Kochi Metro Speeds Up Kakkanad Line Amid Monsoon Work Push
RAILWAYS & METRO RAIL

Kochi Metro Speeds Up Kakkanad Line Amid Monsoon Work Push

Kochi Metro, eight years on the rails, is racing to deliver its second-phase extension from Jawaharlal Nehru Stadium to Infopark via Kakkanad after Afcons Infrastructure took the contract in June 2024 with a 600-day target. Setbacks over road-widening and shifting overhead power lines have pushed completion to December 2026, yet Kochi Metro Rail Ltd (KMRL) says the timetable is now back on track thanks to round-the-clock piling even in the monsoon.

To date, 552 piles鈥攁bout 28 per cent of the viaduct requirement鈥攁re in place, while roughly 1.5 per cent of pile caps, 6 per cent of U-girders, 5 per cent of pier caps and 1.2 per cent of I-girders are finished. Ground-based tasks such as geotechnical and utility investigations are largely done, allowing precast superstructure elements to be fabricated at the Kalamassery casting yard for swift installation once site foundations are ready.

KMRL has rolled out a wet-weather regimen: stockpiling materials, reinforcing temporary works, clearing drains and culverts, deploying emergency-response teams and posting thirty traffic wardens at critical junctions to keep vehicles moving safely.

The agency insists the heavy lifting鈥攍iterally and figuratively鈥攊s under control, with pier construction about to begin and precast segments poised for rapid erection. If the current momentum holds, commuters could ride the 11.2-kilometre Kakkanad spur well before the metro celebrates its twelfth anniversary.


Kochi Metro, eight years on the rails, is racing to deliver its second-phase extension from Jawaharlal Nehru Stadium to Infopark via Kakkanad after Afcons Infrastructure took the contract in June 2024 with a 600-day target. Setbacks over road-widening and shifting overhead power lines have pushed completion to December 2026, yet Kochi Metro Rail Ltd (KMRL) says the timetable is now back on track thanks to round-the-clock piling even in the monsoon.To date, 552 piles鈥攁bout 28 per cent of the viaduct requirement鈥攁re in place, while roughly 1.5 per cent of pile caps, 6 per cent of U-girders, 5 per cent of pier caps and 1.2 per cent of I-girders are finished. Ground-based tasks such as geotechnical and utility investigations are largely done, allowing precast superstructure elements to be fabricated at the Kalamassery casting yard for swift installation once site foundations are ready.KMRL has rolled out a wet-weather regimen: stockpiling materials, reinforcing temporary works, clearing drains and culverts, deploying emergency-response teams and posting thirty traffic wardens at critical junctions to keep vehicles moving safely.The agency insists the heavy lifting鈥攍iterally and figuratively鈥攊s under control, with pier construction about to begin and precast segments poised for rapid erection. If the current momentum holds, commuters could ride the 11.2-kilometre Kakkanad spur well before the metro celebrates its twelfth anniversary.

Next Story
Infrastructure Energy

South West Pinnacle Wins Rs 30 Cr Oman Mining Contract

South West Pinnacle Exploration Ltd has secured a Rs 30 crore contract from Minerals Development Oman (MDO) for mining exploration in concession areas 12B and 13.The two-year project will be carried out via Alara Resources LLC, a JV in Oman. MDO, backed by Oman鈥檚 investment authorities, focuses on monetising mineral wealth.The contract covers copper, gold, and chromite and highlights South West Pinnacle鈥檚 growing footprint in international exploration and mining services. ..

Next Story
Equipment

Godrej GEG Boosts Intralogistics with AI and Green Tech

Godrej Enterprises Group (GEG) is revolutionising warehouse and factory logistics through its Material Handling Equipment and Storage Solutions arms by integrating AI, IoT, and automation.With 20鈥�25% market share and 85% local sourcing, GEG champions Atmanirbhar Bharat and sustainability. The Chennai plant, a green manufacturing leader, uses RoHS-compliant materials and has slashed energy consumption by 60%.GEG serves e-commerce, FMCG, retail, and cold chains with high-performance racking and electric forklifts. Upcoming IoT-enabled forklifts and telematics solutions aim to improve speed, sa..

Next Story
Infrastructure Urban

Amit Shah Inaugurates Key Projects Across Gujarat

Union 亚博体育官网首页 Minister Amit Shah inaugurated and laid the foundation stone for various projects in Gujarat鈥檚 Panchmahal district and Ahmedabad.In Godhra, he inaugurated the Center of Excellence building, sports complex, reservoir, and Miyawaki plantation. In Ahmedabad, he unveiled a new cooperative complex in Adaroda village and a primary school in Juwal.These projects, under the Model Co-op Village scheme, aim to boost education, sustainability, and rural development across the state. ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement