CAG Audit exposes discrepancies in BBP-1 implementation
ROADS & HIGHWAYS

CAG Audit exposes discrepancies in BBP-1 implementation

The audit report by the Comptroller and Auditor General of India (CAG) regarding the 'Implementation of Phase-I of Bharatmala Pariyojana (BPP-1)' has brought to light significant revelations. The report highlights that the National Highway Authority of India (NHAI) Board sanctioned the Dwarka Expressway at a civil cost of Rs 72.87 billion, equating to Rs 2.50 billion per kilometre. This stands in stark contrast to the per kilometre civil cost of Rs 182 million that had been approved by the Cabinet Committee on Economic Affairs (CCEA).

In addition, the report uncovers that the Delhi-Vadodara Expressway, with an estimated civil cost of approximately Rs 328.39 billion, was endorsed by the NHAI Board even though it had not been included in the list of BPP-I projects approved by the CCEA.

The report sheds light on the fact that NHAI was responsible for the development of 70,950 km out of the designated 76,999 km of national highways for BPP-I. The NHAI was granted the authority to determine the construction approach for its projects. However, the audit discerned that NHAI was making decisions about construction methods without proper documented justifications.

According to the CAG report, "The audit also noticed that the evaluation and approval framework initially proposed to the CCEA failed to establish clear definitions for the terms 'project' and 'package'. As a result, the determination of whether construction packages within a single project should be regarded as individual projects or combined as one comprehensive project lacked clarity."

The CAG report further expounds that the appraisal and endorsement framework stipulated by the CCEA for BPP-I was not being adhered to by the entities responsible for project execution.

"The analysis encompassed a sample of 50 NHAI projects, and among these, eight projects had not undergone appraisal by the Project Appraisal and Technical Scrutiny Committee. This omission occurred due to the projects either being evaluated under the previous NHDP program or classified as balance works or one-time improvement initiatives," the report elucidated.

The audit report by the Comptroller and Auditor General of India (CAG) regarding the 'Implementation of Phase-I of Bharatmala Pariyojana (BPP-1)' has brought to light significant revelations. The report highlights that the National Highway Authority of India (NHAI) Board sanctioned the Dwarka Expressway at a civil cost of Rs 72.87 billion, equating to Rs 2.50 billion per kilometre. This stands in stark contrast to the per kilometre civil cost of Rs 182 million that had been approved by the Cabinet Committee on Economic Affairs (CCEA).In addition, the report uncovers that the Delhi-Vadodara Expressway, with an estimated civil cost of approximately Rs 328.39 billion, was endorsed by the NHAI Board even though it had not been included in the list of BPP-I projects approved by the CCEA.The report sheds light on the fact that NHAI was responsible for the development of 70,950 km out of the designated 76,999 km of national highways for BPP-I. The NHAI was granted the authority to determine the construction approach for its projects. However, the audit discerned that NHAI was making decisions about construction methods without proper documented justifications.According to the CAG report, The audit also noticed that the evaluation and approval framework initially proposed to the CCEA failed to establish clear definitions for the terms 'project' and 'package'. As a result, the determination of whether construction packages within a single project should be regarded as individual projects or combined as one comprehensive project lacked clarity.The CAG report further expounds that the appraisal and endorsement framework stipulated by the CCEA for BPP-I was not being adhered to by the entities responsible for project execution.The analysis encompassed a sample of 50 NHAI projects, and among these, eight projects had not undergone appraisal by the Project Appraisal and Technical Scrutiny Committee. This omission occurred due to the projects either being evaluated under the previous NHDP program or classified as balance works or one-time improvement initiatives, the report elucidated.

Next Story
Infrastructure Urban

3i Infotech Reports Rs 7.25 Bn Revenue for FY25

3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..

Next Story
Infrastructure Urban

Emerald Finance Joins Baya PTE to Boost SME Bill Discounting

Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..

Next Story
Infrastructure Urban

BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25

BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement