Supreme Court dismissed the SLP preferred by MPRDC
22 Oct 2021
3 Min Read
CW Team
In the matter of Madhya Pradesh Road Development Corporation (MPRDC) vs MoRT&H& M/s VEPL being SLP (C) 15646 of 2021, Supreme Court has dismissed the SLP preferred by MPRDC and upheld the impugned judgment dated September 03, 2021 rendered by Division Bench of High Court of Madhya Pradesh at Jabalpur in W.P No. 11783 of 2021.
The contention of MPRDC that the Arbitral Tribunal constituted in terms of the agreement doesn鈥檛 have jurisdiction to adjudicate the disputes and the same need to be referred to Tribunal as per M.P Madhyastham Adhikaran Adhiniyam, 1983 has been negated by the Courts.
Vindhyachal Expressway Pvt (VEPL) entered into a Concession Agreement with Madhya Pradesh Road Development Corporation (MPRDC) for four laning with paved shoulders between Km. 229+829 at Rewa City to Km. 140+600 at MP/UP border in the state of Madhya Pradesh (NH-7) on DBFOT basis. VEPL invoked arbitration on July 6, 2020 in terms of the provision of the concession agreement and the same was to be conducted in terms of the rules of International Centre for Alternative Dispute Resolution, New Delhi (ICADR).
MPRDC and MoRT&H (Respondents) were made party by VEPL as MoRT&H being the Principal and MPRDC is the Executing Agency. Since Respondents failed to nominate their Arbitrator then on September 24, 2020 ICADR duly nominated the Arbitrator on behalf of the Respondents. The Ld. Tribunal got constituted on October 27, 2020 comprising Justice A K Sikri (Retd), Justice Vikramjit Sen (Retd) and A S Chandhiok, Sr. Adv. Thereafter, MPRDC filed an application under Section 16 of Arbitration and Conciliation Act, 1996 and contended that the Tribunal doesn鈥檛 have the power to adjudicate the disputes as the same amount to Works Contract and so the same need to be adjudicated by the Tribunal under M P Madhyastham Adhikaran Adhiniyam, 1983. VEPL duly argued and contended that the scope of work doesn鈥檛 fall under the definition of works contract and MPRDC is only the executing agency and MoRT&H is the Principal Authority in terms of the MoU dated September 30, 2009.
The Tribunal ruled in favor of VEPL and dismissed the Section 16 application vide order dated December 29, 2020. MPRDC challenged the said order under Article 226 of Constitution at the High Court of Madhya Pradesh at Jabalpur by preferring a Writ Petition being W.P No. 11783 of 2021 and the same was dismissed vide judgment dated September 03, 2021. The Supreme Court has duly stated that the Court(s) under Article 226 cannot give any relief against the order of the Tribunal under Section 16 and the same need to be challenged under Section 34 of the Arbitration & Conciliation Act, 1996.
The order of the High Court and the dismissal of the SLP duly promotes the party autonomy in terms of opting for Arbitration methodology.
Former Solicitor General Ranjit Kumar, Senior Advocate appeared for the VEPL before the Hon鈥檅le Courts. The S&A Team led by Manoj K Singh, Founding Partner, and Nilava Bandyopadhyay, Sr. Partner is representing M/s VEPL in the arbitration and also represented in the Writ petition and the SLP.
In the matter of Madhya Pradesh Road Development Corporation (MPRDC) vs MoRT&H& M/s VEPL being SLP (C) 15646 of 2021, Supreme Court has dismissed the SLP preferred by MPRDC and upheld the impugned judgment dated September 03, 2021 rendered by Division Bench of High Court of Madhya Pradesh at Jabalpur in W.P No. 11783 of 2021. The contention of MPRDC that the Arbitral Tribunal constituted in terms of the agreement doesn鈥檛 have jurisdiction to adjudicate the disputes and the same need to be referred to Tribunal as per M.P Madhyastham Adhikaran Adhiniyam, 1983 has been negated by the Courts.Vindhyachal Expressway Pvt (VEPL) entered into a Concession Agreement with Madhya Pradesh Road Development Corporation (MPRDC) for four laning with paved shoulders between Km. 229+829 at Rewa City to Km. 140+600 at MP/UP border in the state of Madhya Pradesh (NH-7) on DBFOT basis. VEPL invoked arbitration on July 6, 2020 in terms of the provision of the concession agreement and the same was to be conducted in terms of the rules of International Centre for Alternative Dispute Resolution, New Delhi (ICADR). MPRDC and MoRT&H (Respondents) were made party by VEPL as MoRT&H being the Principal and MPRDC is the Executing Agency. Since Respondents failed to nominate their Arbitrator then on September 24, 2020 ICADR duly nominated the Arbitrator on behalf of the Respondents. The Ld. Tribunal got constituted on October 27, 2020 comprising Justice A K Sikri (Retd), Justice Vikramjit Sen (Retd) and A S Chandhiok, Sr. Adv. Thereafter, MPRDC filed an application under Section 16 of Arbitration and Conciliation Act, 1996 and contended that the Tribunal doesn鈥檛 have the power to adjudicate the disputes as the same amount to Works Contract and so the same need to be adjudicated by the Tribunal under M P Madhyastham Adhikaran Adhiniyam, 1983. VEPL duly argued and contended that the scope of work doesn鈥檛 fall under the definition of works contract and MPRDC is only the executing agency and MoRT&H is the Principal Authority in terms of the MoU dated September 30, 2009. The Tribunal ruled in favor of VEPL and dismissed the Section 16 application vide order dated December 29, 2020. MPRDC challenged the said order under Article 226 of Constitution at the High Court of Madhya Pradesh at Jabalpur by preferring a Writ Petition being W.P No. 11783 of 2021 and the same was dismissed vide judgment dated September 03, 2021. The Supreme Court has duly stated that the Court(s) under Article 226 cannot give any relief against the order of the Tribunal under Section 16 and the same need to be challenged under Section 34 of the Arbitration & Conciliation Act, 1996. The order of the High Court and the dismissal of the SLP duly promotes the party autonomy in terms of opting for Arbitration methodology.Former Solicitor General Ranjit Kumar, Senior Advocate appeared for the VEPL before the Hon鈥檅le Courts. The S&A Team led by Manoj K Singh, Founding Partner, and Nilava Bandyopadhyay, Sr. Partner is representing M/s VEPL in the arbitration and also represented in the Writ petition and the SLP.
Next Story
HCL-Foxconn to invest Rs 37 billion in chip plant near Jewar airport
The Union Cabinet has approved the establishment of a new semiconductor unit near Jewar airport in Uttar Pradesh under the India Semiconductor Mission. This sixth plant, a joint venture between HCL and Foxconn, marks further progress in India鈥檚 semiconductor journey. The project will see an investment of Rs 37 billion.The facility will produce display driver chips for mobile phones, laptops, automobiles, PCs, and other digital devices. It is designed for a monthly capacity of 20,000 wafers and an output of 36 million units.Five semiconductor units are already in advanced stages of constructi..
Next Story
Brigade acquires Velachery land for Rs 16-billion project
Brigade Enterprises has acquired a 5.41-acre land parcel on Velachery Road, Chennai, through an outright purchase for Rs 4.417 billion. Located next to Phoenix Market City, the site will be developed into a premium residential project with a gross development value of approximately Rs 16 billion and a development potential of 0.8 million square feet.The project offers strategic access to both the OMR IT Corridor and Chennai鈥檚 Central Business District, promising strong connectivity and premium lifestyle offerings. Brigade plans to create signature residences focused on aesthetics, functional..
Next Story
Liebherr marks 10,000th XPower wheel loader milestone
Liebherr-Werk Bischofshofen has rolled out its 10,000th XPower wheel loader, marking a major production milestone. The anniversary L 580 XPower model, featuring a power-split travel drive developed with ZF Friedrichshafen AG, was handed over to the BERGER Group in Passau.鈥淭he transmission from our partner ZF is a key component of the drivetrain in our XPower wheel loaders,鈥� said Gerhard Pirnbacher, Head of Quality Management at Liebherr. 鈥淲ith an impressive total of around 64 million operating hours already clocked up by XPower models, this transmission has proven its exceptional robustn..