Thane-Bhiwandi Metro Line-5: MMRDA mounts spans over Majiwada Flyover
04 Oct 2024
2 Min Read
CW Team
The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a major milestone in the ongoing Metro Line-5 (Thane-Bhiwandi) project by successfully erecting two critical spans鈥�57.50 meters and 46.00 meters鈥攐ver the busy Majiwada Flyover using high-capacity cranes (450T and 700T).
The complex operation, which required precise engineering and extensive safety measures, was executed in a densely populated area above a congested roadway. According to MMRDA Metropolitan Commissioner Dr Sanjay Mukherjee, the team completed the task within just five hours during the night, ensuring minimal traffic disruption with the support of local authorities.
The 57.50-meter span between Pier 10 and Pier 11 was lifted using tandem girders weighing 290 MT on Ghodbunder Road, while the 46.00-meter span on the Thane-Bhiwandi Road utilised a super-lift arrangement to account for a 20-meter crane radius. This operation highlights the technical expertise and commitment of the team to completing the project on time.
The Thane-Bhiwandi Metro Line-5 project is being implemented in two phases. Phase-I, covering a 12.7 km stretch with six elevated stations, is 93% complete, with track installation and architectural finishes currently underway. The depot for Line-5 is planned at Kasheli, and preliminary work has commenced. The total cost for Metro Line-5 is estimated at Rs 84.17 billion.
The process of appointing a general consultant for Phase-II between Bhiwandi and Kalyan is in progress, with the appointment of a civil contractor to follow. Once completed, Metro Line-5 will provide interconnectivity with the ongoing Metro Line-4 (Wadala-Kasarvadavli) and the proposed Metro Line-12 (Kalyan-Taloja), along with the existing Central Railway suburban network, significantly enhancing regional connectivity.
(freepressjournal)
The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a major milestone in the ongoing Metro Line-5 (Thane-Bhiwandi) project by successfully erecting two critical spans鈥�57.50 meters and 46.00 meters鈥攐ver the busy Majiwada Flyover using high-capacity cranes (450T and 700T).
The complex operation, which required precise engineering and extensive safety measures, was executed in a densely populated area above a congested roadway. According to MMRDA Metropolitan Commissioner Dr Sanjay Mukherjee, the team completed the task within just five hours during the night, ensuring minimal traffic disruption with the support of local authorities.
The 57.50-meter span between Pier 10 and Pier 11 was lifted using tandem girders weighing 290 MT on Ghodbunder Road, while the 46.00-meter span on the Thane-Bhiwandi Road utilised a super-lift arrangement to account for a 20-meter crane radius. This operation highlights the technical expertise and commitment of the team to completing the project on time.
The Thane-Bhiwandi Metro Line-5 project is being implemented in two phases. Phase-I, covering a 12.7 km stretch with six elevated stations, is 93% complete, with track installation and architectural finishes currently underway. The depot for Line-5 is planned at Kasheli, and preliminary work has commenced. The total cost for Metro Line-5 is estimated at Rs 84.17 billion.
The process of appointing a general consultant for Phase-II between Bhiwandi and Kalyan is in progress, with the appointment of a civil contractor to follow. Once completed, Metro Line-5 will provide interconnectivity with the ongoing Metro Line-4 (Wadala-Kasarvadavli) and the proposed Metro Line-12 (Kalyan-Taloja), along with the existing Central Railway suburban network, significantly enhancing regional connectivity.
(freepressjournal)
Next Story
Postal Dept Unveils Stamp Honouring 125 Years of Kodaikanal Observatory
The Department of Posts is proud to release a commemorative postage stamp celebrating 125 years of the Kodaikanal Solar Observatory (KSO). Recognising the legacy of the KSO through this special stamp is a fitting tribute to one of India鈥檚 most significant scientific institutions and highlights the nation鈥檚 long-standing contribution to global science.The Commemorative stamp was released by S Rajendra Kumar, Chief Postmaster General, Karnataka Circle in the gracious presence of A S Kiran Kumar, Chairperson, Governing Council, IIA and Former Chairman, ISRO and other esteemed guests at Indian..
Next Story
IIFT Sets Up First Overseas Campus and Expands Global Reach in Dubai
The Indian Institute of Foreign Trade (IIFT), an autonomous body under the Ministry of Commerce and Industry, Government of India, has announced the establishment of its first overseas campus in Dubai, United Arab Emirates. This marks a key step in expanding IIFT鈥檚 global presence and strengthening India鈥檚 engagement in international business education.This historic development has been made possible with the approvals from the Ministry of Education, and No Objection Certificates from the Ministry of External Affairs, Ministry of 亚博体育官网首页 Affairs, and the University Grants Commission. It marks..
Next Story
KEC International Bags Rs 11.33 Bn Transmission & Distribution Orders
KEC International, a prominent global infrastructure EPC company and a part of the RPG Group, announced that it had secured new transmission and distribution (T\&D) project orders worth Rs 11.33 billion in India. The company鈥檚 shares were expected to draw attention on Monday, May 19.The newly won orders include a significant contract from Power Grid Corporation of India (PGCIL) for the construction of a 卤800 kV HVDC transmission line along with a 765 kV GIS substation. Additionally, KEC International secured an order from a leading private developer for a 400 kV Quad transmission line.V..