Western Railway Swiftly Replaces Bridge 5 Steel Girder Near Mumbai Central
RAILWAYS & METRO RAIL

Western Railway Swiftly Replaces Bridge 5 Steel Girder Near Mumbai Central

As part of a major infrastructure upgrade, the steel girder of Bridge 5, located between Mumbai Central and Grant Road on the Mumbai Central division of Western Railway, has been replaced with a specially designed Non-Standard Pre-Stressed Concrete (PSC) slab. This upgrade was crucial for improving the safety and durability of the bridge, which plays a vital role in the busy Mumbai rail network.

The project, originally expected to take 13 hours, was completed ahead of schedule in just 10 hours, thanks to efficient planning and execution. Bridge 5, a skew bridge with a 49-degree angle and a span of 12 meters, presented significant challenges due to limited space. To carry out the replacement, the team used 10 PSC slabs, each measuring 11,565 mm in length and 650 mm in depth, along with ballast retainers.

Due to the site conditions, the crane had to be positioned directly on the through lines, which required the removal of overhead electrical equipment on three tracks. Despite these constraints, the project team successfully managed the task with precision and careful coordination. The completion of this upgrade not only improves the structural integrity of the bridge but also contributes to the smoother operation of trains on one of Mumbai's busiest rail corridors. This project sets a new standard for future infrastructure upgrades within the Western Railway division.

News source: The Free Press Journal

As part of a major infrastructure upgrade, the steel girder of Bridge 5, located between Mumbai Central and Grant Road on the Mumbai Central division of Western Railway, has been replaced with a specially designed Non-Standard Pre-Stressed Concrete (PSC) slab. This upgrade was crucial for improving the safety and durability of the bridge, which plays a vital role in the busy Mumbai rail network. The project, originally expected to take 13 hours, was completed ahead of schedule in just 10 hours, thanks to efficient planning and execution. Bridge 5, a skew bridge with a 49-degree angle and a span of 12 meters, presented significant challenges due to limited space. To carry out the replacement, the team used 10 PSC slabs, each measuring 11,565 mm in length and 650 mm in depth, along with ballast retainers. Due to the site conditions, the crane had to be positioned directly on the through lines, which required the removal of overhead electrical equipment on three tracks. Despite these constraints, the project team successfully managed the task with precision and careful coordination. The completion of this upgrade not only improves the structural integrity of the bridge but also contributes to the smoother operation of trains on one of Mumbai's busiest rail corridors. This project sets a new standard for future infrastructure upgrades within the Western Railway division. News source: The Free Press Journal

Next Story
Infrastructure Urban

3i Infotech Reports Rs 7.25 Bn Revenue for FY25

3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..

Next Story
Infrastructure Urban

Emerald Finance Joins Baya PTE to Boost SME Bill Discounting

Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..

Next Story
Infrastructure Urban

BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25

BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement