BMRCL launches first U-girder on Outer Ring Road
RAILWAYS & METRO RAIL

BMRCL launches first U-girder on Outer Ring Road

The Namma Metro's first U-girder was installed at Doddanekundi on Outer Ring Road (ORR) early on Sunday morning.

Bangalore Metro Rail Corporation Limited (BMRCL), along with contractor Shankaranarayana Constructions (SNC), began work on erecting the U-girder near Bagmane World Technology Centre in Doddanekundi on ORR. The first U-girder was established on top of pillars between 473 and 474 at about 4 am.

The U-girder was transported on a 43 m long trailer to the pier area from Lowry Junction close to KR Puram at 2.25 am. Traffic police had barricaded the road area to enable the work.

Each U-girder is 4.6 m wide, 28 m long, and weighs 165 metric tonnes (mt). It is lifted and installed with two hydraulic cranes, one with a capacity of 700 mt and another with 400 mt.

This is the first time U-girders are being utilised in Bengaluru to speed up the metro construction work.

BMRCL decided to employ U-girders for building the viaduct on Silk Board-KR Puram (19.5 km) on Outer Ring Road and KR Puram-Kempegowda International Airport (36 km) areas.

The U-girders will be used for nearly 80% of the corridor's length in the ORR-KIA route. The U-girders will involve casting the whole span of a viaduct between two piers in a single piece, whereas box-girders will have many parts between two piers. One U-girder between two pillars can be erected overnight, against 5-6 days needed in case of box girders.

Experts said U-girders would also save time as well as lower construction expenses. The much longer U-girders drastically decrease construction time. However, due to their length, they need absolute precision during construction. Also, their length makes ferrying them from the casting yard to the location a difficult task.


Also read: RITES submits DPR for Namma Metro's phase 3 corridors to BMRCL

The Namma Metro's first U-girder was installed at Doddanekundi on Outer Ring Road (ORR) early on Sunday morning. Bangalore Metro Rail Corporation Limited (BMRCL), along with contractor Shankaranarayana Constructions (SNC), began work on erecting the U-girder near Bagmane World Technology Centre in Doddanekundi on ORR. The first U-girder was established on top of pillars between 473 and 474 at about 4 am. The U-girder was transported on a 43 m long trailer to the pier area from Lowry Junction close to KR Puram at 2.25 am. Traffic police had barricaded the road area to enable the work. Each U-girder is 4.6 m wide, 28 m long, and weighs 165 metric tonnes (mt). It is lifted and installed with two hydraulic cranes, one with a capacity of 700 mt and another with 400 mt. This is the first time U-girders are being utilised in Bengaluru to speed up the metro construction work. BMRCL decided to employ U-girders for building the viaduct on Silk Board-KR Puram (19.5 km) on Outer Ring Road and KR Puram-Kempegowda International Airport (36 km) areas. The U-girders will be used for nearly 80% of the corridor's length in the ORR-KIA route. The U-girders will involve casting the whole span of a viaduct between two piers in a single piece, whereas box-girders will have many parts between two piers. One U-girder between two pillars can be erected overnight, against 5-6 days needed in case of box girders. Experts said U-girders would also save time as well as lower construction expenses. The much longer U-girders drastically decrease construction time. However, due to their length, they need absolute precision during construction. Also, their length makes ferrying them from the casting yard to the location a difficult task. Image Source Also read: RITES submits DPR for Namma Metro's phase 3 corridors to BMRCL

Next Story
Infrastructure Urban

3i Infotech Reports Rs 7.25 Bn Revenue for FY25

3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..

Next Story
Infrastructure Urban

Emerald Finance Joins Baya PTE to Boost SME Bill Discounting

Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..

Next Story
Infrastructure Urban

BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25

BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement