Mumbai-Ahmedabad bullet train project: L&T begins pier concreting work
RAILWAYS & METRO RAIL

Mumbai-Ahmedabad bullet train project: L&T begins pier concreting work

Construction major Larsen and Toubro (L&T) has started pouring concrete for the first pier of the 508.17 km Mumbai-Ahmedabad High Speed Rail (MAHSR) line, which will run through 12 stations connecting Maharashtra and Gujarat.

This milestone was reached three months after workers began pouring concrete for the first pier's open base in Gujarat's Valsad District. Shuttering panels arrived on-site last week to assist with casting jobs.

This pier (P-13), located at chainage KM 205+500 on the line's 237.1 km Package C4, is one of only two civil packages awarded so far for the main-construction line.

It runs elevated from Zaroli Village on the Maharashtra-Gujarat border to Vadodara via four stations at Vapi, Bilimora, Surat, and Bharuch, accounting for 46.66% of the main line and making it the longest.

As a reaffirmation, the majority of the line will be elevated, with contractors like L&T planning to use the full span launching system to build it.

Large stretches of land between Ahmedabad and Vadodara need to be cleared. In reality, three megaprojects are visible within 2 km of each other in Bodka village, south of Vadodara.

The Delhi-Mumbai Expressway (DME), the Mumbai-Ahmedabad Bullet Train (MAHSR), and the Western Dedicated Freight Corridor (WDFC) run from west to east.


Also read: L&T bags Mumbai 鈥� Ahmedabad Bullet Train Project

Also read: SCC-VRS consortium emerges as lowest bidder for MAHSR packages

Construction major Larsen and Toubro (L&T) has started pouring concrete for the first pier of the 508.17 km Mumbai-Ahmedabad High Speed Rail (MAHSR) line, which will run through 12 stations connecting Maharashtra and Gujarat. This milestone was reached three months after workers began pouring concrete for the first pier's open base in Gujarat's Valsad District. Shuttering panels arrived on-site last week to assist with casting jobs. This pier (P-13), located at chainage KM 205+500 on the line's 237.1 km Package C4, is one of only two civil packages awarded so far for the main-construction line. It runs elevated from Zaroli Village on the Maharashtra-Gujarat border to Vadodara via four stations at Vapi, Bilimora, Surat, and Bharuch, accounting for 46.66% of the main line and making it the longest. As a reaffirmation, the majority of the line will be elevated, with contractors like L&T planning to use the full span launching system to build it. Large stretches of land between Ahmedabad and Vadodara need to be cleared. In reality, three megaprojects are visible within 2 km of each other in Bodka village, south of Vadodara. The Delhi-Mumbai Expressway (DME), the Mumbai-Ahmedabad Bullet Train (MAHSR), and the Western Dedicated Freight Corridor (WDFC) run from west to east. Image Source Also read: L&T bags Mumbai 鈥� Ahmedabad Bullet Train Project Also read: SCC-VRS consortium emerges as lowest bidder for MAHSR packages

Next Story
Infrastructure Urban

3i Infotech Reports Rs 7.25 Bn Revenue for FY25

3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..

Next Story
Infrastructure Urban

Emerald Finance Joins Baya PTE to Boost SME Bill Discounting

Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..

Next Story
Infrastructure Urban

BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25

BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement