Nehru bridge in Ahmedabad to be hydraulically lifted
18 Mar 2021
2 Min Read
Editorial Team
The 61-year old Nehru bridge over the Sabarmati river in Ahmedabad, weighing approximately 2,500 tonne is being closed for repair work and will be lifted by 50 mm using 20-odd hydraulic jacks.
Once raised, engineers will replace 126 of the 144 rocker-cum-roller bearings of the bridge with specialised elastomeric bearings. The various expansion joints of the bridge will also be replaced using the latest engineering techniques.
Process involved in lifting the bridge:
Hydraulic jacks would be inserted in the space between the girder (carriageway or slab) and the bridge's pillar. The girder is attached to the pillar by a system of end bearings.
Hydraulic jacks would then lift the slab with equal pressure on all sides so that the slab does not break or tilt while being lifted from the pier (pillar).
Engineers would then reach up to the pillars to replace the old bearings with the one-metre bearing. The girder would then be installed back in position by a uniform hydraulic retraction technique.
This is a rare instance of such intricate operations being carried out. The repair work will be completed within 45 days.
The bridge, which has been closed for repair work for a 45 day period, is already heavily affecting traffic around the area. Long traffic snarls can already be witnessed on Sardar Bridge, Gandhi Bridge and Ellis Bridge, three important connections to the city's nodal transport hub, agri-trading hubs and wholesale markets.
According to the Ahmedabad municipal corporation, the average traffic on the two bridges鈥擲ardar Bridge and Ellis Bridge is estimated to be around 8,000 to 9,000 passenger cars per hour in the last few days.
The Nehru Bridge's foundation was laid in 1956 by the Chief Minister of Bombay province, Morarji Desai. Back then, the estimated cost of the bridge was Rs 50 lakh.
The 61-year old Nehru bridge over the Sabarmati river in Ahmedabad, weighing approximately 2,500 tonne is being closed for repair work and will be lifted by 50 mm using 20-odd hydraulic jacks.
Once raised, engineers will replace 126 of the 144 rocker-cum-roller bearings of the bridge with specialised elastomeric bearings. The various expansion joints of the bridge will also be replaced using the latest engineering techniques.
Process involved in lifting the bridge:
Hydraulic jacks would be inserted in the space between the girder (carriageway or slab) and the bridge's pillar. The girder is attached to the pillar by a system of end bearings.
Hydraulic jacks would then lift the slab with equal pressure on all sides so that the slab does not break or tilt while being lifted from the pier (pillar).
Engineers would then reach up to the pillars to replace the old bearings with the one-metre bearing. The girder would then be installed back in position by a uniform hydraulic retraction technique.
This is a rare instance of such intricate operations being carried out. The repair work will be completed within 45 days.
The bridge, which has been closed for repair work for a 45 day period, is already heavily affecting traffic around the area. Long traffic snarls can already be witnessed on Sardar Bridge, Gandhi Bridge and Ellis Bridge, three important connections to the city's nodal transport hub, agri-trading hubs and wholesale markets.
According to the Ahmedabad municipal corporation, the average traffic on the two bridges鈥擲ardar Bridge and Ellis Bridge is estimated to be around 8,000 to 9,000 passenger cars per hour in the last few days.
The Nehru Bridge's foundation was laid in 1956 by the Chief Minister of Bombay province, Morarji Desai. Back then, the estimated cost of the bridge was Rs 50 lakh.
Image Source
Next Story
unWOOD transforms plastic waste into durable wood alternative
unWOOD, a breakthrough innovation, is converting hard-to-recycle plastic waste into a durable alternative to natural wood. Developed through a proprietary process called Intelligent Compounding, unWOOD uses a Macro Molecular Fiber Matrix (MMFM) structure to replicate the strength, look, and feel of hardwood鈥攚ithout the environmental cost.Conceptualised by Dr Babu Padmanabhan, the material addresses key flaws in traditional plastic recycling by consuming minimal energy, using zero water, and generating no microplastics. 鈥淎ny application that introduces plastics into areas where it cannot be..
Next Story
H盲fele launches Matrix undermount runners range
H盲fele has introduced its new Matrix range of undermount runners, designed to enhance drawer motion across kitchens, wardrobes, bathroom units, and more.Available in four weight capacities and a wide range of lengths, the Matrix undermount runners support diverse drawer designs. The 40 kg and 60 kg variants feature synchronised technology for superior motion and drawer stability. All runners come with an integrated soft-close mechanism to ensure smooth and noiseless operation.This in-house range is ideal for kitchen cabinets, bed storage units, living room furniture and bathroom drawers, offe..
Next Story
India's first AI-integrated campus announced in Noida
Yashoda Hospital and Bhutani Infra have announced plans to develop India鈥檚 first fully AI-integrated mixed-use campus in Greater Noida West. The upcoming project will feature a hospital, retail spaces, offices, SOHOs, serviced apartments, and a hotel鈥攁ll operating within a self-learning, generative AI-powered ecosystem.The AI-first campus will integrate real-time data systems, predictive analytics, and adaptive infrastructure to offer personalised experiences across functions. From AI-enabled footfall tracking and dynamic energy optimisation to smart F&B and retail insights, the develo..