Cost of Mumbai Metro 3 sees a 44% surge to Rs 231.36 bn
RAILWAYS & METRO RAIL

Cost of Mumbai Metro 3 sees a 44% surge to Rs 231.36 bn

The Eknath Shinde-Devendra Fadnavis government in Maharashtra is set to approve an increase in the cost of the Colaba-Bandra-SEEPZ Metro 3 project to Rs 334.06 billion from Rs 231.36 billion, a rise of Rs 102.70 billion, or about 44%.

The state cabinet, at its meeting slated for this week, is expected to approve the proposal.

Several reasons are being cited for the increase, including the time taken in excavation owing to the presence of basalt rock, adoption of bottom-up construction technology for want of space, additional cost incurred on account of rocky layers and the need to dispose of them, and the need to erect temporary steel decks for road traffic to allow construction of underground stations, as many of them are in congested areas.

Yet another reason for the cost escalation is that Metro 3 stations have to accommodate eight coaches as against the six used by the Delhi Metro. Moreover, labour and accommodation are more expensive in Mumbai.

The state government鈥檚 approval came days after it allowed the Mumbai Metro Rail Corporation (MMRCL) to resume work on the Metro 3 car shed at Aarey Colony in Goregaon (East).

A senior official with the state urban development department said the loan needed for the project from the Japan International Cooperation Agency (JICA) has increased by Rs 66.89 billion to Rs 199.24 billion.

The state government will have to bear an paltry additional cost of Rs 1.33 billion as its contribution has gone up to Rs 25.54 billion from Rs 24.21 billion. But its share capital in the project will have to be increased to Rs 36.99 billion from Rs 24.02 billion. This amount will come from the Mumbai Metropolitan Region Development Authority (MMRDA) and is to be used for land acquisition, rehabilitation and tax.

See also:
Kochi water metro services to start in September
NHSRCL finishes 75 km pier work of MAHSR


The Eknath Shinde-Devendra Fadnavis government in Maharashtra is set to approve an increase in the cost of the Colaba-Bandra-SEEPZ Metro 3 project to Rs 334.06 billion from Rs 231.36 billion, a rise of Rs 102.70 billion, or about 44%. The state cabinet, at its meeting slated for this week, is expected to approve the proposal. Several reasons are being cited for the increase, including the time taken in excavation owing to the presence of basalt rock, adoption of bottom-up construction technology for want of space, additional cost incurred on account of rocky layers and the need to dispose of them, and the need to erect temporary steel decks for road traffic to allow construction of underground stations, as many of them are in congested areas. Yet another reason for the cost escalation is that Metro 3 stations have to accommodate eight coaches as against the six used by the Delhi Metro. Moreover, labour and accommodation are more expensive in Mumbai. The state government鈥檚 approval came days after it allowed the Mumbai Metro Rail Corporation (MMRCL) to resume work on the Metro 3 car shed at Aarey Colony in Goregaon (East). A senior official with the state urban development department said the loan needed for the project from the Japan International Cooperation Agency (JICA) has increased by Rs 66.89 billion to Rs 199.24 billion. The state government will have to bear an paltry additional cost of Rs 1.33 billion as its contribution has gone up to Rs 25.54 billion from Rs 24.21 billion. But its share capital in the project will have to be increased to Rs 36.99 billion from Rs 24.02 billion. This amount will come from the Mumbai Metropolitan Region Development Authority (MMRDA) and is to be used for land acquisition, rehabilitation and tax.See also: Kochi water metro services to start in September NHSRCL finishes 75 km pier work of MAHSR

Next Story
Products

unWOOD transforms plastic waste into durable wood alternative

unWOOD, a breakthrough innovation, is converting hard-to-recycle plastic waste into a durable alternative to natural wood. Developed through a proprietary process called Intelligent Compounding, unWOOD uses a Macro Molecular Fiber Matrix (MMFM) structure to replicate the strength, look, and feel of hardwood鈥攚ithout the environmental cost.Conceptualised by Dr Babu Padmanabhan, the material addresses key flaws in traditional plastic recycling by consuming minimal energy, using zero water, and generating no microplastics. 鈥淎ny application that introduces plastics into areas where it cannot be..

Next Story
Real Estate

H盲fele launches Matrix undermount runners range

H盲fele has introduced its new Matrix range of undermount runners, designed to enhance drawer motion across kitchens, wardrobes, bathroom units, and more.Available in four weight capacities and a wide range of lengths, the Matrix undermount runners support diverse drawer designs. The 40 kg and 60 kg variants feature synchronised technology for superior motion and drawer stability. All runners come with an integrated soft-close mechanism to ensure smooth and noiseless operation.This in-house range is ideal for kitchen cabinets, bed storage units, living room furniture and bathroom drawers, offe..

Next Story
Real Estate

India's first AI-integrated campus announced in Noida

Yashoda Hospital and Bhutani Infra have announced plans to develop India鈥檚 first fully AI-integrated mixed-use campus in Greater Noida West. The upcoming project will feature a hospital, retail spaces, offices, SOHOs, serviced apartments, and a hotel鈥攁ll operating within a self-learning, generative AI-powered ecosystem.The AI-first campus will integrate real-time data systems, predictive analytics, and adaptive infrastructure to offer personalised experiences across functions. From AI-enabled footfall tracking and dynamic energy optimisation to smart F&B and retail insights, the develo..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement