Noida International Airport: Land hearing for villagers from Nov 1
30 Oct 2021
2 Min Read
CW Team
From 1st November, the Noida district administration will hold hearings to collect feedback from villagers who will be required to sell their land for the second phase of the Noida airport. This phase will affect a total of 6,830 families.
The first meeting will take place on 1st November in Mundhera, according to officials. The hearings will resume on 8th November after a break for Diwali and run until 11th November.
Balram Singh, an additional district magistrate, said that the public hearing schedule has been finalised. They will take place on November 1 and 2 and will resume on 8th November after the Diwali celebrations. Residents of the six villages where land would be acquired would be notified of the hearing locations and times.
On September 25, the district administration received the social impact assessment report from a six-member Gautam Buddha University team, which requested a few more details.
According to the SIA report, the number of families displaced this time will be nearly double that of the first stage. The administration had identified 3,003 families who needed to be relocated during the first phase, which included the acquisition of 1,334 hectares.
According to the SIA report, 5,063 families will have to be relocated for the second stage, which will span 1,363 hectares. Karauli Bangar, Kureb, Mundhera, Birampur, Dayanatpur, and Ranhera are the six villages where land will be acquired.
Houses in three of the six villages, Ranhera, Kureb, and Karauli Bangar, would have to be demolished, according to officials.
The state government has yet to respond to the district administration's request that the acquisition of Abadi land in Nagla Hukum Singh, a settlement in Karauli Bangar revenue village, be postponed.
Nagla Hukum Singh villagers have been holding panchayats regularly and have threatened to boycott public hearings and other acquisition procedures if their demands are not met.
Also read: Farmers to be rehabilitated for Noida airport project seek clear plan
From 1st November, the Noida district administration will hold hearings to collect feedback from villagers who will be required to sell their land for the second phase of the Noida airport. This phase will affect a total of 6,830 families.
The first meeting will take place on 1st November in Mundhera, according to officials. The hearings will resume on 8th November after a break for Diwali and run until 11th November.
Balram Singh, an additional district magistrate, said that the public hearing schedule has been finalised. They will take place on November 1 and 2 and will resume on 8th November after the Diwali celebrations. Residents of the six villages where land would be acquired would be notified of the hearing locations and times.
On September 25, the district administration received the social impact assessment report from a six-member Gautam Buddha University team, which requested a few more details.
According to the SIA report, the number of families displaced this time will be nearly double that of the first stage. The administration had identified 3,003 families who needed to be relocated during the first phase, which included the acquisition of 1,334 hectares.
According to the SIA report, 5,063 families will have to be relocated for the second stage, which will span 1,363 hectares. Karauli Bangar, Kureb, Mundhera, Birampur, Dayanatpur, and Ranhera are the six villages where land will be acquired.
Houses in three of the six villages, Ranhera, Kureb, and Karauli Bangar, would have to be demolished, according to officials.
The state government has yet to respond to the district administration's request that the acquisition of Abadi land in Nagla Hukum Singh, a settlement in Karauli Bangar revenue village, be postponed.
Nagla Hukum Singh villagers have been holding panchayats regularly and have threatened to boycott public hearings and other acquisition procedures if their demands are not met.
Image Source
Also read: Farmers to be rehabilitated for Noida airport project seek clear plan
Next Story
Blum India brings Design Reverie to Hyderabad
Blum India hosted the Hyderabad edition of its signature event, Design Reverie, at the historic Taj Falaknuma Palace, making it a memorable evening for the city鈥檚 architecture and interior design community. As per news reports, the event combined modern design sensibilities with the grandeur of a palace setting and the spiritual charm of Sufi qawwali.This marked the third edition of the event, after previous gatherings in Delhi and Bangalore. In Hyderabad, the focus was on fostering relaxed yet meaningful dialogue among design professionals鈥攁way from the typical conference setup. The eveni..
Next Story
Hafele launches Platinum Studio in Nagpur
Hafele has expanded its franchise footprint in central India by opening a new Studio Partner Platinum showroom in Nagpur in collaboration with Onkar Furnitech. The studio was inaugurated by Nitin Gadkari, Minister of Road Transport and Highways, along with Padma Gupta, Director 鈥� HR & Customer Experience, Hafele South Asia.Located at Sarthak Plaza, South Ambazari Road, Laxmi Nagar, the showroom offers an immersive experience of Hafele鈥檚 wide-ranging interior and home solutions. Designed as a hands-on, real-life application space, the studio showcases Hafele鈥檚 full portfolio鈥攊ncludi..
Next Story
Truflo by Hindware wins GPTW honour again
Truflo by Hindware has been certified a Great Place to Work for the fourth consecutive year, reaffirming its commitment to a people-first culture. The certification was awarded by the Great Place to Work Institute following a rigorous evaluation of employee experience, leadership, culture, and HR practices.Known as India鈥檚 fastest-growing plastic pipes and fittings company, Truflo has focused on fostering an inclusive, innovative, and growth-driven work environment. The company prioritises employee well-being and professional development, creating a culture where people feel valued and empow..