Aizawl to come under railway map within 9 months
RAILWAYS & METRO RAIL

Aizawl to come under railway map within 9 months

Mizoram's Aizawl will be the fourth capital city in the Northeast to come under railway link within the next nine months as the Northeast Frontier Railway (NFR) is laying the new 51.38 km Broad Gauge track up to Sairang, top officials said on Sunday. A senior Mizoram government official said that NFR General Manager Arun Kumar Chaudhary, during a meeting with state Chief Minister Lalduhoma, informed that the 51.38 km new line between Bhairabi (near Assam's Hailakandi District) and Sairang (near Aizawl) expected to be completed by July next year.

The Rs 82.13 billion Bairabi-Sairang railway project is now in advanced stage, a senior NFR official said. Assam's main city of Guwahati (adjoining capital Dispur), Tripura's capital Agartala, and Arunachal Pradesh's Naharlagun (adjacent to capital city Itanagar) are already on the railway network since many years. NFR's Chief Public Relations Officer (CPRO) Kapinjal Kishore Sharma said that the whole Bairabi-Sairang project, once completed, would be a game-changer venture in terms of communication and commerce for the people of Mizoram. The economic and environment-friendly railway services would have a positive impact on almost all development works in the state, he said.

"Over 93 % of the physical works of the Bairabi-Sairang railway project are complete. There are four stations in the 51.38 km route -- Hortoki, Kawnpui, Mualkhang, and Sairang," the CPRO told IANS.

The Bairabi and Sairang railway project is divided into four sections -- Bairabi-Hortoki, Hortoki-Kawnpui, Kawnpui-Mualkhang, and Mualkhang-Sairang. Sharma said that Bhairabi-Hortoki section, which is 17.38 km long, has been completed and was commissioned in July, and train service is operational from August.

The railway project involves 48 tunnels in tough terrains. Of the total length of 12,853 metres tunnels, 12, 807 metres tunneling works have already been completed. The project will have a total 55 major bridges and 87 minor bridges. The work of construction of the tallest pier of the project in the approach of Sairang station has also been completed.

The height of this pier is 104 meters -- 42 meters taller than the Qutub Minar. The project also includes five Road Over Bridges and six Road Under Bridges. The NFR spokesman said that there are many challenges in the execution of this project like very less working seasons due to very heavy and prolonged (more than five months) monsoons, very tough and mountainous terrain through deep forests, poor accessibility, non-availability of construction materials and skilled workers in Mizoram.

However, the NFR is making all-out efforts for fulfilling its commitment towards early completion of the project, Sharma said. The senior Mizoram government official said that the Bairabi-Sairang railway project being a 'National Project' of importance, once completed, would not just be an asset for Mizoram but would be an economic asset for the nation.

He said that the new railway line from Bairabi to Sairang was approved by the Union government in 2008-2009 at an initial cost of Rs 23.84 billion as a national project. Work on the project commenced in 2015. In a setback, at least 24 workers, mostly from West Bengal, were killed and several injured after an under-construction railway bridge of the Bairabi-Sairang railway project collapsed on August 23 last year. The railway bridge was under construction over the Kurung river.

Mizoram's Aizawl will be the fourth capital city in the Northeast to come under railway link within the next nine months as the Northeast Frontier Railway (NFR) is laying the new 51.38 km Broad Gauge track up to Sairang, top officials said on Sunday. A senior Mizoram government official said that NFR General Manager Arun Kumar Chaudhary, during a meeting with state Chief Minister Lalduhoma, informed that the 51.38 km new line between Bhairabi (near Assam's Hailakandi District) and Sairang (near Aizawl) expected to be completed by July next year. The Rs 82.13 billion Bairabi-Sairang railway project is now in advanced stage, a senior NFR official said. Assam's main city of Guwahati (adjoining capital Dispur), Tripura's capital Agartala, and Arunachal Pradesh's Naharlagun (adjacent to capital city Itanagar) are already on the railway network since many years. NFR's Chief Public Relations Officer (CPRO) Kapinjal Kishore Sharma said that the whole Bairabi-Sairang project, once completed, would be a game-changer venture in terms of communication and commerce for the people of Mizoram. The economic and environment-friendly railway services would have a positive impact on almost all development works in the state, he said. Over 93 % of the physical works of the Bairabi-Sairang railway project are complete. There are four stations in the 51.38 km route -- Hortoki, Kawnpui, Mualkhang, and Sairang, the CPRO told IANS. The Bairabi and Sairang railway project is divided into four sections -- Bairabi-Hortoki, Hortoki-Kawnpui, Kawnpui-Mualkhang, and Mualkhang-Sairang. Sharma said that Bhairabi-Hortoki section, which is 17.38 km long, has been completed and was commissioned in July, and train service is operational from August. The railway project involves 48 tunnels in tough terrains. Of the total length of 12,853 metres tunnels, 12, 807 metres tunneling works have already been completed. The project will have a total 55 major bridges and 87 minor bridges. The work of construction of the tallest pier of the project in the approach of Sairang station has also been completed. The height of this pier is 104 meters -- 42 meters taller than the Qutub Minar. The project also includes five Road Over Bridges and six Road Under Bridges. The NFR spokesman said that there are many challenges in the execution of this project like very less working seasons due to very heavy and prolonged (more than five months) monsoons, very tough and mountainous terrain through deep forests, poor accessibility, non-availability of construction materials and skilled workers in Mizoram. However, the NFR is making all-out efforts for fulfilling its commitment towards early completion of the project, Sharma said. The senior Mizoram government official said that the Bairabi-Sairang railway project being a 'National Project' of importance, once completed, would not just be an asset for Mizoram but would be an economic asset for the nation. He said that the new railway line from Bairabi to Sairang was approved by the Union government in 2008-2009 at an initial cost of Rs 23.84 billion as a national project. Work on the project commenced in 2015. In a setback, at least 24 workers, mostly from West Bengal, were killed and several injured after an under-construction railway bridge of the Bairabi-Sairang railway project collapsed on August 23 last year. The railway bridge was under construction over the Kurung river.

Next Story
Infrastructure Urban

Innova Captab Reports Rs 12,437 Mn Revenue in FY25

Innova Captab Limited announced financial results for the quarter and fiscal year ended 31 March 2025. The company reported Q4 FY25 revenue from operations of Rs 3,147 million, reflecting 20 per cent year-on-year growth. Profit after tax stood at Rs 296 million, a 3 per cent increase.For the full year, revenue grew 15 per cent to Rs 12,437 million, led by volume growth across business segments. EBITDA rose 19 per cent to Rs 1,982 million, with margins improving to 15.9 per cent. Profit after tax increased 36 per cent to Rs 1,283 million.Managing Director Vinay Lohariwala highlighted the commis..

Next Story
Infrastructure Urban

Redington Reports Rs 995,620 Mn Revenue in FY25

Redington Limited announced its financial results for the quarter and fiscal year ended 31 March 2025. The company reported Q4 FY25 consolidated revenues of Rs 265,100 million, an 18 per cent increase year-on-year, with net profit rising 23 per cent to Rs 4,000 million, excluding one-time divestment gains.For the full fiscal year, Redington recorded record consolidated revenues of Rs 995,620 million, up 11 per cent compared to the previous year. Consolidated profit after tax grew 10 per cent excluding divestment gains, reflecting sustained profitability.Broad-based growth was driven by Indiaâ€..

Next Story
Infrastructure Urban

SKF India Reports Rs 49,199 Mn Revenue in FY25

SKF India Limited announced its unaudited financial results for the fourth quarter and audited financials for the fiscal year ending 31 March 2025. Consolidated revenue from operations for FY25 stood at Rs 49,199 million, an increase of 8 per cent over Rs 45,701 million in the previous year.Profit before tax (PBT) rose 4 per cent year-on-year to Rs 7,632 million. For Q4 FY25, consolidated revenue was Rs 12,134 million, reflecting a 1 per cent growth compared to the same quarter last year. PBT for the quarter increased 20 per cent to Rs 2,757 million.SKF India’s performance was driven by stro..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement