Is highway execution at risk in India?
01 Feb 2019
2 Min Read
CW Staff
CRISIL Research has lowered its execution forecast for the National Highways Authority of India (NHAI) projects for fiscal 2019 to 3,600-3,800 km from the earlier anticipated 4,300 km, but is still 22 per cent higher than fiscal 2018. The firm estimates around 800 km of execution is at risk this fiscal, as dated on November 2018, because many hybrid annuity model (HAM) projects are still awaiting appointed dates for a longer duration after they were awarded.
The appointed date is the de-facto starting date of a project, when the NHAI hands over its contract letter to a developer or concessionaire. As on November 2018, CRISIL Research analysed 40 HAM projects amounting to 1,913 km (over 55 per cent of total HAM awarding that year), awarded by NHAI in fiscal 2018. In all, 3,400 km of HAM projects were awarded last fiscal. Its analysis indicates that many have achieved financial closure but most are still awaiting appointed dates on account of delays in land acquisition or regulatory clearances.
The firm鈥檚 interactions with stakeholders indicate that land acquisition for most of the projects awarded are in the advanced stage, but lenders will begin disbursements only after the mandatory 80 per cent land is at least at the 3G stage. 鈥淎s per MOSPI, execution in NHAI projects increased 23 per cent YoY to 1,363 km in H1 FY2019. We expects the run rate to continue, with NHAI execution expected at 3,600-3,800 km in FY2019, albeit pending appointed dates would be a drag,鈥� cities Hetal Gandhi, Director, CRISIL Research.
The situation with projects awarded under the engineering, procurement, construction (EPC) model is better than HAM. Typically, land acquisition is higher in EPC than HAM, because the NHAI gets an additional 150 days鈥� buffer on account of time taken by developers for financial closure. A sample of EPC projects awarded
last fiscal shows that 54 per cent have started execution.
Some projects in the advanced stages of execution are yet to receive the balance right of way, potentially affecting execution. In case 100 per cent of land is not provided on time, road developers have two options: Await right of way from NHAI and execute projects once received, or, de-scope part of the project for which land is not available and adjust the project cost on a pro-rata basis. However, the outcome will depend on individual stretches and is finalised based on negotiations with NHAI.
CRISIL Research has lowered its execution forecast for the National Highways Authority of India (NHAI) projects for fiscal 2019 to 3,600-3,800 km from the earlier anticipated 4,300 km, but is still 22 per cent higher than fiscal 2018. The firm estimates around 800 km of execution is at risk this fiscal, as dated on November 2018, because many hybrid annuity model (HAM) projects are still awaiting appointed dates for a longer duration after they were awarded.
The appointed date is the de-facto starting date of a project, when the NHAI hands over its contract letter to a developer or concessionaire. As on November 2018, CRISIL Research analysed 40 HAM projects amounting to 1,913 km (over 55 per cent of total HAM awarding that year), awarded by NHAI in fiscal 2018. In all, 3,400 km of HAM projects were awarded last fiscal. Its analysis indicates that many have achieved financial closure but most are still awaiting appointed dates on account of delays in land acquisition or regulatory clearances.
The firm鈥檚 interactions with stakeholders indicate that land acquisition for most of the projects awarded are in the advanced stage, but lenders will begin disbursements only after the mandatory 80 per cent land is at least at the 3G stage. 鈥淎s per MOSPI, execution in NHAI projects increased 23 per cent YoY to 1,363 km in H1 FY2019. We expects the run rate to continue, with NHAI execution expected at 3,600-3,800 km in FY2019, albeit pending appointed dates would be a drag,鈥� cities Hetal Gandhi, Director, CRISIL Research.
The situation with projects awarded under the engineering, procurement, construction (EPC) model is better than HAM. Typically, land acquisition is higher in EPC than HAM, because the NHAI gets an additional 150 days鈥� buffer on account of time taken by developers for financial closure. A sample of EPC projects awarded
last fiscal shows that 54 per cent have started execution.
Some projects in the advanced stages of execution are yet to receive the balance right of way, potentially affecting execution. In case 100 per cent of land is not provided on time, road developers have two options: Await right of way from NHAI and execute projects once received, or, de-scope part of the project for which land is not available and adjust the project cost on a pro-rata basis. However, the outcome will depend on individual stretches and is finalised based on negotiations with NHAI.
Next Story
Blum India brings Design Reverie to Hyderabad
Blum India hosted the Hyderabad edition of its signature event, Design Reverie, at the historic Taj Falaknuma Palace, making it a memorable evening for the city鈥檚 architecture and interior design community. As per news reports, the event combined modern design sensibilities with the grandeur of a palace setting and the spiritual charm of Sufi qawwali.This marked the third edition of the event, after previous gatherings in Delhi and Bangalore. In Hyderabad, the focus was on fostering relaxed yet meaningful dialogue among design professionals鈥攁way from the typical conference setup. The eveni..
Next Story
Hafele launches Platinum Studio in Nagpur
Hafele has expanded its franchise footprint in central India by opening a new Studio Partner Platinum showroom in Nagpur in collaboration with Onkar Furnitech. The studio was inaugurated by Nitin Gadkari, Minister of Road Transport and Highways, along with Padma Gupta, Director 鈥� HR & Customer Experience, Hafele South Asia.Located at Sarthak Plaza, South Ambazari Road, Laxmi Nagar, the showroom offers an immersive experience of Hafele鈥檚 wide-ranging interior and home solutions. Designed as a hands-on, real-life application space, the studio showcases Hafele鈥檚 full portfolio鈥攊ncludi..
Next Story
Truflo by Hindware wins GPTW honour again
Truflo by Hindware has been certified a Great Place to Work for the fourth consecutive year, reaffirming its commitment to a people-first culture. The certification was awarded by the Great Place to Work Institute following a rigorous evaluation of employee experience, leadership, culture, and HR practices.Known as India鈥檚 fastest-growing plastic pipes and fittings company, Truflo has focused on fostering an inclusive, innovative, and growth-driven work environment. The company prioritises employee well-being and professional development, creating a culture where people feel valued and empow..