Next Phase of Kolkata's Orange Line Metro Tunnel Work Set To Begin
10 Dec 2024
2 Min Read
CW Team
Rail Vikas Nigam Ltd (RVNL) had completed the basic work for the underground tunnels of the Orange Line Metro along VIP Road and was set to commence the next phase of construction. The ongoing project, part of the New Garia-Airport Metro corridor, was soon expected to enter a critical stage, requiring the tunnel to curve eastward toward the airport.
To ensure smooth traffic management during this phase, RVNL had sought a revised traffic block and prepared an alternative road for Kolkata-bound vehicles. The report mentioned that, as part of its strategy to minimise traffic disruptions on VIP Road, RVNL had divided the construction of the final stretch into three phases.
It was noted that this 29-km, mostly elevated Metro line would transition underground in its last leg. Contractors from Afcons were tasked with building a 300-meter ramp and 500 meters of twin tunnels using the cut-and-cover method.
In April, RVNL had begun work on the diaphragm wall and top slab, around 700 meters from the airport, after cordoning off a section of VIP Road and creating a compensatory 100m x 12m road space on the Kolkata-bound flank, using land provided by the Airports Authority of India (AAI). With the first phase now complete, RVNL had applied to the Bidhannagar traffic department for a revised traffic arrangement.
A new compensatory road, 70m x 12m in size, had been constructed on AAI land to redirect traffic while allowing construction to progress. Senior officials from the Bidhannagar traffic police and the state Public Works Department (PWD) had recently inspected the new setup. An official mentioned that traffic trials were being organized to direct vehicles through a mandatory left turn along a 20-meter-wide stretch.
Meanwhile, RVNL was set to extend barricades near Kaikhali to facilitate ramp construction beyond pier 846, where the viaduct ends. The U-turn traffic signal post had also been slightly shifted toward the airport to accommodate this adjustment.
The report emphasised that this meticulous planning aimed to ensure uninterrupted Metro construction while maintaining smooth traffic flow on one of Kolkata's key arterial roads.
Rail Vikas Nigam Ltd (RVNL) had completed the basic work for the underground tunnels of the Orange Line Metro along VIP Road and was set to commence the next phase of construction. The ongoing project, part of the New Garia-Airport Metro corridor, was soon expected to enter a critical stage, requiring the tunnel to curve eastward toward the airport.To ensure smooth traffic management during this phase, RVNL had sought a revised traffic block and prepared an alternative road for Kolkata-bound vehicles. The report mentioned that, as part of its strategy to minimise traffic disruptions on VIP Road, RVNL had divided the construction of the final stretch into three phases.It was noted that this 29-km, mostly elevated Metro line would transition underground in its last leg. Contractors from Afcons were tasked with building a 300-meter ramp and 500 meters of twin tunnels using the cut-and-cover method.In April, RVNL had begun work on the diaphragm wall and top slab, around 700 meters from the airport, after cordoning off a section of VIP Road and creating a compensatory 100m x 12m road space on the Kolkata-bound flank, using land provided by the Airports Authority of India (AAI). With the first phase now complete, RVNL had applied to the Bidhannagar traffic department for a revised traffic arrangement.A new compensatory road, 70m x 12m in size, had been constructed on AAI land to redirect traffic while allowing construction to progress. Senior officials from the Bidhannagar traffic police and the state Public Works Department (PWD) had recently inspected the new setup. An official mentioned that traffic trials were being organized to direct vehicles through a mandatory left turn along a 20-meter-wide stretch.Meanwhile, RVNL was set to extend barricades near Kaikhali to facilitate ramp construction beyond pier 846, where the viaduct ends. The U-turn traffic signal post had also been slightly shifted toward the airport to accommodate this adjustment.The report emphasised that this meticulous planning aimed to ensure uninterrupted Metro construction while maintaining smooth traffic flow on one of Kolkata's key arterial roads.
Next Story
3i Infotech Reports Rs 7.25 Bn Revenue for FY25
3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..
Next Story
Emerald Finance Joins Baya PTE to Boost SME Bill Discounting
Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..
Next Story
BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25
BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..