Chennai Metro鈥檚 first driverless train set to arrive in October
27 Sep 2024
2 Min Read
CW Team
Chennai Metro Rail's inaugural driverless train, part of the ambitious Rs 632.46 billion Phase II project, has been completed and is scheduled to arrive at the Poonamallee depot by mid-October.
The manufacturing contract for these driverless trains was awarded for Rs 11.25 billion. Production began seven months ago at Sri City, initially aiming for an August delivery. However, delays in component procurement pushed the timeline back, with the train now expected to reach Chennai by the end of October.
According to officials from Chennai Metro Rail Limited (CMRL), while manufacturing is complete, the train must undergo a series of tests before transportation to the Poonamallee depot. The first test, known as 'static testing', will take place at the Sri City facility to ensure all systems are operational prior to moving the train.
"We don鈥檛 anticipate any further delays, and the train should arrive next month. After its arrival, we will begin the testing process immediately," stated a CMRL official. He emphasised that this slight delay will not affect the overall progress of Phase II, as inspections and tests are planned to be completed within the next five months, coinciding with ongoing viaduct work between Poonamallee and Porur, according to The Hindu.
The driverless train will first be tested on the Poonamallee-Porur stretch, part of Corridor 4 under Phase II of the Chennai Metro project. Testing will commence once the viaduct construction is completed, expected within the same five-month timeframe. Upon successful testing, the train is projected to begin operations along this corridor by late next year.
"Once the viaduct between Poonamallee and Porur is ready, we will initiate trials along the stretch. These trials will ensure the smooth functioning of the driverless train before it is rolled out for public use," the official added.
The arrival of the train's coaches will be followed by comprehensive testing procedures. Coaches will be assembled and various systems will undergo thorough checks, including the passenger information system, pantograph, brakes, heating, ventilation, air-conditioning systems, and the Train Control Management System.
Equipped with advanced safety features and state-of-the-art technology, these fully automated trains are expected to operate more efficiently than their predecessors, providing a smoother and faster travel experience for Chennai residents.
(Swarajya Mag)
Chennai Metro Rail's inaugural driverless train, part of the ambitious Rs 632.46 billion Phase II project, has been completed and is scheduled to arrive at the Poonamallee depot by mid-October.
The manufacturing contract for these driverless trains was awarded for Rs 11.25 billion. Production began seven months ago at Sri City, initially aiming for an August delivery. However, delays in component procurement pushed the timeline back, with the train now expected to reach Chennai by the end of October.
According to officials from Chennai Metro Rail Limited (CMRL), while manufacturing is complete, the train must undergo a series of tests before transportation to the Poonamallee depot. The first test, known as 'static testing', will take place at the Sri City facility to ensure all systems are operational prior to moving the train.
We don鈥檛 anticipate any further delays, and the train should arrive next month. After its arrival, we will begin the testing process immediately, stated a CMRL official. He emphasised that this slight delay will not affect the overall progress of Phase II, as inspections and tests are planned to be completed within the next five months, coinciding with ongoing viaduct work between Poonamallee and Porur, according to The Hindu.
The driverless train will first be tested on the Poonamallee-Porur stretch, part of Corridor 4 under Phase II of the Chennai Metro project. Testing will commence once the viaduct construction is completed, expected within the same five-month timeframe. Upon successful testing, the train is projected to begin operations along this corridor by late next year.
Once the viaduct between Poonamallee and Porur is ready, we will initiate trials along the stretch. These trials will ensure the smooth functioning of the driverless train before it is rolled out for public use, the official added.
The arrival of the train's coaches will be followed by comprehensive testing procedures. Coaches will be assembled and various systems will undergo thorough checks, including the passenger information system, pantograph, brakes, heating, ventilation, air-conditioning systems, and the Train Control Management System.
Equipped with advanced safety features and state-of-the-art technology, these fully automated trains are expected to operate more efficiently than their predecessors, providing a smoother and faster travel experience for Chennai residents.
(Swarajya Mag)
Next Story
3i Infotech Reports Rs 7.25 Bn Revenue for FY25
3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..
Next Story
Emerald Finance Joins Baya PTE to Boost SME Bill Discounting
Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..
Next Story
BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25
BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..