In related developments, NHPC recently issued a tender for a 125 MW/500 MWh standalone BESS connected to Kerala's intrastate transmission system (Tranche I). Similarly, Gujarat Urja Vikas Nigam invited bids to establish a 500 MW/1000 MWh standalone BESS under tariff-based competitive bidding (Phase VI).
News source: Mercom India
Telangana Power Generation Corporation (TGGENCO) has issued a tender for establishing a 250 MW/500 MWh standalone battery energy storage system (BESS) pilot project in Telangana.
Developers will be eligible to receive viability gap funding of Rs 2.7 million per MWh or 30 per cent of the project鈥檚 capital cost, whichever is lower.
The deadline for bid submission is February 21, 2025, with bids scheduled to be opened on February 25. Applicants are required to pay a document fee of Rs 29,500 and a document processing fee of Rs 10,000/MW. Additionally, they must provide an earnest money deposit of Rs 432,000 per MW and a performance bank guarantee of Rs 1.08 million per MW.
The minimum bid size has been set at 100 MWh, equivalent to 50 MW for two hours. Successful developers must commission the project within 18 months of signing the battery energy storage purchase agreement, which will remain valid for 12 years from the project's full commissioning date.
Developers will be responsible for selecting the battery technology and connecting the system to the state transmission network. The project will rely on power supplied by the state distribution companies (DISCOMs) for charging and will dispatch power to the DISCOM network as instructed by the state load dispatch center. DISCOMs will ensure the required charging power is provided.
The BESS must support two operational cycles per day with an annual system availability of at least 95 per cent. Developers are also required to maintain a monthly AC-to-AC roundtrip efficiency of 85 per cent.
TGGENCO will facilitate the project by providing land on lease at no cost through a suitable agreement. Developers are required to use commercially established technologies to mitigate risks and ensure timely commissioning.
To qualify, bidders must have a net worth of at least Rs 4.32 million per MW of the quoted capacity as of the last financial year or seven days prior to the bid submission deadline.
In related developments, NHPC recently issued a tender for a 125 MW/500 MWh standalone BESS connected to Kerala's intrastate transmission system (Tranche I). Similarly, Gujarat Urja Vikas Nigam invited bids to establish a 500 MW/1000 MWh standalone BESS under tariff-based competitive bidding (Phase VI).
News source: Mercom India
Next Story
HCL-Foxconn to invest Rs 37 billion in chip plant near Jewar airport
The Union Cabinet has approved the establishment of a new semiconductor unit near Jewar airport in Uttar Pradesh under the India Semiconductor Mission. This sixth plant, a joint venture between HCL and Foxconn, marks further progress in India鈥檚 semiconductor journey. The project will see an investment of Rs 37 billion.The facility will produce display driver chips for mobile phones, laptops, automobiles, PCs, and other digital devices. It is designed for a monthly capacity of 20,000 wafers and an output of 36 million units.Five semiconductor units are already in advanced stages of constructi..
Next Story
Brigade acquires Velachery land for Rs 16-billion project
Brigade Enterprises has acquired a 5.41-acre land parcel on Velachery Road, Chennai, through an outright purchase for Rs 4.417 billion. Located next to Phoenix Market City, the site will be developed into a premium residential project with a gross development value of approximately Rs 16 billion and a development potential of 0.8 million square feet.The project offers strategic access to both the OMR IT Corridor and Chennai鈥檚 Central Business District, promising strong connectivity and premium lifestyle offerings. Brigade plans to create signature residences focused on aesthetics, functional..
Next Story
Liebherr marks 10,000th XPower wheel loader milestone
Liebherr-Werk Bischofshofen has rolled out its 10,000th XPower wheel loader, marking a major production milestone. The anniversary L 580 XPower model, featuring a power-split travel drive developed with ZF Friedrichshafen AG, was handed over to the BERGER Group in Passau.鈥淭he transmission from our partner ZF is a key component of the drivetrain in our XPower wheel loaders,鈥� said Gerhard Pirnbacher, Head of Quality Management at Liebherr. 鈥淲ith an impressive total of around 64 million operating hours already clocked up by XPower models, this transmission has proven its exceptional robustn..