Nagpur: Walkable Street project stumbles
SMART CITIES

Nagpur: Walkable Street project stumbles

The Nagpur Municipal Corporation's (NMC) Rs 150 million Healthy Walkable Street project is set to miss its second extended deadline of March 16, 2025. The project aims to develop the 1.2km stretch along both sides of the road from Abhyankar Nagar Square to Kachipura Square, incorporating a pedestrian walkway, cycling track, plazas, seating arrangements, safety walls, and parking facilities. 

Currently, only 600 meters of the project, spanning from Abhyankar Nagar Square to Bajaj Nagar Square, is under construction. Progress was slow, prompting repeated interventions from municipal commissioner Abhijeet Chaudhari. During an inspection, Chaudhari expressed dissatisfaction with the sluggish pace and directed the contractor to clear the site of construction debris, maintain cleanliness, and ensure complete barricading along the road. Additionally, the commissioner instructed the project department to issue a show-cause notice to the contractor for delays. 

The project's first extended deadline ended on September 16, 2024. Following the commissioner's directives, NMC imposed a fine of Rs5,000 per day on the contractor for the delays. 

According to executive engineer (projects) Kalpana Patane, the contractor has made partial progress, completing 90% of the redevelopment of footpaths on the left-hand side from VNIT to Bajaj Nagar Square, and the right-hand side from Bajaj Nagar Square to Kachipura Square. However, work on other sections is yet to begin due to opposition from shopkeepers. 

Those owning shops along the route fear the redevelopment of footpaths will reduce road width, potentially affecting customer access. Furthermore, the stretch adjacent to Kachipura slum will be developed with low-cost solutions to address specific challenges. 

In addition to the footpaths, NMC plans to improve the geometry of three key intersections, including Abhyankar Nagar Square, Bajaj Nagar Square, and Kachipura Chowk. Work has already begun at Bajaj Nagar Square, which had developed into a saucer-like shape after tar roads were converted to cement concrete on all four side, but the square itself remained a tar road at a lower level. 

To address this, cobblestones will be used to align all the intersections with the road height, simultaneously reducing vehicle speeds. Redesigned traffic islands and consistent road widths at junctions are also part of the project. NMC officials remain optimistic about overcoming these hurdles but acknowledge the need for more effective coordination to meet the revised deadline. The contractor may be granted another extension as NMC remains intent on completing the project despite the delays. 

                                                                                                                                              

The Nagpur Municipal Corporation's (NMC) Rs 150 million Healthy Walkable Street project is set to miss its second extended deadline of March 16, 2025. The project aims to develop the 1.2km stretch along both sides of the road from Abhyankar Nagar Square to Kachipura Square, incorporating a pedestrian walkway, cycling track, plazas, seating arrangements, safety walls, and parking facilities. Currently, only 600 meters of the project, spanning from Abhyankar Nagar Square to Bajaj Nagar Square, is under construction. Progress was slow, prompting repeated interventions from municipal commissioner Abhijeet Chaudhari. During an inspection, Chaudhari expressed dissatisfaction with the sluggish pace and directed the contractor to clear the site of construction debris, maintain cleanliness, and ensure complete barricading along the road. Additionally, the commissioner instructed the project department to issue a show-cause notice to the contractor for delays. The project's first extended deadline ended on September 16, 2024. Following the commissioner's directives, NMC imposed a fine of Rs5,000 per day on the contractor for the delays. According to executive engineer (projects) Kalpana Patane, the contractor has made partial progress, completing 90% of the redevelopment of footpaths on the left-hand side from VNIT to Bajaj Nagar Square, and the right-hand side from Bajaj Nagar Square to Kachipura Square. However, work on other sections is yet to begin due to opposition from shopkeepers. Those owning shops along the route fear the redevelopment of footpaths will reduce road width, potentially affecting customer access. Furthermore, the stretch adjacent to Kachipura slum will be developed with low-cost solutions to address specific challenges. In addition to the footpaths, NMC plans to improve the geometry of three key intersections, including Abhyankar Nagar Square, Bajaj Nagar Square, and Kachipura Chowk. Work has already begun at Bajaj Nagar Square, which had developed into a saucer-like shape after tar roads were converted to cement concrete on all four side, but the square itself remained a tar road at a lower level. To address this, cobblestones will be used to align all the intersections with the road height, simultaneously reducing vehicle speeds. Redesigned traffic islands and consistent road widths at junctions are also part of the project. NMC officials remain optimistic about overcoming these hurdles but acknowledge the need for more effective coordination to meet the revised deadline. The contractor may be granted another extension as NMC remains intent on completing the project despite the delays.                                                                                                                                               

Next Story
Infrastructure Urban

3i Infotech Reports Rs 7.25 Bn Revenue for FY25

3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..

Next Story
Infrastructure Urban

Emerald Finance Joins Baya PTE to Boost SME Bill Discounting

Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..

Next Story
Infrastructure Urban

BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25

BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, 鈥淲e are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement