Construction of Bullet train continues in full swing
RAILWAYS & METRO RAIL

Construction of Bullet train continues in full swing

Work continues on the Mumbai-to-Ahmedabad Bullet train project. The pile work has been erected over a distance of 227.62 km, while the piers have been constructed over a distance of 126.44 km. Up until December 31, 2022, a total of 24.73 per cent of physical progress has been made, with Gujarat achieving 30.68 per cent and Maharashtra achieving 13.37 per cent. The 21.44 km of girders have been launched. At the Surat and Anand stations, 50 m rail slabs have already been cast.

The government has decided to operate Bullet trains on the 508.09 km Mumbai-Ahmedabad high speed rail corridor that connects the two financial centers in Maharashtra and Gujarat. It is most likely that the time required to complete the journey will be two hours and seven minutes. The train will make stops in Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad, and Sabarmati along the way.

Each direction is anticipated to see 17,900 passengers use the corridor each day. NHSRCL says that on the year of commissioning, the passengers will be ferried in 35 daily train trips made by 10 car configurations with 24 rakes. About 92,900 passengers are likely to use the system each day, according to NHSRCL. From 6 a.m. to midnight, passengers can board the train at intervals of 30 minutes.

It is anticipated that the bullet train will travel at 320 km per hour. At this time, the speed limit is 160 km per hour. There will be standard class, business class, and grand class on the high-speed train. Hiroshi Suzuki, Japan's Ambassador to India, went to Gujarat's Surat last month to check on the construction progress. He was happy with the ongoing development and also made an announcement regarding the developments on his Twitter account.

"The India-Japan flagship project is now making progress in full swing," Suzuki wrote on Twitter.

Work continues on the Mumbai-to-Ahmedabad Bullet train project. The pile work has been erected over a distance of 227.62 km, while the piers have been constructed over a distance of 126.44 km. Up until December 31, 2022, a total of 24.73 per cent of physical progress has been made, with Gujarat achieving 30.68 per cent and Maharashtra achieving 13.37 per cent. The 21.44 km of girders have been launched. At the Surat and Anand stations, 50 m rail slabs have already been cast. The government has decided to operate Bullet trains on the 508.09 km Mumbai-Ahmedabad high speed rail corridor that connects the two financial centers in Maharashtra and Gujarat. It is most likely that the time required to complete the journey will be two hours and seven minutes. The train will make stops in Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad, and Sabarmati along the way. Each direction is anticipated to see 17,900 passengers use the corridor each day. NHSRCL says that on the year of commissioning, the passengers will be ferried in 35 daily train trips made by 10 car configurations with 24 rakes. About 92,900 passengers are likely to use the system each day, according to NHSRCL. From 6 a.m. to midnight, passengers can board the train at intervals of 30 minutes. It is anticipated that the bullet train will travel at 320 km per hour. At this time, the speed limit is 160 km per hour. There will be standard class, business class, and grand class on the high-speed train. Hiroshi Suzuki, Japan's Ambassador to India, went to Gujarat's Surat last month to check on the construction progress. He was happy with the ongoing development and also made an announcement regarding the developments on his Twitter account. The India-Japan flagship project is now making progress in full swing, Suzuki wrote on Twitter.

Next Story
Infrastructure Urban

3i Infotech Reports Rs 7.25 Bn Revenue for FY25

3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..

Next Story
Infrastructure Urban

Emerald Finance Joins Baya PTE to Boost SME Bill Discounting

Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..

Next Story
Infrastructure Urban

BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25

BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement