Gauhati HC seeks Centre & NHAI to clarify stance on NH 715 alignment
24 Jan 2025
2 Min Read
CW Team
The Gauhati High Court instructed the central government and the National Highways Authority of India (NHAI) to clarify their stance on the alignment of National Highway No. 715, which runs from Kaliabor Tiniali to Numaligarh. This section of NH 715 (formerly NH 37) is undergoing expansion into a four-lane highway.
A division bench comprising Chief Justice Vijay Bishnoi and Justice Kaushik Goswami heard arguments in two Public Interest Litigation (PIL) petitions (Nos. 38/2024 and 61/2024) filed by petitioners opposing the approval granted by the authorities for a new alignment of NH 715 during its expansion.
The court noted that decisions regarding new highway construction and the widening of existing highways typically fall under the jurisdiction of NHAI experts, and courts usually avoid intervening in such matters while exercising their extraordinary writ jurisdiction.
However, counsel for the petitioners argued that the Ministry of Road Transport and Highways (MoRTH) had clearly defined the alignment of NH 715 in its official records. According to MoRTH, NH 715 begins at its junction with NH-15 near Tezpur, connecting Jakhalabandha, Bokakhat, and Jorhat, and terminates at NH-2 near Jhanji in Assam. The petitioners contended that the ongoing expansion deviates from this originally specified alignment.
Senior counsel for PIL 38/2024 highlighted a meeting held on October 19, 2024, attended by Assam鈥檚 Minister of Transport & Fisheries, NHAI officials, and local representatives. In this meeting, NHAI clarified that the NH 715 expansion was a Brown Field project, involving the upgrading of the existing highway and two bypasses.
The petitioners argued that, based on MoRTH鈥檚 guidelines, widening an existing highway qualifies as a Brown Field project, while construction along a new alignment is categorized as a Green Field project. They claimed there was no justification for deviating from the original alignment for NH 715's expansion.
After reviewing these submissions, the court directed the Union of India and NHAI to respond to the issues raised. It instructed Deputy Solicitor General of India R.K.D. Choudhury and NHAI standing counsel C. Boruah to file their responses within two weeks.
The Gauhati High Court instructed the central government and the National Highways Authority of India (NHAI) to clarify their stance on the alignment of National Highway No. 715, which runs from Kaliabor Tiniali to Numaligarh. This section of NH 715 (formerly NH 37) is undergoing expansion into a four-lane highway.
A division bench comprising Chief Justice Vijay Bishnoi and Justice Kaushik Goswami heard arguments in two Public Interest Litigation (PIL) petitions (Nos. 38/2024 and 61/2024) filed by petitioners opposing the approval granted by the authorities for a new alignment of NH 715 during its expansion.
The court noted that decisions regarding new highway construction and the widening of existing highways typically fall under the jurisdiction of NHAI experts, and courts usually avoid intervening in such matters while exercising their extraordinary writ jurisdiction.
However, counsel for the petitioners argued that the Ministry of Road Transport and Highways (MoRTH) had clearly defined the alignment of NH 715 in its official records. According to MoRTH, NH 715 begins at its junction with NH-15 near Tezpur, connecting Jakhalabandha, Bokakhat, and Jorhat, and terminates at NH-2 near Jhanji in Assam. The petitioners contended that the ongoing expansion deviates from this originally specified alignment.
Senior counsel for PIL 38/2024 highlighted a meeting held on October 19, 2024, attended by Assam鈥檚 Minister of Transport & Fisheries, NHAI officials, and local representatives. In this meeting, NHAI clarified that the NH 715 expansion was a Brown Field project, involving the upgrading of the existing highway and two bypasses.
The petitioners argued that, based on MoRTH鈥檚 guidelines, widening an existing highway qualifies as a Brown Field project, while construction along a new alignment is categorized as a Green Field project. They claimed there was no justification for deviating from the original alignment for NH 715's expansion.
After reviewing these submissions, the court directed the Union of India and NHAI to respond to the issues raised. It instructed Deputy Solicitor General of India R.K.D. Choudhury and NHAI standing counsel C. Boruah to file their responses within two weeks.
Next Story
3i Infotech Reports Rs 7.25 Bn Revenue for FY25
3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..
Next Story
Emerald Finance Joins Baya PTE to Boost SME Bill Discounting
Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..
Next Story
BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25
BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..