Bengaluru鈥檚 Pink Line 95% Complete
RAILWAYS & METRO RAIL

Bengaluru鈥檚 Pink Line 95% Complete

Bengaluru Metro Rail Corporation Limited (BMRCL) has announced that 95% of the tunneling work for the Pink Line of Namma Metro is complete, with the 21-km stretch expected to be operational by 2026. The corridor runs from Kalena Agrahara in South Bengaluru to Nagawara in the North, including a 13.8-km underground section from Dairy Circle to Nagawara.

BMRCL Chief Engineer (Underground), Subrahmanya Gudge, highlighted that the Pink Line stations will generally have only two entries, except MG Road Metro station, which will feature four to prevent road crossings. He also emphasized how lessons from Phase 1 streamlined tunneling in Phase 2. 鈥淯nlike the earlier phase, which involved international experts from Germany, Japan, and Thailand, the current phase relied entirely on BMRCL鈥檚 in-house team and Indian expertise,鈥� he said.

Construction for the Pink Line began in August 2020 at Cantonment underground station with a tunnel boring machine (TBM). Over time, eight additional TBMs were deployed, culminating in the final breakthrough at Nagawara on October 30, 2024.

The next phase of work will focus on systems including traction, signaling, telecommunication, electrical infrastructure, tunnel ventilation, air-conditioning, and signage. For the first time in Bengaluru Metro, underground stations on the Pink Line will feature platform screen doors. Trains on the stretch will operate at a maximum speed of 80 kmph, with stations spanning 200 meters.

In comparison, Phase 1 of Bengaluru Metro involved 10 km of tunnels with seven underground stations, including the Majestic interchange, and took over five years to complete with six TBMs.

Bengaluru Metro Rail Corporation Limited (BMRCL) has announced that 95% of the tunneling work for the Pink Line of Namma Metro is complete, with the 21-km stretch expected to be operational by 2026. The corridor runs from Kalena Agrahara in South Bengaluru to Nagawara in the North, including a 13.8-km underground section from Dairy Circle to Nagawara. BMRCL Chief Engineer (Underground), Subrahmanya Gudge, highlighted that the Pink Line stations will generally have only two entries, except MG Road Metro station, which will feature four to prevent road crossings. He also emphasized how lessons from Phase 1 streamlined tunneling in Phase 2. 鈥淯nlike the earlier phase, which involved international experts from Germany, Japan, and Thailand, the current phase relied entirely on BMRCL鈥檚 in-house team and Indian expertise,鈥� he said. Construction for the Pink Line began in August 2020 at Cantonment underground station with a tunnel boring machine (TBM). Over time, eight additional TBMs were deployed, culminating in the final breakthrough at Nagawara on October 30, 2024. The next phase of work will focus on systems including traction, signaling, telecommunication, electrical infrastructure, tunnel ventilation, air-conditioning, and signage. For the first time in Bengaluru Metro, underground stations on the Pink Line will feature platform screen doors. Trains on the stretch will operate at a maximum speed of 80 kmph, with stations spanning 200 meters. In comparison, Phase 1 of Bengaluru Metro involved 10 km of tunnels with seven underground stations, including the Majestic interchange, and took over five years to complete with six TBMs.

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train Set to Launch by 2028

India鈥檚 first bullet train is set to revolutionize high-speed travel along the western corridor, with the Mumbai-Ahmedabad high-speed rail project aiming for a 2028 launch. This announcement marks a major milestone in India鈥檚 infrastructure goals, as it promises to reduce travel time between the two economic hubs from eight hours to just three.Spanning a planned 508-kilometre stretch, the corridor stands as a flagship example of Indo-Japanese collaboration in technology and engineering. Once operational, the train is expected to transform intercity mobility and place India among the select..

Next Story
Infrastructure Transport

Mumbai-Gandhinagar Train Service Enhances Passenger Capacity

The Mumbai Central鈥揋andhinagar Capital Vande Bharat Express has increased its passenger capacity by adding four additional AC chair car coaches to meet the growing commuter demand on one of India鈥檚 busiest business corridors. This upgrade, effective from 11 May, raised the train鈥檚 seating capacity from 1,128 to 1,440 passengers, allowing it to serve 936 more passengers daily in both directions. The increase was described as a practical measure to accommodate the surging demand on the busy Mumbai鈥揂hmedabad鈥揋andhinagar route, which regularly operates at over 150 percent seat occupancy...

Next Story
Infrastructure Urban

Delhi Plans 12 Sewage Plants to Clean Najafgarh Drain Efficiently

Delhi鈥檚 ambitious plan to improve the water quality of the Yamuna River has gained significant momentum as the Delhi Jal Board (DJB) has begun work on 12 new sewage treatment plants (STPs) aimed at reducing the volume of untreated sewage being discharged from the Najafgarh Drain.This initiative forms part of the ongoing efforts to clean the Yamuna and restore the river鈥檚 health, which has long been a critical environmental issue for the national capital. Given the alarming pollution levels in the Yamuna, experts and officials consider this project a vital step toward addressing the persist..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement