Mumbai Metro 2A, 7 to be fully operational from January 2022
31 May 2021
2 Min Read
CW Team
Two under-construction metro lines of the Mumbai Metro鈥擬etro-7 (Dahanukar Wadi to Aarey) and Metro-2A (Dahisar-Aarey) are set to start operations from January 2022.
RA Rajeev, MMRDA Chief, told the media that the trial runs on both lines will commence from Monday. On Monday, Chief minister Uddhav Thackeray will launch the trial run.
Metro-2A links Dahisar to DN Nagar with 16 stations in between, while Metro-7 will join Dahisar (East) with Andheri (East) and would have 13 stations in between. The two lines will offer notable relief to the people travelling in the western suburbs.
Rajeev said that both the lines would become completely functional in January next year. It will decrease the load of local trains by around 10-12% and will also lessen the travel time, notably.
The metros will move at a speed of 80 km per hour. They will commence the trial run from Monday, and it will be accomplished by October. Following that, the first phase will become operational from October onwards, he continued.
The cumulative cost for the two metro lines is about Rs 12,800 crore, of which about Rs 6,000 crore have been utilised till date. It is approximated that 9.2 lakh people will be travelling on both these lines once functional.
Both the lines were anticipated to be operational by December last year, but the Covid-19 pandemic and the following lockdown induced delays. After the lockdown was relieved, MMRDA started the work.
MMRDA is the central administration for the Mumbai Metro Master Plan which is intended to complete a 337-km network in and throughout the city. MMRDA is also executing the Mumbai Trans-Harbour Link (MTHL) 鈥� a 22 km sea bridge joining Mumbai and Navi Mumbai.
Mumbai got its first metro linking the suburbs of Ghatkopar, Andheri and Versova in 2014.
Also read: Mumbai Metro: MMRDA completes overhead electrification work
Also read: Mumbai Metro-5 to be completed in four years: MMRDA
Two under-construction metro lines of the Mumbai Metro鈥擬etro-7 (Dahanukar Wadi to Aarey) and Metro-2A (Dahisar-Aarey) are set to start operations from January 2022.
RA Rajeev, MMRDA Chief, told the media that the trial runs on both lines will commence from Monday. On Monday, Chief minister Uddhav Thackeray will launch the trial run.
Metro-2A links Dahisar to DN Nagar with 16 stations in between, while Metro-7 will join Dahisar (East) with Andheri (East) and would have 13 stations in between. The two lines will offer notable relief to the people travelling in the western suburbs.
Rajeev said that both the lines would become completely functional in January next year. It will decrease the load of local trains by around 10-12% and will also lessen the travel time, notably.
The metros will move at a speed of 80 km per hour. They will commence the trial run from Monday, and it will be accomplished by October. Following that, the first phase will become operational from October onwards, he continued.
The cumulative cost for the two metro lines is about Rs 12,800 crore, of which about Rs 6,000 crore have been utilised till date. It is approximated that 9.2 lakh people will be travelling on both these lines once functional.
Both the lines were anticipated to be operational by December last year, but the Covid-19 pandemic and the following lockdown induced delays. After the lockdown was relieved, MMRDA started the work.
MMRDA is the central administration for the Mumbai Metro Master Plan which is intended to complete a 337-km network in and throughout the city. MMRDA is also executing the Mumbai Trans-Harbour Link (MTHL) 鈥� a 22 km sea bridge joining Mumbai and Navi Mumbai.
Mumbai got its first metro linking the suburbs of Ghatkopar, Andheri and Versova in 2014.
Image SourceAlso read: Mumbai Metro: MMRDA completes overhead electrification work
Also read: Mumbai Metro-5 to be completed in four years: MMRDA
Next Story
unWOOD transforms plastic waste into durable wood alternative
unWOOD, a breakthrough innovation, is converting hard-to-recycle plastic waste into a durable alternative to natural wood. Developed through a proprietary process called Intelligent Compounding, unWOOD uses a Macro Molecular Fiber Matrix (MMFM) structure to replicate the strength, look, and feel of hardwood鈥攚ithout the environmental cost.Conceptualised by Dr Babu Padmanabhan, the material addresses key flaws in traditional plastic recycling by consuming minimal energy, using zero water, and generating no microplastics. 鈥淎ny application that introduces plastics into areas where it cannot be..
Next Story
H盲fele launches Matrix undermount runners range
H盲fele has introduced its new Matrix range of undermount runners, designed to enhance drawer motion across kitchens, wardrobes, bathroom units, and more.Available in four weight capacities and a wide range of lengths, the Matrix undermount runners support diverse drawer designs. The 40 kg and 60 kg variants feature synchronised technology for superior motion and drawer stability. All runners come with an integrated soft-close mechanism to ensure smooth and noiseless operation.This in-house range is ideal for kitchen cabinets, bed storage units, living room furniture and bathroom drawers, offe..
Next Story
India's first AI-integrated campus announced in Noida
Yashoda Hospital and Bhutani Infra have announced plans to develop India鈥檚 first fully AI-integrated mixed-use campus in Greater Noida West. The upcoming project will feature a hospital, retail spaces, offices, SOHOs, serviced apartments, and a hotel鈥攁ll operating within a self-learning, generative AI-powered ecosystem.The AI-first campus will integrate real-time data systems, predictive analytics, and adaptive infrastructure to offer personalised experiences across functions. From AI-enabled footfall tracking and dynamic energy optimisation to smart F&B and retail insights, the develo..