Andhra Regulator Passes Order on Deemed Generation Losses
30 Aug 2024
2 Min Read
CW Team
The Andhra Pradesh Electricity Regulatory Commission (APERC) has issued a significant order concerning deemed generation losses for renewable energy projects in the state. This order directly impacts solar and wind power projects that have been affected by grid unavailability or other interruptions, causing losses in power generation.
Context of the Order: Deemed generation losses occur when power generation is hindered due to factors beyond the control of the renewable energy producers, such as grid outages or curtailments. The order from APERC addresses compensation and responsibility for such losses.
Impact on Renewable Energy Producers: The APERC's decision is crucial for solar and wind power developers in Andhra Pradesh as it determines how these losses will be treated. The order outlines the circumstances under which these producers can claim compensation for the losses incurred due to grid unavailability.
Compensation Mechanism: The order provides a detailed mechanism for calculating the compensation owed to power producers. It takes into account the duration of the grid outage, the capacity of the affected renewable energy project, and the prevailing tariffs. This approach is expected to provide a fair compensation framework for the losses suffered by the producers.
Effect on Electricity Tariffs: The order also touches on the implications for electricity tariffs in the state. Since the compensation for deemed generation losses may impact the cost of power procurement, there could be a subsequent effect on the tariffs paid by consumers. The APERC has sought to balance the interests of both the renewable energy producers and the consumers in its order.
Policy and Regulatory Implications: The APERC's decision is a significant policy measure that could influence the regulatory landscape for renewable energy in Andhra Pradesh. By addressing the issue of deemed generation losses, the commission aims to provide more certainty and stability for investors and developers in the renewable energy sector.
Long-Term Outlook: This order is expected to encourage further investments in the renewable energy sector in Andhra Pradesh by mitigating the risks associated with generation losses due to grid issues. It also aligns with the state's broader goals of increasing its renewable energy capacity and ensuring a reliable supply of green energy.
The APERC's order on deemed generation losses is a crucial step in supporting the growth of renewable energy in Andhra Pradesh, providing clarity on compensation mechanisms, and fostering a more stable environment for solar and wind power producers in the state.
The Andhra Pradesh Electricity Regulatory Commission (APERC) has issued a significant order concerning deemed generation losses for renewable energy projects in the state. This order directly impacts solar and wind power projects that have been affected by grid unavailability or other interruptions, causing losses in power generation.
Context of the Order: Deemed generation losses occur when power generation is hindered due to factors beyond the control of the renewable energy producers, such as grid outages or curtailments. The order from APERC addresses compensation and responsibility for such losses.
Impact on Renewable Energy Producers: The APERC's decision is crucial for solar and wind power developers in Andhra Pradesh as it determines how these losses will be treated. The order outlines the circumstances under which these producers can claim compensation for the losses incurred due to grid unavailability.
Compensation Mechanism: The order provides a detailed mechanism for calculating the compensation owed to power producers. It takes into account the duration of the grid outage, the capacity of the affected renewable energy project, and the prevailing tariffs. This approach is expected to provide a fair compensation framework for the losses suffered by the producers.
Effect on Electricity Tariffs: The order also touches on the implications for electricity tariffs in the state. Since the compensation for deemed generation losses may impact the cost of power procurement, there could be a subsequent effect on the tariffs paid by consumers. The APERC has sought to balance the interests of both the renewable energy producers and the consumers in its order.
Policy and Regulatory Implications: The APERC's decision is a significant policy measure that could influence the regulatory landscape for renewable energy in Andhra Pradesh. By addressing the issue of deemed generation losses, the commission aims to provide more certainty and stability for investors and developers in the renewable energy sector.
Long-Term Outlook: This order is expected to encourage further investments in the renewable energy sector in Andhra Pradesh by mitigating the risks associated with generation losses due to grid issues. It also aligns with the state's broader goals of increasing its renewable energy capacity and ensuring a reliable supply of green energy.
The APERC's order on deemed generation losses is a crucial step in supporting the growth of renewable energy in Andhra Pradesh, providing clarity on compensation mechanisms, and fostering a more stable environment for solar and wind power producers in the state.
Next Story
Ahmedabad鈥檚 Rs 1.17 Billion Flyover Opens
A major infrastructure milestone was achieved in Ahmedabad with the inauguration of a new Rs 1.17-billion flyover at Pallav Char Rasta on May 18.Union 亚博体育官网首页 and Cooperation Minister Amit Shah, who represents the Gandhinagar Lok Sabha constituency, unveiled the structure that was expected to ease vehicular congestion for nearly 1.5 lakh daily commuters navigating through the city鈥檚 busy Naranpura zone. The flyover, constructed across the 132-feet Ring Road, extended 935 metres in length and spanned 8.4 metres in width. It reached a height of 5.37 metres at the Pragatinagar junction and feature..
Next Story
CEC halts Balbharati-Paud Phata Road project in Pune; SC to review plan
In a notable development, the Supreme Court-appointed Central Empowered Committee (CEC) has instructed the Maharashtra government to immediately stop all construction activities related to the proposed Balbharati-Paud Phata Road (BBPP) project until the apex court completes its review of the matter.A letter dated May 16, signed by Siddhanta Das, chairman of the CEC, and addressed to the Maharashtra chief secretary, stated that no work should proceed in areas classified as 鈥渄eemed forest鈥� along the 2.1 km proposed road alignment. The committee cautioned that continuing construction in these..
Next Story
NHAI to Build 3.2 Km Bridge Over Ganga Connecting Buxar and Bharauli
The National Highways Authority of India (NHAI) has taken a significant step to enhance regional infrastructure by initiating preparations to construct a new bridge over the Ganga River. This bridge aims to strengthen the road connection between Bihar and Uttar Pradesh.The project, to be developed under NHAI鈥檚 supervision, is estimated to cost around Rs 368 crore. It will link Buxar in Bihar with Bharauli in Uttar Pradesh, facilitating smoother travel for thousands of daily commuters. Of the total 3.2 km length, 1.2 km will be built to the west of the existing Veer Kunwar Singh Bridge, while..