Second phase of Biomining project set to be completed by July
30 Jun 2023
3 Min Read
CW Team
It was reported that the completion of the second phase of the biomining project, which aimed to segregate and process the accumulated solid waste at Ariyamangalam, the largest dumping yard in Tiruchi, was expected within a month. It was stated that the work had already reached 99% completion.
According to reports, Zigma Global Environ Solutions, a solid waste management firm based in Erode, was responsible for carrying out the biomining project. The project had started processing and clearing the garbage in October. The Smart Cities Mission initiative had allocated a budget of Rs 250 million for phase II of the project with the goal of clearing over 3.3 lakh cubic metres of waste.
The waste dumped in the yard, which amounted to approximately 3.3 lakh cubic meters, had been scientifically recycled. The process of disposing of the RDF (Refuse Derived Fuel), an industrial fuel, was currently in progress. B Sundarapandiyan, the manager of the firm, mentioned that they expected to complete the work by July since almost 99% of the task had already been accomplished. Currently, the RDF was being sent to factories in other states.
The transportation of the RDF generated from the dump yard was being carried out to various cement factories in Tamil Nadu and other states such as Maharashtra, Karnataka, and Andhra Pradesh. This fuel was being used as a substitute for fossil fuel in the kilns of these factories. On a daily basis, an average of 7,000 to 10,000 tonnes of RDF were being transported.
During the first phase of biomining, which started in January 2019, waste totalling over 7.6 lakh cubic metres was removed from the dump yard at an expense of approximately Rs 490 million. Currently, the Corporation had successfully reclaimed 36 acres out of the total 47.7-acre area designated for the project.
To evaluate the waste located beneath the surface and determine measures to strengthen the soil, the civic body had sought the expertise of specialists. Experts from the National Institute of Technology (NIT) were conducting a comprehensive study to develop a Detailed Project Report (DPR) for the third phase of biomining. Once the DPR was completed, a tender would be issued for phase III, focusing on clearing seven lakh cubic metres of solid waste located below the surface. The process of clearing the garbage through scientific recycling was expected to take place over the next two years.
Also read:
NMDC to invest in first gold block
16 states receive Rs 560.41 billion for capital investment
It was reported that the completion of the second phase of the biomining project, which aimed to segregate and process the accumulated solid waste at Ariyamangalam, the largest dumping yard in Tiruchi, was expected within a month. It was stated that the work had already reached 99% completion.
According to reports, Zigma Global Environ Solutions, a solid waste management firm based in Erode, was responsible for carrying out the biomining project. The project had started processing and clearing the garbage in October. The Smart Cities Mission initiative had allocated a budget of Rs 250 million for phase II of the project with the goal of clearing over 3.3 lakh cubic metres of waste.
The waste dumped in the yard, which amounted to approximately 3.3 lakh cubic meters, had been scientifically recycled. The process of disposing of the RDF (Refuse Derived Fuel), an industrial fuel, was currently in progress. B Sundarapandiyan, the manager of the firm, mentioned that they expected to complete the work by July since almost 99% of the task had already been accomplished. Currently, the RDF was being sent to factories in other states.
The transportation of the RDF generated from the dump yard was being carried out to various cement factories in Tamil Nadu and other states such as Maharashtra, Karnataka, and Andhra Pradesh. This fuel was being used as a substitute for fossil fuel in the kilns of these factories. On a daily basis, an average of 7,000 to 10,000 tonnes of RDF were being transported.
During the first phase of biomining, which started in January 2019, waste totalling over 7.6 lakh cubic metres was removed from the dump yard at an expense of approximately Rs 490 million. Currently, the Corporation had successfully reclaimed 36 acres out of the total 47.7-acre area designated for the project.
To evaluate the waste located beneath the surface and determine measures to strengthen the soil, the civic body had sought the expertise of specialists. Experts from the National Institute of Technology (NIT) were conducting a comprehensive study to develop a Detailed Project Report (DPR) for the third phase of biomining. Once the DPR was completed, a tender would be issued for phase III, focusing on clearing seven lakh cubic metres of solid waste located below the surface. The process of clearing the garbage through scientific recycling was expected to take place over the next two years.
Also read:
NMDC to invest in first gold block16 states receive Rs 560.41 billion for capital investment
Next Story
Blum India brings Design Reverie to Hyderabad
Blum India hosted the Hyderabad edition of its signature event, Design Reverie, at the historic Taj Falaknuma Palace, making it a memorable evening for the city鈥檚 architecture and interior design community. As per news reports, the event combined modern design sensibilities with the grandeur of a palace setting and the spiritual charm of Sufi qawwali.This marked the third edition of the event, after previous gatherings in Delhi and Bangalore. In Hyderabad, the focus was on fostering relaxed yet meaningful dialogue among design professionals鈥攁way from the typical conference setup. The eveni..
Next Story
Hafele launches Platinum Studio in Nagpur
Hafele has expanded its franchise footprint in central India by opening a new Studio Partner Platinum showroom in Nagpur in collaboration with Onkar Furnitech. The studio was inaugurated by Nitin Gadkari, Minister of Road Transport and Highways, along with Padma Gupta, Director 鈥� HR & Customer Experience, Hafele South Asia.Located at Sarthak Plaza, South Ambazari Road, Laxmi Nagar, the showroom offers an immersive experience of Hafele鈥檚 wide-ranging interior and home solutions. Designed as a hands-on, real-life application space, the studio showcases Hafele鈥檚 full portfolio鈥攊ncludi..
Next Story
Truflo by Hindware wins GPTW honour again
Truflo by Hindware has been certified a Great Place to Work for the fourth consecutive year, reaffirming its commitment to a people-first culture. The certification was awarded by the Great Place to Work Institute following a rigorous evaluation of employee experience, leadership, culture, and HR practices.Known as India鈥檚 fastest-growing plastic pipes and fittings company, Truflo has focused on fostering an inclusive, innovative, and growth-driven work environment. The company prioritises employee well-being and professional development, creating a culture where people feel valued and empow..