Konkan Railway completes 100% rail electrification of entire stretch
RAILWAYS & METRO RAIL

Konkan Railway completes 100% rail electrification of entire stretch

Konkan Railway has completed 100% rail electrification of its entire stretch, as part of its mission to electrify its entire Broad Gauge network to provide an environmentally friendly, green, and clean mode of transportation to its people under the Mission 100% Electrification - moving towards net zero carbon emission plan.

In November of 2015, the foundation stone was laid for the electrification of the entire 741 km route. The project will cost Rs 1287 crore to complete. Beginning in March 2020, the Commission of Railway Safety (CRS) inspection of the entire Konkan Railway route will be completed in six phases. On the 24th of March 2022, CRS inspected the final section between Ratnagiri and Thivim, and authorization was obtained on the 28th of March 2022.

Due to the difficult terrain of the Konkan Railway and the unfavourable climate caused by the Covid-19 Pandemic, the electrification project has been difficult. Furthermore, due to the extreme monsoon in the Konkan region, special arrangements had to be made at several locations to keep the electrification mission running.

The numerous inherent benefits of electric traction should be noted, including significant fuel savings of more than Rs 150 million, seamless operation of electric traction on the West Coast, a pollution-free mode of transportation, and reduced reliance on HSD oil.

Because the Konkan Railway is one of the largest railway routes in India, train operations with electric traction will be phased in overtime on the newly electrified KR route.

The Konkan Railway has always put safety first and will continue to work for the nation's advancement.


Also read: KEC bags RSS AMS electrification contract of Delhi Metro's Phase 4

Konkan Railway has completed 100% rail electrification of its entire stretch, as part of its mission to electrify its entire Broad Gauge network to provide an environmentally friendly, green, and clean mode of transportation to its people under the Mission 100% Electrification - moving towards net zero carbon emission plan. In November of 2015, the foundation stone was laid for the electrification of the entire 741 km route. The project will cost Rs 1287 crore to complete. Beginning in March 2020, the Commission of Railway Safety (CRS) inspection of the entire Konkan Railway route will be completed in six phases. On the 24th of March 2022, CRS inspected the final section between Ratnagiri and Thivim, and authorization was obtained on the 28th of March 2022. Due to the difficult terrain of the Konkan Railway and the unfavourable climate caused by the Covid-19 Pandemic, the electrification project has been difficult. Furthermore, due to the extreme monsoon in the Konkan region, special arrangements had to be made at several locations to keep the electrification mission running. The numerous inherent benefits of electric traction should be noted, including significant fuel savings of more than Rs 150 million, seamless operation of electric traction on the West Coast, a pollution-free mode of transportation, and reduced reliance on HSD oil. Because the Konkan Railway is one of the largest railway routes in India, train operations with electric traction will be phased in overtime on the newly electrified KR route. The Konkan Railway has always put safety first and will continue to work for the nation's advancement. Image Source Also read: KEC bags RSS AMS electrification contract of Delhi Metro's Phase 4

Next Story
Infrastructure Urban

ClickPost Launches Atlas to Benchmark E-commerce Logistics

ClickPost, a leading logistics intelligence platform, has launched Atlas, a subscription-based benchmarking tool designed to transform how e-commerce brands strategise logistics. Powered by ClickPost鈥檚 proprietary network, which processes over 50 million shipments each month, Atlas enables brands to benchmark key operational metrics in real time against industry peers and standards.Unlike traditional dashboards, Atlas delivers comparative insights鈥攆rom fulfilment speeds, RTO rates and average order values to city-level delivery times and sales data鈥攁llowing brands to identify operational..

Next Story
Real Estate

Kalyani Launches Two New LivingTree Towers in Bengaluru

Bengaluru-based Kalyani Developers has announced the launch of Towers 3 and 4 at its flagship residential project, Kalyani LivingTree, located in KIADB Aerospace Park. The expansion adds 525 premium 3BHK apartments, ranging from 1300 to 1600 sq ft, and over 7.5 lakh sq ft of built-up area. Prices start from Rs 1.2 crore.These towers, the most exclusive in Phase 1, offer uninterrupted pool and landscape views, and access to over 60 lifestyle amenities, two clubhouses totalling 1 lakh sq ft, and more than 80 per cent open space.LivingTree spans 25 acres and will comprise ten towers of 23鈥�24 fl..

Next Story
Infrastructure Urban

Blue Water Logistics IPO opens May 27

Hyderabad-based Blue Water Logistics is launching its Rs 40.5 crore IPO on May 27, 2025, which will remain open for subscription until May 29. The price band has been set at Rs 132 to Rs 135 per share, with a lot size of 1,000 shares. This is a book-built issue entirely comprising a fresh issue of 30 lakh equity shares. The IPO will be listed on the NSE Emerge platform.Smart Horizon Capital Advisors is the sole book-running lead manager, while Maashitla Securities will act as the registrar. The anchor book will open on May 26, 2025. The IPO allocates 8,35,000 shares to anchor investors, 1,56,0..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement