CMRL gets approval for beautification work of central railway station
23 Jul 2021
2 Min Read
CW Team
The Central Square project is now on track as the Chennai Metro Rail Limited (CMRL) has received Southern Railway鈥檚 nod to continue with the beautification work it had planned in front of the Moore Market Complex and Central Railway Station.
The Rs 400 crore Central Square project has almost been completed in front of Ripon Buildings. The beautification work is a part of it.
The project also includes additional passenger facilities for multi-modal integration to connect suburban trains, MRTS and metro rail with outstation buses and trains through pedestrian subways, underground parking and a 20-storey central plaza with bus bays.
Earlier this year, Southern Railway had denied permission for the beautification work in front of Central Railway Station and Moore Market Complex, indicating interference to passenger flow. It slowed down the project. But, the work planned in front of Ripon Buildings has been in full swing.
A Southern Railway official said they permitted CMRL to continue with Central Square developmental works on railway land near Chennai Central and MMC.
The official said that they communicated it to CMRL. The work will involve canopies, seating, landscaping and pergolas, pathways, etc.
Additionally, a CMRL official said that the work in front of the Ripon Buildings will be done by the end of this month.
The official said that Southern Railway gave CMRL the approval for beautifying their premises just two days back. The work planned in front of Central and MMC will need two months. They will eliminate the existing cement blocks on the surface and have new paving aside from other features.
While work for the pedestrian subways and the underground parking is underway, CMRL will shortly float a tender to look for an investor for the construction work of the multi-storied Central Plaza.
The plaza is likely to have a shopping area, hotel, office spaces, and a waiting lounge for passengers and bus crew.
The plaza will include bus bays on the front for outstation and local buses to pick up and drop off passengers.
The official said that they have planned three-level underground parking. Excavation is going on for the two levels at the bottom.
Also read: Chennai Central, Egmore station redevelopment is yet to start
The Central Square project is now on track as the Chennai Metro Rail Limited (CMRL) has received Southern Railway鈥檚 nod to continue with the beautification work it had planned in front of the Moore Market Complex and Central Railway Station.
The Rs 400 crore Central Square project has almost been completed in front of Ripon Buildings. The beautification work is a part of it.
The project also includes additional passenger facilities for multi-modal integration to connect suburban trains, MRTS and metro rail with outstation buses and trains through pedestrian subways, underground parking and a 20-storey central plaza with bus bays.
Earlier this year, Southern Railway had denied permission for the beautification work in front of Central Railway Station and Moore Market Complex, indicating interference to passenger flow. It slowed down the project. But, the work planned in front of Ripon Buildings has been in full swing.
A Southern Railway official said they permitted CMRL to continue with Central Square developmental works on railway land near Chennai Central and MMC.
The official said that they communicated it to CMRL. The work will involve canopies, seating, landscaping and pergolas, pathways, etc.
Additionally, a CMRL official said that the work in front of the Ripon Buildings will be done by the end of this month.
The official said that Southern Railway gave CMRL the approval for beautifying their premises just two days back. The work planned in front of Central and MMC will need two months. They will eliminate the existing cement blocks on the surface and have new paving aside from other features.
While work for the pedestrian subways and the underground parking is underway, CMRL will shortly float a tender to look for an investor for the construction work of the multi-storied Central Plaza.
The plaza is likely to have a shopping area, hotel, office spaces, and a waiting lounge for passengers and bus crew.
The plaza will include bus bays on the front for outstation and local buses to pick up and drop off passengers.
The official said that they have planned three-level underground parking. Excavation is going on for the two levels at the bottom.
Image Source
Also read: Chennai Central, Egmore station redevelopment is yet to start
Next Story
REC Kicks Off Swachhata Pakhwada 2025
REC, a Maharatna CPSU under the Ministry of Power and a leading NBFC, today commenced Swachhata Pakhwada 2025, a fortnight-long cleanliness and awareness campaign to be observed from 16 May to 31 May 2025, across its offices in the country. The initiative aligns with the Government of India's overarching objective to promote hygiene, sustainable practices, and public awareness across the nation.鈥� 鈥疶he event began with a solemn Swachhata Pledge, administered by Jitendra Srivastava, IAS, CMD, REC, to all employees. The CMD emphasized the importance of the Swachh Bharat Mission and highl..
Next Story
Infra.Market Becomes India鈥檚 Second-Largest Tile Maker
Infra.Market has emerged as India鈥檚 second-largest player in the ceramic tiles sector by installed capacity, with a total manufacturing capability of 81.57 million square metres. The company, a prominent name in the building materials space, operates 19 manufacturing plants and has seen a five-fold growth over the past three to four years. Backed by an investment of around Rs 1,400 crore, Infra.Market鈥檚 expansion has been powered by its multi-brand strategy and category diversification, enhancing its reach in both domestic and export markets.Currently, exports account for 25 to 30 per cent..
Next Story
FY25 Thermal Power Capacity Addition Misses Target
India added just 4.53 gigawatts (GW) of thermal power capacity in FY25, significantly below the 15.4 GW target, according to the Central Electricity Authority鈥檚 latest report. Of the planned 22 thermal units, only six were commissioned last fiscal year鈥攖wo in the central sector and four in state sectors.New units commissioned include Ghatampur TPP, Khurja SCTPP, Jawaharpur STPP, Bhusawal TPS, Panki TPS Extension, and Yadadri TPS, ranging from 660 MW to 800 MW. The commissioning of the remaining 16 units has been deferred to FY26.Delays are attributed to equipment supply issues, land acquis..