SYSTRA-DB awarded the General Consultancy contract for Mumbai Metro
29 Dec 2022
2 Min Read
CW Team
SYSTRA MVA Consulting - DB Engineering & Consulting JV was awarded the General Consultant (GC) contract for Mumbai Metro's 9.20 km Line-10 (Gaimukh - Shivaji Chowk) and 20.7 km Line-12 (Kalyan - Taloja).
Through the Quality and Cost-Based Selection (QCBS) method, the consortium was chosen as the preferred bidder for the contract in July 2022. Their bid of Rs 2.65 billion and overall score of 91.06 beat out AECOM-HILL JV and AYESA-KNR JV.
The appointment of the SYSTRA-DB JV to assist the Mumbai Metropolitan Region Development Authority (MMRDA) is expected to pave the way for the rapid implementation of both lines through assistance with design, supervision, safety, quality control, and contract management for civil and systems work.
The project's brief scope includes GC-07A Appointment of a General Consultant for Civil and System Works of Mumbai Metro Line 10 (Gaimukh - Shivaji Chowk (Mira Road) and Mumbai Metro Line 12 (Kalyan- Taloja) of MMRDA's Mumbai Metro Rail Project.
According to MMRDA, the estimated duration of both projects is 54 months.
Line-4/4A (Green Line) will be extended west to become Line-10 (Gaimukh to Shivaji Chowk), with four stops at Gaimukh Reti Bundar, Varsova Char Phata, Kashimira, and Shivaji Chowk.
A 20.75 km southern extension of the 24.95 km Line-5 (Orange Line) would be built as Line-12 (Kalyan to Taloja), with 17 stops at Ganesh Nagar, Pisvali Gaon, Golavali, Dombivli MIDC, Sagaon, Sonarpada, Manpada, Hedutane, Kolegaon, Nilaje Gaon, Vadavali, Bale, Waklan, Turbhe, Pisarve Depot, Pisarve, Taloja. The route's depot is planned for Pisarve.
Also read:
ADB, JICA line up loans for Delhi-SNB RRTS.
Metro to connect Noida Airport and New Delhi Railway Station
SYSTRA MVA Consulting - DB Engineering & Consulting JV was awarded the General Consultant (GC) contract for Mumbai Metro's 9.20 km Line-10 (Gaimukh - Shivaji Chowk) and 20.7 km Line-12 (Kalyan - Taloja).
Through the Quality and Cost-Based Selection (QCBS) method, the consortium was chosen as the preferred bidder for the contract in July 2022. Their bid of Rs 2.65 billion and overall score of 91.06 beat out AECOM-HILL JV and AYESA-KNR JV.
The appointment of the SYSTRA-DB JV to assist the Mumbai Metropolitan Region Development Authority (MMRDA) is expected to pave the way for the rapid implementation of both lines through assistance with design, supervision, safety, quality control, and contract management for civil and systems work.
The project's brief scope includes GC-07A Appointment of a General Consultant for Civil and System Works of Mumbai Metro Line 10 (Gaimukh - Shivaji Chowk (Mira Road) and Mumbai Metro Line 12 (Kalyan- Taloja) of MMRDA's Mumbai Metro Rail Project.
According to MMRDA, the estimated duration of both projects is 54 months.
Line-4/4A (Green Line) will be extended west to become Line-10 (Gaimukh to Shivaji Chowk), with four stops at Gaimukh Reti Bundar, Varsova Char Phata, Kashimira, and Shivaji Chowk.
A 20.75 km southern extension of the 24.95 km Line-5 (Orange Line) would be built as Line-12 (Kalyan to Taloja), with 17 stops at Ganesh Nagar, Pisvali Gaon, Golavali, Dombivli MIDC, Sagaon, Sonarpada, Manpada, Hedutane, Kolegaon, Nilaje Gaon, Vadavali, Bale, Waklan, Turbhe, Pisarve Depot, Pisarve, Taloja. The route's depot is planned for Pisarve.
Also read:
ADB, JICA line up loans for Delhi-SNB RRTS.Metro to connect Noida Airport and New Delhi Railway Station
Next Story
unWOOD transforms plastic waste into durable wood alternative
unWOOD, a breakthrough innovation, is converting hard-to-recycle plastic waste into a durable alternative to natural wood. Developed through a proprietary process called Intelligent Compounding, unWOOD uses a Macro Molecular Fiber Matrix (MMFM) structure to replicate the strength, look, and feel of hardwood鈥攚ithout the environmental cost.Conceptualised by Dr Babu Padmanabhan, the material addresses key flaws in traditional plastic recycling by consuming minimal energy, using zero water, and generating no microplastics. 鈥淎ny application that introduces plastics into areas where it cannot be..
Next Story
H盲fele launches Matrix undermount runners range
H盲fele has introduced its new Matrix range of undermount runners, designed to enhance drawer motion across kitchens, wardrobes, bathroom units, and more.Available in four weight capacities and a wide range of lengths, the Matrix undermount runners support diverse drawer designs. The 40 kg and 60 kg variants feature synchronised technology for superior motion and drawer stability. All runners come with an integrated soft-close mechanism to ensure smooth and noiseless operation.This in-house range is ideal for kitchen cabinets, bed storage units, living room furniture and bathroom drawers, offe..
Next Story
India's first AI-integrated campus announced in Noida
Yashoda Hospital and Bhutani Infra have announced plans to develop India鈥檚 first fully AI-integrated mixed-use campus in Greater Noida West. The upcoming project will feature a hospital, retail spaces, offices, SOHOs, serviced apartments, and a hotel鈥攁ll operating within a self-learning, generative AI-powered ecosystem.The AI-first campus will integrate real-time data systems, predictive analytics, and adaptive infrastructure to offer personalised experiences across functions. From AI-enabled footfall tracking and dynamic energy optimisation to smart F&B and retail insights, the develo..