Pune ring road project nears completion
ROADS & HIGHWAYS

Pune ring road project nears completion

The Pune Metropolitan Region Development Authority (PMRDA) is making significant progress in the development of Pune's infrastructure with the nearing completion of the comprehensive project report for the ring road. This marks a major milestone in the city's infrastructure development.

The proposed ring road has a total length of 128 kilometers and will feature fifteen flyovers, two railway flyovers, and five tunnels. PMRDA has submitted land acquisition proposals for the initial five-kilometer stretch between Solu, Nirgudi, and Vadgaon Shinde near Lohegaon to the district administration, indicating progress in the first phase of the project.

Ramdas Jagtap, the Public Relations Officer and Deputy Collector of PMRDA, stated that the detailed project report (DPR) for the ring road is in its final stage. He mentioned that the initial phase will prioritise the five-kilometer stretch between Solu and Vadgaon Shinde, and land acquisition proposals for this segment have been submitted to the district administration. The revised cost of the ring road has also been recently approved.

However, the land acquisition process is expected to face challenges, particularly due to existing constructions along the proposed route. These obstacles, along with other factors, may lead to an increase in project costs. PMRDA acknowledges the opposition to the ring road and the government's reluctance to provide funding.

The presence of the existing 'MSRDC' ring road, located approximately 15 kilometers away from the proposed ring road and spanning 110 meters in width, has led to a decision to reduce the width of the new road.

PMRDA has obtained state government approval to construct a 65-meter wide ring road and has appointed a consulting company to prepare the project report. The survey work and report preparation are now in the final stages, according to PMRDA.

Key aspects of the proposed ring road include:
- Eight phases of construction
- Fifteen flyovers, two railway flyovers, and five tunnels
- Total length of 128 kilometers, with PMRDA responsible for approximately 88 kilometers and the remaining 40 kilometers falling under MSRDC's jurisdiction
- The Municipal Corporation will oversee the construction of the 5.70-kilometer stretch passing through its jurisdiction.

The first phase of development will focus on the five-kilometer stretch between Solu and Vadgaon Shinde. Land acquisition proposals for this segment have been prepared and forwarded to the District Collector for approval. PMRDA intends to promptly initiate the land acquisition process for this area.

The recent approval of PMRDA's budget by the Maharashtra state government also includes the endorsement of the ring road improvement expenditure, totaling around Rs 140 billion. A significant portion of this budget, approximately Rs 58 billion, is expected to be allocated for land acquisition.

The Pune Metropolitan Region Development Authority (PMRDA) is making significant progress in the development of Pune's infrastructure with the nearing completion of the comprehensive project report for the ring road. This marks a major milestone in the city's infrastructure development. The proposed ring road has a total length of 128 kilometers and will feature fifteen flyovers, two railway flyovers, and five tunnels. PMRDA has submitted land acquisition proposals for the initial five-kilometer stretch between Solu, Nirgudi, and Vadgaon Shinde near Lohegaon to the district administration, indicating progress in the first phase of the project. Ramdas Jagtap, the Public Relations Officer and Deputy Collector of PMRDA, stated that the detailed project report (DPR) for the ring road is in its final stage. He mentioned that the initial phase will prioritise the five-kilometer stretch between Solu and Vadgaon Shinde, and land acquisition proposals for this segment have been submitted to the district administration. The revised cost of the ring road has also been recently approved. However, the land acquisition process is expected to face challenges, particularly due to existing constructions along the proposed route. These obstacles, along with other factors, may lead to an increase in project costs. PMRDA acknowledges the opposition to the ring road and the government's reluctance to provide funding. The presence of the existing 'MSRDC' ring road, located approximately 15 kilometers away from the proposed ring road and spanning 110 meters in width, has led to a decision to reduce the width of the new road. PMRDA has obtained state government approval to construct a 65-meter wide ring road and has appointed a consulting company to prepare the project report. The survey work and report preparation are now in the final stages, according to PMRDA. Key aspects of the proposed ring road include: - Eight phases of construction - Fifteen flyovers, two railway flyovers, and five tunnels - Total length of 128 kilometers, with PMRDA responsible for approximately 88 kilometers and the remaining 40 kilometers falling under MSRDC's jurisdiction - The Municipal Corporation will oversee the construction of the 5.70-kilometer stretch passing through its jurisdiction. The first phase of development will focus on the five-kilometer stretch between Solu and Vadgaon Shinde. Land acquisition proposals for this segment have been prepared and forwarded to the District Collector for approval. PMRDA intends to promptly initiate the land acquisition process for this area. The recent approval of PMRDA's budget by the Maharashtra state government also includes the endorsement of the ring road improvement expenditure, totaling around Rs 140 billion. A significant portion of this budget, approximately Rs 58 billion, is expected to be allocated for land acquisition.

Next Story
Infrastructure Urban

ClickPost Launches Atlas to Benchmark E-commerce Logistics

ClickPost, a leading logistics intelligence platform, has launched Atlas, a subscription-based benchmarking tool designed to transform how e-commerce brands strategise logistics. Powered by ClickPost鈥檚 proprietary network, which processes over 50 million shipments each month, Atlas enables brands to benchmark key operational metrics in real time against industry peers and standards.Unlike traditional dashboards, Atlas delivers comparative insights鈥攆rom fulfilment speeds, RTO rates and average order values to city-level delivery times and sales data鈥攁llowing brands to identify operational..

Next Story
Real Estate

Kalyani Launches Two New LivingTree Towers in Bengaluru

Bengaluru-based Kalyani Developers has announced the launch of Towers 3 and 4 at its flagship residential project, Kalyani LivingTree, located in KIADB Aerospace Park. The expansion adds 525 premium 3BHK apartments, ranging from 1300 to 1600 sq ft, and over 7.5 lakh sq ft of built-up area. Prices start from Rs 1.2 crore.These towers, the most exclusive in Phase 1, offer uninterrupted pool and landscape views, and access to over 60 lifestyle amenities, two clubhouses totalling 1 lakh sq ft, and more than 80 per cent open space.LivingTree spans 25 acres and will comprise ten towers of 23鈥�24 fl..

Next Story
Infrastructure Urban

Blue Water Logistics IPO opens May 27

Hyderabad-based Blue Water Logistics is launching its Rs 40.5 crore IPO on May 27, 2025, which will remain open for subscription until May 29. The price band has been set at Rs 132 to Rs 135 per share, with a lot size of 1,000 shares. This is a book-built issue entirely comprising a fresh issue of 30 lakh equity shares. The IPO will be listed on the NSE Emerge platform.Smart Horizon Capital Advisors is the sole book-running lead manager, while Maashitla Securities will act as the registrar. The anchor book will open on May 26, 2025. The IPO allocates 8,35,000 shares to anchor investors, 1,56,0..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement