Central Railway to Replace 126 km of Tracks in Mumbai by April
RAILWAYS & METRO RAIL

Central Railway to Replace 126 km of Tracks in Mumbai by April

Central Railway has made notable progress on its track replacement initiative in Mumbai, having completed 65 km of new tracks since April 2024. Senior railway officials have emphasised that this replacement project is vital due to the aging condition of the tracks and the adverse effects of Mumbai's coastal, humid climate, which accelerates wear and tear. The goal is to replace a total of 126 km of tracks by April 2025.

The replacement work covers key sections in the Mumbai division, including Chhatrapati Shivaji Maharaj Terminus (CSMT) to Kalyan, Kalyan to Lonavala, Kalyan to Igatpuri, and Panvel. These areas are crucial for daily operations, supporting 1,810 local trains and around 250 to 300 mail and express trains.

Track replacement is conducted in short intervals called 鈥渂locks,鈥� lasting several hours, during which 200 to 600 meters of tracks are replaced. The process involves a team of 30 railway officials from various departments, using specialised machinery to remove the old rails and install new ones. The new rails are welded and aligned to meet the necessary operational standards. Maintenance and replacement follow the tracks' lifecycle to ensure safety and reliability.

(Indian Express)

Central Railway has made notable progress on its track replacement initiative in Mumbai, having completed 65 km of new tracks since April 2024. Senior railway officials have emphasised that this replacement project is vital due to the aging condition of the tracks and the adverse effects of Mumbai's coastal, humid climate, which accelerates wear and tear. The goal is to replace a total of 126 km of tracks by April 2025. The replacement work covers key sections in the Mumbai division, including Chhatrapati Shivaji Maharaj Terminus (CSMT) to Kalyan, Kalyan to Lonavala, Kalyan to Igatpuri, and Panvel. These areas are crucial for daily operations, supporting 1,810 local trains and around 250 to 300 mail and express trains. Track replacement is conducted in short intervals called 鈥渂locks,鈥� lasting several hours, during which 200 to 600 meters of tracks are replaced. The process involves a team of 30 railway officials from various departments, using specialised machinery to remove the old rails and install new ones. The new rails are welded and aligned to meet the necessary operational standards. Maintenance and replacement follow the tracks' lifecycle to ensure safety and reliability. (Indian Express)

Next Story
Infrastructure Energy

GAIL to Operate Dabhol LNG Terminal Year-Round, Plans Expansion

GAIL (India) will operate its Dabhol liquefied natural gas (LNG) terminal in Ratnagiri, Maharashtra, through the monsoon season for the first time, following the completion of a breakwater facility. The five million tonne per year terminal was earlier shut from May 25 for nearly four months due to high tides.The breakwater allows year-round ship access, improving operational flexibility. GAIL has applied for all weather terminal status and expects authorisation soon, which would enable uninterrupted LNG cargo scheduling.Chairman Sandeep Kumar Gupta confirmed the new development and highlighted..

Next Story
Infrastructure Energy

PNG Network Expanded to 111 More Delhi Villages by L-G and CM

The Delhi government has extended its Piped Natural Gas (PNG) network to an additional one hundred eleven villages, taking the total to two hundred forty-one. The initiative was inaugurated by Lieutenant Governor Vinai Kumar Saxena and Chief Minister Rekha Gupta, reflecting a joint vision for inclusive and sustainable energy access.Implemented by Indraprastha Gas Limited (IGL), the expansion nears completion of the city's rural gas connectivity mission. Phase I had covered one hundred thirty villages, and the remaining one hundred sixteen are expected to be connected by year-end.A new CNG stat..

Next Story
Real Estate

Lucknow to Launch Rs 33 Billion Housing and Commercial Projects

The Lucknow Development Authority (LDA) has announced two major infrastructure projects valued at nearly Rs 33 billion, aimed at reshaping the city鈥檚 urban landscape. The initiatives include river view residential apartments and a landmark hotel-commercial complex.The housing project will feature around four thousand apartments across fifty-one acres behind the Police Headquarters on Shaheed Path. Located in Maleshemau village, it will offer one to four BHK flats and penthouses, with units reserved for economically weaker sections and lower-income groups. Amenities will include a swimming po..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement