亚博体育官网首页

Tripura floats tender for 1 MW residential rooftop solar projects
POWER & RENEWABLE ENERGY

Tripura floats tender for 1 MW residential rooftop solar projects

The Tripura State Electricity Corporation Limited (TSECL) has invited bids to empanel developers for 1 MW of residential rooftop solar projects in the state at different locations under rooftop solar program Phase-II.

The TSECL has invited bids to design, supply, install, and commission 1 MW rooftop solar projects.

The successful bidder will also have to look after the grid-connected rooftop solar project maintenance activities for five years.

The last date for bids submission online is 27 September 2021. On 29th September bids will be opened.

The solar project should be finished within 180 days from 15 months from the Ministry of New and Renewable Energy鈥檚 (MNRE) approval or the letter of allocation, whichever is first.

As a security deposit, the successful bidder will have to submit 3% of the project cost within 15 days of issuing the letter of intent (LoI).

Before the opening date of the bid, the bidder should have designed, installed, supplied, and commissioned grid-connected solar projects having a cumulative aggregate capacity of 100 kW minimum, which should have been commissioned.

Bidders of the general category can quote between 100 kW and 200 kW only.

For FY 21-22, the MNRE recently issued benchmark prices for grid-connected rooftop solar systems. This is applicable for every project to be granted and for empanelment of vendors by state implementing agencies under MNRE rooftop solar program phase-II after ten days from the notification, which is August 28, 2021.

During the last three FY, the average annual turnover of the bidders should be Rs 15,000 per kW for the bid capacity. The bidder should have an average annual turnover of Rs 5,000 per kW during the last three FY, for micro, small, and medium enterprises (MSMEs).

Alternatively, as of 31st March 2021, the bidder under the general category should have a positive net worth of a minimum of Rs 10,000 per kW. Similarly, the bidder should have a positive net worth of Rs 5,000 per kW as of the last day of the prior FY for MSMEs of Tripura.


Also read: Central Electronics floats tender for 2,000 mono PERC cells

Also read: GSECL invites bids for 4.5 MW of grid-connected solar projects

The Tripura State Electricity Corporation Limited (TSECL) has invited bids to empanel developers for 1 MW of residential rooftop solar projects in the state at different locations under rooftop solar program Phase-II. The TSECL has invited bids to design, supply, install, and commission 1 MW rooftop solar projects. The successful bidder will also have to look after the grid-connected rooftop solar project maintenance activities for five years. The last date for bids submission online is 27 September 2021. On 29th September bids will be opened. The solar project should be finished within 180 days from 15 months from the Ministry of New and Renewable Energy鈥檚 (MNRE) approval or the letter of allocation, whichever is first. As a security deposit, the successful bidder will have to submit 3% of the project cost within 15 days of issuing the letter of intent (LoI). Before the opening date of the bid, the bidder should have designed, installed, supplied, and commissioned grid-connected solar projects having a cumulative aggregate capacity of 100 kW minimum, which should have been commissioned. Bidders of the general category can quote between 100 kW and 200 kW only. For FY 21-22, the MNRE recently issued benchmark prices for grid-connected rooftop solar systems. This is applicable for every project to be granted and for empanelment of vendors by state implementing agencies under MNRE rooftop solar program phase-II after ten days from the notification, which is August 28, 2021. During the last three FY, the average annual turnover of the bidders should be Rs 15,000 per kW for the bid capacity. The bidder should have an average annual turnover of Rs 5,000 per kW during the last three FY, for micro, small, and medium enterprises (MSMEs). Alternatively, as of 31st March 2021, the bidder under the general category should have a positive net worth of a minimum of Rs 10,000 per kW. Similarly, the bidder should have a positive net worth of Rs 5,000 per kW as of the last day of the prior FY for MSMEs of Tripura. Image Source Also read: Central Electronics floats tender for 2,000 mono PERC cells Also read: GSECL invites bids for 4.5 MW of grid-connected solar projects

Next Story
Products

unWOOD transforms plastic waste into durable wood alternative

unWOOD, a breakthrough innovation, is converting hard-to-recycle plastic waste into a durable alternative to natural wood. Developed through a proprietary process called Intelligent Compounding, unWOOD uses a Macro Molecular Fiber Matrix (MMFM) structure to replicate the strength, look, and feel of hardwood鈥攚ithout the environmental cost.Conceptualised by Dr Babu Padmanabhan, the material addresses key flaws in traditional plastic recycling by consuming minimal energy, using zero water, and generating no microplastics. 鈥淎ny application that introduces plastics into areas where it cannot be..

Next Story
Real Estate

H盲fele launches Matrix undermount runners range

H盲fele has introduced its new Matrix range of undermount runners, designed to enhance drawer motion across kitchens, wardrobes, bathroom units, and more.Available in four weight capacities and a wide range of lengths, the Matrix undermount runners support diverse drawer designs. The 40 kg and 60 kg variants feature synchronised technology for superior motion and drawer stability. All runners come with an integrated soft-close mechanism to ensure smooth and noiseless operation.This in-house range is ideal for kitchen cabinets, bed storage units, living room furniture and bathroom drawers, offe..

Next Story
Real Estate

India's first AI-integrated campus announced in Noida

Yashoda Hospital and Bhutani Infra have announced plans to develop India鈥檚 first fully AI-integrated mixed-use campus in Greater Noida West. The upcoming project will feature a hospital, retail spaces, offices, SOHOs, serviced apartments, and a hotel鈥攁ll operating within a self-learning, generative AI-powered ecosystem.The AI-first campus will integrate real-time data systems, predictive analytics, and adaptive infrastructure to offer personalised experiences across functions. From AI-enabled footfall tracking and dynamic energy optimisation to smart F&B and retail insights, the develo..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement