In just 77 days, Agra Metro Rail Project reached major milestone
RAILWAYS & METRO RAIL

In just 77 days, Agra Metro Rail Project reached major milestone

The 440-meter-long tunnel connecting the planned underground Jama Masjid metro station with the Agra Fort metro station was finished by TBM Yamuna in just 77 days, making it the country's quickest progress on a metro project. This achievement marked a significant milestone for the Agra Metro Rail Project. Beginning in February 2023, tunnelling operations began on the 3 km underground stretch of the priority corridor that runs between the Taj Mahal and Jama Masjid. As part of the Agra Metro Rail Project, the tunnelling work connecting Ramlila Maidan and Agra Fort Metro Station has also been finished.

From the Ramleela Maidan crossover to the Agra Fort, the machine constructed 239 rings (334m) in 77 days. Two lines and 27 stops make up the 29.4 km long Agra Metro. The Priority Corridor's commissioning is anticipated to happen by the deadline of August 2024. By March 2024, the Uttar Pradesh Metro Rail Corporation (UPMRC) intends to provide the inhabitants of Agra with a first-rate metro system, calling it a significant accomplishment in a short period of time.

The 440-meter-long tunnel connecting the planned underground Jama Masjid metro station with the Agra Fort metro station was finished by TBM Yamuna in just 77 days, making it the country's quickest progress on a metro project. This achievement marked a significant milestone for the Agra Metro Rail Project. Beginning in February 2023, tunnelling operations began on the 3 km underground stretch of the priority corridor that runs between the Taj Mahal and Jama Masjid. As part of the Agra Metro Rail Project, the tunnelling work connecting Ramlila Maidan and Agra Fort Metro Station has also been finished. From the Ramleela Maidan crossover to the Agra Fort, the machine constructed 239 rings (334m) in 77 days. Two lines and 27 stops make up the 29.4 km long Agra Metro. The Priority Corridor's commissioning is anticipated to happen by the deadline of August 2024. By March 2024, the Uttar Pradesh Metro Rail Corporation (UPMRC) intends to provide the inhabitants of Agra with a first-rate metro system, calling it a significant accomplishment in a short period of time.

Next Story
Infrastructure Urban

3i Infotech Reports Rs 7.25 Bn Revenue for FY25

3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..

Next Story
Infrastructure Urban

Emerald Finance Joins Baya PTE to Boost SME Bill Discounting

Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..

Next Story
Infrastructure Urban

BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25

BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement