25000-tonne girder links Mumbai Coastal Rd to Bandra-Worli Sea Link
02 May 2024
2 Min Read
CW Team
Officials announced that the BrihanMumbai Municipal Corporation (BMC) had achieved a groundbreaking milestone in connecting the upcoming Mumbai Coastal Road (MCR) with the existing Bandra Worli Sea Link (BWSL) through the use of 'tidal waves conditions' in the Arabian Sea. They stated that this was the first experiment of its kind in the country.
The significant achievement involved the successful installation of the first gigantic 136-meter-long Bow Arch String Girder, constructed of steel and weighing approximately 2,000 tonnes. This occurred at 3.25 a.m. on Friday morning, linking the two vital routes in south Mumbai via India's largest 'arch bridge'.
BMC Municipal Commissioner Bhushan Gagrani, along with Additional Municipal Commissioner Amit Saini and other officials, observed the completion of this engineering marvel after an intense effort of 85 minutes during the early hours while Mumbai was asleep. The massive girder, measuring 18-21 meters wide, was lowered into place.
The journey of the girder began on Wednesday at 12.30 pm on a 25,000-tonne barge from Mazagon Docks and arrived at Worli Bay at 4 am the following day, awaiting further processing.
The setting up of the girder commenced at 2 am on April 26, taking into account the existing tidal conditions. It was gradually brought to the midpoint of the MCR and the BWSL on the barge and expertly stabilized amidst the sea waves and winds to ensure optimal conditions for the final setup.
To achieve this, the engineering teams established four 'mating units', two on the MCR and two on the BWSL, measuring 2 meters and 1.8 meters cones respectively. These were precisely connected at 3.25 am, completing the connectivity amid a resounding round of applause, cheers, and cries of 'hip hip hurray'.
Officials announced that the BrihanMumbai Municipal Corporation (BMC) had achieved a groundbreaking milestone in connecting the upcoming Mumbai Coastal Road (MCR) with the existing Bandra Worli Sea Link (BWSL) through the use of 'tidal waves conditions' in the Arabian Sea. They stated that this was the first experiment of its kind in the country.
The significant achievement involved the successful installation of the first gigantic 136-meter-long Bow Arch String Girder, constructed of steel and weighing approximately 2,000 tonnes. This occurred at 3.25 a.m. on Friday morning, linking the two vital routes in south Mumbai via India's largest 'arch bridge'.
BMC Municipal Commissioner Bhushan Gagrani, along with Additional Municipal Commissioner Amit Saini and other officials, observed the completion of this engineering marvel after an intense effort of 85 minutes during the early hours while Mumbai was asleep. The massive girder, measuring 18-21 meters wide, was lowered into place.
The journey of the girder began on Wednesday at 12.30 pm on a 25,000-tonne barge from Mazagon Docks and arrived at Worli Bay at 4 am the following day, awaiting further processing.
The setting up of the girder commenced at 2 am on April 26, taking into account the existing tidal conditions. It was gradually brought to the midpoint of the MCR and the BWSL on the barge and expertly stabilized amidst the sea waves and winds to ensure optimal conditions for the final setup.
To achieve this, the engineering teams established four 'mating units', two on the MCR and two on the BWSL, measuring 2 meters and 1.8 meters cones respectively. These were precisely connected at 3.25 am, completing the connectivity amid a resounding round of applause, cheers, and cries of 'hip hip hurray'.
Next Story
3i Infotech Reports Rs 7.25 Bn Revenue for FY25
3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..
Next Story
Emerald Finance Joins Baya PTE to Boost SME Bill Discounting
Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..
Next Story
BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25
BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..