Jiribam-Imphal new line railway project completes 93% of work
05 Apr 2023
3 Min Read
CW Team
According to officials, the Jiribam-Imphal new line railway project, one of the critical connectivity projects for the North-eastern region, has made 93.30 percent progress.
"The works for this new line railway project, among other connectivity projects, is also going on in full swing to connect Imphal, the capital city of Manipur to the rest of the country. The Jiribam - Imphal project has already achieved physical progress of 93.30 per cent," Sabyasachi De, CPRO of NF Railway said.
According to the NF Railway CPRO, the Jiribam-Imphal railway project includes many tunnels and bridges in difficult terrain that spans more than 111 kilometres.
"The total length of tunnels in this project is 61.32 km out of which 59.11 km of tunnelling works have already been completed. The project will have a total of 11 major bridges and 137 minor bridges, out of which work for 05 major bridges and 101 minor bridges have been completed so far. The tallest pier railway bridge in the world with a height of 141 meters is also being constructed in this project and nearing completion," Sabyasachi De said.
Indian Railways is making a substantial contribution to the transformation of the Northeastern states by completing a number of new railway line projects.
Under capital connectivity initiatives, new railway lines are being built to connect all of the state capitals in the northeastern region.
The Jiribam-Imphal new line railway project, for example, is one of the critical connectivity projects for the Northeastern region that is nearing completion.
He further stated that the portion from Jiribam to Khongsang has already been opened to rail traffic.
"After completion of the entire project, the present road journey time of about 10 hours to reach Imphal from Jiribam will get reduced to 2.5 hours by railways. NF Railway is putting their full effort by working 24X7 for the completion of this project with all the challenges like heavy rainfall and other logistic hindrances. The new rail project will provide enhanced connectivity to the people of Manipur, help grow small-scale industries in the area and boost the tourism of the state," Sabyasachi De further said.
The NF Railway, CPRO, also stated that it will assist the state in acquiring necessary supplies faster and will assist state local producers in exporting their products outside the state more quickly.
"Economy of the state will receive a boost," he added.
See also:
Int’l connectivity is a priority for North East Frontier Railway
World's highest pier railway bridge in Manipur takes shape
According to officials, the Jiribam-Imphal new line railway project, one of the critical connectivity projects for the North-eastern region, has made 93.30 percent progress.
The works for this new line railway project, among other connectivity projects, is also going on in full swing to connect Imphal, the capital city of Manipur to the rest of the country. The Jiribam - Imphal project has already achieved physical progress of 93.30 per cent, Sabyasachi De, CPRO of NF Railway said.
According to the NF Railway CPRO, the Jiribam-Imphal railway project includes many tunnels and bridges in difficult terrain that spans more than 111 kilometres.
The total length of tunnels in this project is 61.32 km out of which 59.11 km of tunnelling works have already been completed. The project will have a total of 11 major bridges and 137 minor bridges, out of which work for 05 major bridges and 101 minor bridges have been completed so far. The tallest pier railway bridge in the world with a height of 141 meters is also being constructed in this project and nearing completion, Sabyasachi De said.
Indian Railways is making a substantial contribution to the transformation of the Northeastern states by completing a number of new railway line projects.
Under capital connectivity initiatives, new railway lines are being built to connect all of the state capitals in the northeastern region.
The Jiribam-Imphal new line railway project, for example, is one of the critical connectivity projects for the Northeastern region that is nearing completion.
He further stated that the portion from Jiribam to Khongsang has already been opened to rail traffic.
After completion of the entire project, the present road journey time of about 10 hours to reach Imphal from Jiribam will get reduced to 2.5 hours by railways. NF Railway is putting their full effort by working 24X7 for the completion of this project with all the challenges like heavy rainfall and other logistic hindrances. The new rail project will provide enhanced connectivity to the people of Manipur, help grow small-scale industries in the area and boost the tourism of the state, Sabyasachi De further said.
The NF Railway, CPRO, also stated that it will assist the state in acquiring necessary supplies faster and will assist state local producers in exporting their products outside the state more quickly.
Economy of the state will receive a boost, he added.
See also: Int’l connectivity is a priority for North East Frontier Railway World's highest pier railway bridge in Manipur takes shape
Next Story
Innova Captab Reports Rs 12,437 Mn Revenue in FY25
Innova Captab Limited announced financial results for the quarter and fiscal year ended 31 March 2025. The company reported Q4 FY25 revenue from operations of Rs 3,147 million, reflecting 20 per cent year-on-year growth. Profit after tax stood at Rs 296 million, a 3 per cent increase.For the full year, revenue grew 15 per cent to Rs 12,437 million, led by volume growth across business segments. EBITDA rose 19 per cent to Rs 1,982 million, with margins improving to 15.9 per cent. Profit after tax increased 36 per cent to Rs 1,283 million.Managing Director Vinay Lohariwala highlighted the commis..
Next Story
Redington Reports Rs 995,620 Mn Revenue in FY25
Redington Limited announced its financial results for the quarter and fiscal year ended 31 March 2025. The company reported Q4 FY25 consolidated revenues of Rs 265,100 million, an 18 per cent increase year-on-year, with net profit rising 23 per cent to Rs 4,000 million, excluding one-time divestment gains.For the full fiscal year, Redington recorded record consolidated revenues of Rs 995,620 million, up 11 per cent compared to the previous year. Consolidated profit after tax grew 10 per cent excluding divestment gains, reflecting sustained profitability.Broad-based growth was driven by Indiaâ€..
Next Story
SKF India Reports Rs 49,199 Mn Revenue in FY25
SKF India Limited announced its unaudited financial results for the fourth quarter and audited financials for the fiscal year ending 31 March 2025. Consolidated revenue from operations for FY25 stood at Rs 49,199 million, an increase of 8 per cent over Rs 45,701 million in the previous year.Profit before tax (PBT) rose 4 per cent year-on-year to Rs 7,632 million. For Q4 FY25, consolidated revenue was Rs 12,134 million, reflecting a 1 per cent growth compared to the same quarter last year. PBT for the quarter increased 20 per cent to Rs 2,757 million.SKF India’s performance was driven by stro..