Mumbai coastal road project 36% completed: BMC
09 Jul 2021
2 Min Read
CW Team
The Brihanmumbai Municipal Corporation (BMC) has completed 36% of the total work of the Mumbai coastal road project, against the 40% target set for completion by mid of 2021.
The civic body aims to finish all the work by December 2023, according to the authorities. The earlier target of project completion was July 2023, which was affected by the Covid-19 pandemic restrictions.
Chief engineer for the coastal road project, Vijay Nighot, said that the completed work includes about 470 metre or 25% of tunneling work of one tunnel and reclamation of 105 hectares of the total 111 hectares.
He further added that the piling work, casting of piers and girders, construction of the ramp work at Marine Drive, and tunneling work are in progress at present.
In December last year, BMC announced that its original aim of finishing the coastal road project by October 2022 had been extended to July 2023.
Nighot had then said that we have wasted eight months due to the court case, that had stayed the project construction in 2019, and additional six months due to the lockdown.
The coastal road will join Nariman Point to Bandra Worli Sea Link, which is 10.58 km long. Twin tunnels of a length of 2.07 km will join Girgaum Chowpatty and Malabar Hill. All underground tunnels will have three lanes of depth 70 m. The coastal road project will cost Rs 8,429 crore.
55% of the work should be accomplished by this December, and 85% of the work should be done by 2022 as per the civic body plan.
Also read: Mumbai鈥檚 coastal road project: BMC completes 330 m of tunnelling work
Also read:
The Brihanmumbai Municipal Corporation (BMC) has completed 36% of the total work of the Mumbai coastal road project, against the 40% target set for completion by mid of 2021.
The civic body aims to finish all the work by December 2023, according to the authorities. The earlier target of project completion was July 2023, which was affected by the Covid-19 pandemic restrictions.
Chief engineer for the coastal road project, Vijay Nighot, said that the completed work includes about 470 metre or 25% of tunneling work of one tunnel and reclamation of 105 hectares of the total 111 hectares.
He further added that the piling work, casting of piers and girders, construction of the ramp work at Marine Drive, and tunneling work are in progress at present.
In December last year, BMC announced that its original aim of finishing the coastal road project by October 2022 had been extended to July 2023.
Nighot had then said that we have wasted eight months due to the court case, that had stayed the project construction in 2019, and additional six months due to the lockdown.
The coastal road will join Nariman Point to Bandra Worli Sea Link, which is 10.58 km long. Twin tunnels of a length of 2.07 km will join Girgaum Chowpatty and Malabar Hill. All underground tunnels will have three lanes of depth 70 m. The coastal road project will cost Rs 8,429 crore.
55% of the work should be accomplished by this December, and 85% of the work should be done by 2022 as per the civic body plan.
Image Source
Also read: Mumbai鈥檚 coastal road project: BMC completes 330 m of tunnelling work
Also read: India鈥檚 biggest TBM begins tunnelling for Mumbai coastal road
Next Story
3i Infotech Reports Rs 7.25 Bn Revenue for FY25
3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..
Next Story
Emerald Finance Joins Baya PTE to Boost SME Bill Discounting
Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..
Next Story
BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25
BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..