Coal India unit seeks bids for 13 MW solar project in Jharkhand
11 Mar 2024
2 Min Read
CW Team
The Central Mine Planning & Design Institute (CMPDI), a subsidiary of Coal India, has issued an invitation for bids regarding the design, supply, installation, commissioning, and testing of grid-connected solar power projects with a cumulative capacity of 13 MW.
It was mentioned that these projects were intended for Central Coalfields Ranchi at NK Area Chatra, Jharkhand, and were accompanied by a five-year operation and maintenance (O&M) period.
It was further informed that the last date for the submission of bids was March 28, 2024, and the opening of bids would take place on the same day.
The notification emphasized that the commencement of work should take place within 30 days of the issuance of the letter of acceptance and the submission of the performance security. Alternatively, the work was required to begin within seven days after the site was handed over for the first activity.
Bidders were obligated to provide an earnest money deposit of Rs 5 million.
The entire contract period, spanning 2,065 days, was detailed in two main phases: the construction of the plant, including testing and commissioning, allotted 240 days, and the comprehensive operation and maintenance of the plant, scheduled for 1,825 days.
It was specified that bidders needed to have completed similar works, specifically related to the design, supply, installation, commissioning, and testing of grid-connected ground-mounted, rooftop, or floating solar projects. Additionally, they were required to have finished three similar completed works, each with a cost not less than 20% of the estimated cost put to tender, or two similar completed works, each with a cost not less than 25% of the estimated cost put to tender, or one similar completed work, with a cost not less than 40% of the estimated cost put to tender.
The Central Mine Planning & Design Institute (CMPDI), a subsidiary of Coal India, has issued an invitation for bids regarding the design, supply, installation, commissioning, and testing of grid-connected solar power projects with a cumulative capacity of 13 MW.
It was mentioned that these projects were intended for Central Coalfields Ranchi at NK Area Chatra, Jharkhand, and were accompanied by a five-year operation and maintenance (O&M) period.
It was further informed that the last date for the submission of bids was March 28, 2024, and the opening of bids would take place on the same day.
The notification emphasized that the commencement of work should take place within 30 days of the issuance of the letter of acceptance and the submission of the performance security. Alternatively, the work was required to begin within seven days after the site was handed over for the first activity.
Bidders were obligated to provide an earnest money deposit of Rs 5 million.
The entire contract period, spanning 2,065 days, was detailed in two main phases: the construction of the plant, including testing and commissioning, allotted 240 days, and the comprehensive operation and maintenance of the plant, scheduled for 1,825 days.
It was specified that bidders needed to have completed similar works, specifically related to the design, supply, installation, commissioning, and testing of grid-connected ground-mounted, rooftop, or floating solar projects. Additionally, they were required to have finished three similar completed works, each with a cost not less than 20% of the estimated cost put to tender, or two similar completed works, each with a cost not less than 25% of the estimated cost put to tender, or one similar completed work, with a cost not less than 40% of the estimated cost put to tender.
Next Story
HCL-Foxconn to invest Rs 37 billion in chip plant near Jewar airport
The Union Cabinet has approved the establishment of a new semiconductor unit near Jewar airport in Uttar Pradesh under the India Semiconductor Mission. This sixth plant, a joint venture between HCL and Foxconn, marks further progress in India鈥檚 semiconductor journey. The project will see an investment of Rs 37 billion.The facility will produce display driver chips for mobile phones, laptops, automobiles, PCs, and other digital devices. It is designed for a monthly capacity of 20,000 wafers and an output of 36 million units.Five semiconductor units are already in advanced stages of constructi..
Next Story
Brigade acquires Velachery land for Rs 16-billion project
Brigade Enterprises has acquired a 5.41-acre land parcel on Velachery Road, Chennai, through an outright purchase for Rs 4.417 billion. Located next to Phoenix Market City, the site will be developed into a premium residential project with a gross development value of approximately Rs 16 billion and a development potential of 0.8 million square feet.The project offers strategic access to both the OMR IT Corridor and Chennai鈥檚 Central Business District, promising strong connectivity and premium lifestyle offerings. Brigade plans to create signature residences focused on aesthetics, functional..
Next Story
Liebherr marks 10,000th XPower wheel loader milestone
Liebherr-Werk Bischofshofen has rolled out its 10,000th XPower wheel loader, marking a major production milestone. The anniversary L 580 XPower model, featuring a power-split travel drive developed with ZF Friedrichshafen AG, was handed over to the BERGER Group in Passau.鈥淭he transmission from our partner ZF is a key component of the drivetrain in our XPower wheel loaders,鈥� said Gerhard Pirnbacher, Head of Quality Management at Liebherr. 鈥淲ith an impressive total of around 64 million operating hours already clocked up by XPower models, this transmission has proven its exceptional robustn..