Andhra Pradesh Aims to Finish Key Ports by Dec 2026
06 Jun 2025
2 Min Read
CW Team
Andhra Pradesh Chief Minister N Chandrababu Naidu has instructed officials to complete Phase 1 works of the Machilipatnam, Ramayapatnam, Mulapeta, and Kakinada Gateway ports by December 2026. The same timeline applies to Phase 1 construction of four fishing harbours鈥擩uvvaladinne, Nizampatnam, Machilipatnam, and Uppada.
Chairing a review meeting at his camp office in Undavalli, the Chief Minister described ports and fishing harbours as vital economic drivers for the state. He urged officials to explore the possibility of upgrading fishing harbours into minor ports, provided the transition does not disrupt the livelihoods of local fishing communities. This move, he said, would boost regional incomes and infrastructure.
Naidu also directed the immediate initiation of Phase 1 works for four new airports in Kuppam, Dagadarthi, Amaravati, and Srikakulam (Palasa). His vision is to develop at least 20 ports and 14 airports throughout Andhra Pradesh to accelerate economic growth.
In addition, the Chief Minister called for the expansion of state roads to meet increasing traffic demand, integrating them with national highways through the Public Private Partnership (PPP) model. He announced the formation of a dedicated Andhra Pradesh Logistics Corporation, which will oversee development across ports, airports, and fishing harbours. Officials were also directed to draft a heliport development plan in agency areas to enhance tourism potential.
During the meeting, officials shared progress updates on key infrastructure projects:
- Machilipatnam Port: 43.25 per cent complete, targeted for November 2026 completion
- Ramayapatnam Port: 63.89 per cent complete
- Mulapeta Port: 46.59 per cent complete
- Kakinada Gateway Port: 29.92 per cent complete
- Juvvaladinne Fishing Harbour: 97.72 per cent complete
- Nizampatnam Fishing Harbour: 81.17 per cent complete
- Machilipatnam Fishing Harbour: 69.20 per cent complete
- Uppada Fishing Harbour: 78.94 per cent complete
With firm timelines and broad infrastructure ambitions, the Andhra Pradesh government aims to position the state as a strategic maritime and logistics hub.
Andhra Pradesh Chief Minister N Chandrababu Naidu has instructed officials to complete Phase 1 works of the Machilipatnam, Ramayapatnam, Mulapeta, and Kakinada Gateway ports by December 2026. The same timeline applies to Phase 1 construction of four fishing harbours鈥擩uvvaladinne, Nizampatnam, Machilipatnam, and Uppada.Chairing a review meeting at his camp office in Undavalli, the Chief Minister described ports and fishing harbours as vital economic drivers for the state. He urged officials to explore the possibility of upgrading fishing harbours into minor ports, provided the transition does not disrupt the livelihoods of local fishing communities. This move, he said, would boost regional incomes and infrastructure.Naidu also directed the immediate initiation of Phase 1 works for four new airports in Kuppam, Dagadarthi, Amaravati, and Srikakulam (Palasa). His vision is to develop at least 20 ports and 14 airports throughout Andhra Pradesh to accelerate economic growth.In addition, the Chief Minister called for the expansion of state roads to meet increasing traffic demand, integrating them with national highways through the Public Private Partnership (PPP) model. He announced the formation of a dedicated Andhra Pradesh Logistics Corporation, which will oversee development across ports, airports, and fishing harbours. Officials were also directed to draft a heliport development plan in agency areas to enhance tourism potential.During the meeting, officials shared progress updates on key infrastructure projects:Machilipatnam Port: 43.25 per cent complete, targeted for November 2026 completionRamayapatnam Port: 63.89 per cent completeMulapeta Port: 46.59 per cent completeKakinada Gateway Port: 29.92 per cent completeJuvvaladinne Fishing Harbour: 97.72 per cent completeNizampatnam Fishing Harbour: 81.17 per cent completeMachilipatnam Fishing Harbour: 69.20 per cent completeUppada Fishing Harbour: 78.94 per cent completeWith firm timelines and broad infrastructure ambitions, the Andhra Pradesh government aims to position the state as a strategic maritime and logistics hub.
Next Story
South West Pinnacle Wins Rs 30 Cr Oman Mining Contract
South West Pinnacle Exploration Ltd has secured a Rs 30 crore contract from Minerals Development Oman (MDO) for mining exploration in concession areas 12B and 13.The two-year project will be carried out via Alara Resources LLC, a JV in Oman. MDO, backed by Oman鈥檚 investment authorities, focuses on monetising mineral wealth.The contract covers copper, gold, and chromite and highlights South West Pinnacle鈥檚 growing footprint in international exploration and mining services.
..
Next Story
Godrej GEG Boosts Intralogistics with AI and Green Tech
Godrej Enterprises Group (GEG) is revolutionising warehouse and factory logistics through its Material Handling Equipment and Storage Solutions arms by integrating AI, IoT, and automation.With 20鈥�25% market share and 85% local sourcing, GEG champions Atmanirbhar Bharat and sustainability. The Chennai plant, a green manufacturing leader, uses RoHS-compliant materials and has slashed energy consumption by 60%.GEG serves e-commerce, FMCG, retail, and cold chains with high-performance racking and electric forklifts. Upcoming IoT-enabled forklifts and telematics solutions aim to improve speed, sa..
Next Story
Amit Shah Inaugurates Key Projects Across Gujarat
Union 亚博体育官网首页 Minister Amit Shah inaugurated and laid the foundation stone for various projects in Gujarat鈥檚 Panchmahal district and Ahmedabad.In Godhra, he inaugurated the Center of Excellence building, sports complex, reservoir, and Miyawaki plantation. In Ahmedabad, he unveiled a new cooperative complex in Adaroda village and a primary school in Juwal.These projects, under the Model Co-op Village scheme, aim to boost education, sustainability, and rural development across the state.
..