Covid-19 delays construction of rural homes under PMAY-G
28 Jul 2021
2 Min Read
CW Team
Covid-19 pandemic has significantly derailed the building of rural houses under the government鈥檚 flagship Pradhan Mantri Awas Yojana - Gramin in 2020-21, bringing down the total accomplishment so far.
Sadhvi Niranjan Jyoti, Minister of State for Rural Development, said in the Lok Sabha, that against the aim of 2.02 crore houses allotted under the scheme till the financial year 2020-21, 1.50 crore homes or 75% have been achieved.
Additionally, a total of over 12.20 lakh homes have been made during the year 2021-22 against an approximated aim of construction of 44.09 lakh homes under the scheme, the minister for state added.
The ministry of rural development is executing Pradhan Mantri Awas Yojana- Gramin (PMAY-G) to help eligible rural households to construct 2.95 crore pucca homes with basic facilities to accomplish the aim of 鈥淗ousing for All鈥�.
According to the statement, the rural development ministry is conducting regular virtual meetings with the states and UTs to evaluate the growth of the scheme. In addition, daily monitoring of the progress is done on several parameters like gaps in the permission of houses, provision of land to landless beneficiaries, cleaning of the permanent waitlist (PWL) of PMAY-G, gaps in the release of central share or state matching share from the treasury.
Further, the review meetings are being conducted with states also for better knowledge of the restrictions being met and rectifying the same for developing progress of PMAY-G.
The Pradhan Mantri Awas Yojana Gramin (PMAY-G) is a centrally sponsored scheme, and the funds are shared by the central and state government in a 60:40 ratio (90:10 in North-Eastern State and hill states comprising Jammu & Kashmir & 100% central share in UTs comprising Ladakh).
Also read: NAREDCO demands one-time loan restructuring for stuck realty projects
Covid-19 pandemic has significantly derailed the building of rural houses under the government鈥檚 flagship Pradhan Mantri Awas Yojana - Gramin in 2020-21, bringing down the total accomplishment so far.
Sadhvi Niranjan Jyoti, Minister of State for Rural Development, said in the Lok Sabha, that against the aim of 2.02 crore houses allotted under the scheme till the financial year 2020-21, 1.50 crore homes or 75% have been achieved.
Additionally, a total of over 12.20 lakh homes have been made during the year 2021-22 against an approximated aim of construction of 44.09 lakh homes under the scheme, the minister for state added.
The ministry of rural development is executing Pradhan Mantri Awas Yojana- Gramin (PMAY-G) to help eligible rural households to construct 2.95 crore pucca homes with basic facilities to accomplish the aim of 鈥淗ousing for All鈥�.
According to the statement, the rural development ministry is conducting regular virtual meetings with the states and UTs to evaluate the growth of the scheme. In addition, daily monitoring of the progress is done on several parameters like gaps in the permission of houses, provision of land to landless beneficiaries, cleaning of the permanent waitlist (PWL) of PMAY-G, gaps in the release of central share or state matching share from the treasury.
Further, the review meetings are being conducted with states also for better knowledge of the restrictions being met and rectifying the same for developing progress of PMAY-G.
The Pradhan Mantri Awas Yojana Gramin (PMAY-G) is a centrally sponsored scheme, and the funds are shared by the central and state government in a 60:40 ratio (90:10 in North-Eastern State and hill states comprising Jammu & Kashmir & 100% central share in UTs comprising Ladakh).
Image Source
Also read: NAREDCO demands one-time loan restructuring for stuck realty projects
Next Story
Mumbai-Ahmedabad Bullet Train Set to Launch by 2028
India鈥檚 first bullet train is set to revolutionize high-speed travel along the western corridor, with the Mumbai-Ahmedabad high-speed rail project aiming for a 2028 launch. This announcement marks a major milestone in India鈥檚 infrastructure goals, as it promises to reduce travel time between the two economic hubs from eight hours to just three.Spanning a planned 508-kilometre stretch, the corridor stands as a flagship example of Indo-Japanese collaboration in technology and engineering. Once operational, the train is expected to transform intercity mobility and place India among the select..
Next Story
Mumbai-Gandhinagar Train Service Enhances Passenger Capacity
The Mumbai Central鈥揋andhinagar Capital Vande Bharat Express has increased its passenger capacity by adding four additional AC chair car coaches to meet the growing commuter demand on one of India鈥檚 busiest business corridors. This upgrade, effective from 11 May, raised the train鈥檚 seating capacity from 1,128 to 1,440 passengers, allowing it to serve 936 more passengers daily in both directions. The increase was described as a practical measure to accommodate the surging demand on the busy Mumbai鈥揂hmedabad鈥揋andhinagar route, which regularly operates at over 150 percent seat occupancy...
Next Story
Delhi Plans 12 Sewage Plants to Clean Najafgarh Drain Efficiently
Delhi鈥檚 ambitious plan to improve the water quality of the Yamuna River has gained significant momentum as the Delhi Jal Board (DJB) has begun work on 12 new sewage treatment plants (STPs) aimed at reducing the volume of untreated sewage being discharged from the Najafgarh Drain.This initiative forms part of the ongoing efforts to clean the Yamuna and restore the river鈥檚 health, which has long been a critical environmental issue for the national capital. Given the alarming pollution levels in the Yamuna, experts and officials consider this project a vital step toward addressing the persist..