Panvel-Karjat suburban railway corridor progresses swiftly
06 Dec 2023
2 Min Read
CW Team
The suburban panorama surrounding Panvel and Karjat is poised for a substantial metamorphosis with the ongoing development of a new suburban railway corridor. Roop Narayan Sunkar, the Member Infrastructure of the Railway Board, recently conducted an inspection of the project, providing insights into its current status and future potential.
Upon completion, the travel time between CSMT and Karjat is anticipated to decrease by around 30 minutes compared to the existing 130-minute journey via Kalyan. The Mumbai Rail Vikas Corporation aims to finalise the project by December 2025, with 46 percent of the work already accomplished.
During the inspection, Member Infrastructure Roop Narayan Sunkar expressed satisfaction and praised the dedication of the field staff. He engaged with project stakeholders and acknowledged the commitment demonstrated in executing this crucial suburban railway corridor. The inspections were conducted alongside MRVC Chairman and Managing Director Subhash Chand Gupta.
Initiated in January 2018, the project has made significant progress, obtaining approvals for detailed estimates, drawings, and designs, including 70 General Arrangement Drawings (GADs) for rail flyovers, tunnels, and stations. Environmental and Social Impact Assessments for stations like Mohope, Chowk, Karjat, Chikhale, and Panvel have also been approved, showcasing meticulous planning.
According to MRVC, land acquisition, a pivotal aspect of large-scale infrastructure projects, has made remarkable strides. Private land covering 57.16 hectares and government land measuring 4.4 hectares has been successfully acquired. Notably, 9.131 hectares of forest land have received clearance, underscoring the project's commitment to environmental sustainability.
Sunil Udasi, Chief Public Relations Officer of MRVC, provided insights into the ongoing works, stating, "Earthwork and bridge construction are in progress, with significant portions already completed. Achievements include completing 13.95 lakh cubic meters of soil earthwork out of the total 20.85 lakh cubic meters. Panvel Station's building construction is underway, with Letters of Acceptance (LOA) issued for various other buildings. Contracts for stations at Chikhale, Mohape, Chowk, and Karjat have been awarded, with active work on Karjat and Mohape already in progress."
Furthermore, progress is evident in the Pune Expressway Rail Under Bridge (RUB), with piling work and pile caps completed. Rail over bridges at Panvel and Karjat are steadily advancing, with structural components such as PSC girders and slabs in various stages of completion. The tunnels, numbered 1, 2, and 3, are taking shape, highlighting the complexity and scale of the project, with notable accomplishments in the primary support and RCC lining works of Tunnel 1.
The suburban panorama surrounding Panvel and Karjat is poised for a substantial metamorphosis with the ongoing development of a new suburban railway corridor. Roop Narayan Sunkar, the Member Infrastructure of the Railway Board, recently conducted an inspection of the project, providing insights into its current status and future potential.
Upon completion, the travel time between CSMT and Karjat is anticipated to decrease by around 30 minutes compared to the existing 130-minute journey via Kalyan. The Mumbai Rail Vikas Corporation aims to finalise the project by December 2025, with 46 percent of the work already accomplished.
During the inspection, Member Infrastructure Roop Narayan Sunkar expressed satisfaction and praised the dedication of the field staff. He engaged with project stakeholders and acknowledged the commitment demonstrated in executing this crucial suburban railway corridor. The inspections were conducted alongside MRVC Chairman and Managing Director Subhash Chand Gupta.
Initiated in January 2018, the project has made significant progress, obtaining approvals for detailed estimates, drawings, and designs, including 70 General Arrangement Drawings (GADs) for rail flyovers, tunnels, and stations. Environmental and Social Impact Assessments for stations like Mohope, Chowk, Karjat, Chikhale, and Panvel have also been approved, showcasing meticulous planning.
According to MRVC, land acquisition, a pivotal aspect of large-scale infrastructure projects, has made remarkable strides. Private land covering 57.16 hectares and government land measuring 4.4 hectares has been successfully acquired. Notably, 9.131 hectares of forest land have received clearance, underscoring the project's commitment to environmental sustainability.
Sunil Udasi, Chief Public Relations Officer of MRVC, provided insights into the ongoing works, stating, Earthwork and bridge construction are in progress, with significant portions already completed. Achievements include completing 13.95 lakh cubic meters of soil earthwork out of the total 20.85 lakh cubic meters. Panvel Station's building construction is underway, with Letters of Acceptance (LOA) issued for various other buildings. Contracts for stations at Chikhale, Mohape, Chowk, and Karjat have been awarded, with active work on Karjat and Mohape already in progress.
Furthermore, progress is evident in the Pune Expressway Rail Under Bridge (RUB), with piling work and pile caps completed. Rail over bridges at Panvel and Karjat are steadily advancing, with structural components such as PSC girders and slabs in various stages of completion. The tunnels, numbered 1, 2, and 3, are taking shape, highlighting the complexity and scale of the project, with notable accomplishments in the primary support and RCC lining works of Tunnel 1.
Next Story
3i Infotech Reports Rs 7.25 Bn Revenue for FY25
3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..
Next Story
Emerald Finance Joins Baya PTE to Boost SME Bill Discounting
Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..
Next Story
BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25
BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..