Kolkata Metro projects affected by significant funding shifts
22 Aug 2024
2 Min Read
CW Team
The Union Budget for the current financial year has had varying effects on Kolkata?s on-going metro projects. While funding for two projects has been reduced, one project has seen a significant increase compared to the previous year.
Overall, the allocation for Kolkata Metro projects has risen by Rs 300 million in comparison to the previous financial year.
The Dumdum Airport-Kavi Subhash (New Garia) via Rajarhat Metro project has received the largest allocation. According to a statement issued by Metro Railway, Rs 1 7.91 billion have been allocated for this line, marking a significant increase from the Rs 12 billion allocated the previous year.
Currently, commercial services are operational from Kavi Subhash to Hemanta Mukhopadhyay on this line. Metro officials expect that the stretch from Hemanta Mukhopadhyay to Beleghata will commence soon, as the Chief Commissioner of Railway Safety has already conducted an inspection of this section.
In contrast, the Noapara-Barasat and Joka-Esplanade metro projects have faced significant budget cuts. The Noapara-Barasat via Bimanbandar Metro corridor has been allocated Rs 2 billion this year, a sharp decrease from the Rs 6.2 billion allocated the previous year. Similarly, the Joka-Esplanade Metro Project has been allocated Rs 12.08 billion in the current fiscal, down from the Rs 13.50 billion allocated in the 2023-2024 Budget.
The Chief Commissioner of Railway Safety has already inspected the Noapara to Dumdum Cantonment stretch of the Noapara-Barasat corridor, and metro services on this stretch are expected to start soon. Additionally, commercial services from Joka to Majerhat have already begun on the Joka-Esplanade corridor, with ongoing construction to extend services beyond Majerhat.
Furthermore, necessary funds have been allocated for the final segment of the tunneling work of the East-West Metro between Esplanade and Sealdah, which spans 800 metres.
The Union Budget for the current financial year has had varying effects on Kolkata?s on-going metro projects. While funding for two projects has been reduced, one project has seen a significant increase compared to the previous year.
Overall, the allocation for Kolkata Metro projects has risen by Rs 300 million in comparison to the previous financial year.
The Dumdum Airport-Kavi Subhash (New Garia) via Rajarhat Metro project has received the largest allocation. According to a statement issued by Metro Railway, Rs 1 7.91 billion have been allocated for this line, marking a significant increase from the Rs 12 billion allocated the previous year.
Currently, commercial services are operational from Kavi Subhash to Hemanta Mukhopadhyay on this line. Metro officials expect that the stretch from Hemanta Mukhopadhyay to Beleghata will commence soon, as the Chief Commissioner of Railway Safety has already conducted an inspection of this section.
In contrast, the Noapara-Barasat and Joka-Esplanade metro projects have faced significant budget cuts. The Noapara-Barasat via Bimanbandar Metro corridor has been allocated Rs 2 billion this year, a sharp decrease from the Rs 6.2 billion allocated the previous year. Similarly, the Joka-Esplanade Metro Project has been allocated Rs 12.08 billion in the current fiscal, down from the Rs 13.50 billion allocated in the 2023-2024 Budget.
The Chief Commissioner of Railway Safety has already inspected the Noapara to Dumdum Cantonment stretch of the Noapara-Barasat corridor, and metro services on this stretch are expected to start soon. Additionally, commercial services from Joka to Majerhat have already begun on the Joka-Esplanade corridor, with ongoing construction to extend services beyond Majerhat.
Furthermore, necessary funds have been allocated for the final segment of the tunneling work of the East-West Metro between Esplanade and Sealdah, which spans 800 metres.
Next Story
3i Infotech Reports Rs 7.25 Bn Revenue for FY25
3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..
Next Story
Emerald Finance Joins Baya PTE to Boost SME Bill Discounting
Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..
Next Story
BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25
BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..