Murkongselek-Pasighat Rail Project Hits 45% Completion
RAILWAYS & METRO RAIL

Murkongselek-Pasighat Rail Project Hits 45% Completion

The Murkongselek鈥揚asighat new railway line, a flagship project under Northeast Frontier Railway (NFR), has reached 45 per cent physical progress as of March 31, 2025, with work valued at approximately Rs 12.52 billion. Designed to enhance rail connectivity between Assam and Arunachal Pradesh, the 26.15-kilometre line is being executed in two distinct phases.

Phase I, covering the Murkongselek鈥揝ille segment (15.6 km), is close to completing its earthwork, with 1.375 million cubic meters finished out of the targeted 1.416 million. Construction is also well underway on 18 major and 35 minor bridges, while ballast supply and track laying are set to begin soon. The Murkongselek station building is nearing completion.

In Phase II (Sille鈥揚asighat, 10.55 km), 0.355 million cubic meters of earthwork has been completed out of the planned 0.685 million, with bridge building and casting ongoing. Land acquisition for a road overbridge at Pasighat Yard is being fast-tracked with local support.

The project has continued steadily despite challenges like prolonged monsoon conditions and local disruptions. During a recent site visit, the NFR General Manager (Construction) directed officials to maintain progress and ensure high construction standards.

Once operational, the new line is expected to spur economic development, promote tourism, and strengthen national integration by connecting remote border areas. The NFR reaffirmed its commitment to completing the project despite logistical and environmental challenges.


The Murkongselek鈥揚asighat new railway line, a flagship project under Northeast Frontier Railway (NFR), has reached 45 per cent physical progress as of March 31, 2025, with work valued at approximately Rs 12.52 billion. Designed to enhance rail connectivity between Assam and Arunachal Pradesh, the 26.15-kilometre line is being executed in two distinct phases.Phase I, covering the Murkongselek鈥揝ille segment (15.6 km), is close to completing its earthwork, with 1.375 million cubic meters finished out of the targeted 1.416 million. Construction is also well underway on 18 major and 35 minor bridges, while ballast supply and track laying are set to begin soon. The Murkongselek station building is nearing completion.In Phase II (Sille鈥揚asighat, 10.55 km), 0.355 million cubic meters of earthwork has been completed out of the planned 0.685 million, with bridge building and casting ongoing. Land acquisition for a road overbridge at Pasighat Yard is being fast-tracked with local support.The project has continued steadily despite challenges like prolonged monsoon conditions and local disruptions. During a recent site visit, the NFR General Manager (Construction) directed officials to maintain progress and ensure high construction standards.Once operational, the new line is expected to spur economic development, promote tourism, and strengthen national integration by connecting remote border areas. The NFR reaffirmed its commitment to completing the project despite logistical and environmental challenges.

Next Story
Real Estate

Mahindra Lifespaces Targets Rs 10,000 Bn Sales by FY30

Mahindra Lifespace Developers aims to more than treble its sales to Rs 100 Bn by financial year twenty thirty, up from Rs 33 Bn in financial year twenty twenty-five. Backed by a strong land bank, robust pipeline, and rights issue of Rs 15 Bn, the company is focusing on growth in premium housing and industrial leasing.The company鈥檚 gross development value (GDV) has grown from Rs 44 Bn in financial year twenty twenty-four to Rs 181 Bn in financial year twenty twenty-five, with the current pipeline at Rs 390 Bn. New launches are planned in Whitefield, Malad, Bhandup, Mahalaxmi and Pune.Mahindra..

Next Story
Infrastructure Transport

Bhubaneswar New Station Starts Three Express Trains to Ease Congestion

East Coast Railway has begun full-scale operations of three major express trains from the Bhubaneswar New Railway Station (BBSN) from 12 May 2025. The move aims to improve connectivity and reduce congestion at the Bhubaneswar Main Station.The trains now operating from BBSN include the Mumbai鈥揃hubaneswar Konark Express, the Secunderabad鈥揃hubaneswar Visakha Express, and the Bhubaneswar鈥揤isakhapatnam Intercity Express. All three were previously routed through the Bhubaneswar Main Station.BBSN, located in northern Bhubaneswar, is expected to benefit residents of northern city zones, Cuttack,..

Next Story
Infrastructure Transport

Indian Railways Clears Survey for New Line in Sikkim

The Ministry of Railways has approved a Final Location Survey for a proposed railway line in Sikkim, connecting Melli to Dentam via Jorethang and Legship. The Rs 22.5 Mn survey will be conducted by Northeast Frontier Railway to assess technical and financial feasibility.The planned 75-kilometre corridor aims to improve rail access in the under-served southern and western regions of Sikkim. The project is backed by Railway Minister Ashwini Vaishnaw and follows efforts by Member of Parliament Indra Hang Subba.This new line is intended to extend the under-construction Sivok鈥揜angpo railway proje..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement