Smart City work near Caculo Mall may miss May 31 target
15 May 2024
2 Min Read
CW Team
The Imagine Panaji Smart City Development (IPSCDL) seems to be considering skipping the smart road work from Caculo Mall to the Tonca sewerage treatment plant (STP) due to practical challenges, despite the May 31 deadline for completing all ongoing smart city work in Panaji.
According to IPSCDL, the cumulative target for completing all road works and making the road functional is May 31. However, they mentioned that this particular stretch might take a "little longer" to finish. IPSCDL stated that major challenges have been encountered in drilling due to the depth of sewerage works along the stretch, which is nearly 8 meters below road level and below the bed of the St Inez creek.
Out of the total 430 metres, the main trunk pipeline of 300 meters has been laid, and work on the remaining 130 meters, which passes under the St Inez creek and connects to the Tonca STP, is currently in progress. IPSCDL added that along this stretch, one out of nine manholes has been completed, and another one is in progress.
IPSCDL, led by its CEO Sanjit Rodrigues, is monitoring the ongoing sewerage work on the stretch on an hourly basis to meet the May 31 deadline. Regarding the stretch from the Four Pillar junction to the Old Patto bridge, the contractor appointed by IPSCDL has completed all major sewerage works, including laying a total pipeline of 1,400 meters, constructing 40 manholes, and installing 80 house connection chambers. Only one inter-connection is pending, which is expected to be completed in a couple of days. Currently, road restoration work is underway.
IPSCDL mentioned that road construction on this stretch for the smart road project can only commence after the Public Works Department (PWD) finishes installing new pumping lines to connect pump houses located at Mala, near Bhandari hospital, and near the income tax office.
The Imagine Panaji Smart City Development (IPSCDL) seems to be considering skipping the smart road work from Caculo Mall to the Tonca sewerage treatment plant (STP) due to practical challenges, despite the May 31 deadline for completing all ongoing smart city work in Panaji.
According to IPSCDL, the cumulative target for completing all road works and making the road functional is May 31. However, they mentioned that this particular stretch might take a little longer to finish. IPSCDL stated that major challenges have been encountered in drilling due to the depth of sewerage works along the stretch, which is nearly 8 meters below road level and below the bed of the St Inez creek.
Out of the total 430 metres, the main trunk pipeline of 300 meters has been laid, and work on the remaining 130 meters, which passes under the St Inez creek and connects to the Tonca STP, is currently in progress. IPSCDL added that along this stretch, one out of nine manholes has been completed, and another one is in progress.
IPSCDL, led by its CEO Sanjit Rodrigues, is monitoring the ongoing sewerage work on the stretch on an hourly basis to meet the May 31 deadline. Regarding the stretch from the Four Pillar junction to the Old Patto bridge, the contractor appointed by IPSCDL has completed all major sewerage works, including laying a total pipeline of 1,400 meters, constructing 40 manholes, and installing 80 house connection chambers. Only one inter-connection is pending, which is expected to be completed in a couple of days. Currently, road restoration work is underway.
IPSCDL mentioned that road construction on this stretch for the smart road project can only commence after the Public Works Department (PWD) finishes installing new pumping lines to connect pump houses located at Mala, near Bhandari hospital, and near the income tax office.
Next Story
HCL-Foxconn to invest Rs 37 billion in chip plant near Jewar airport
The Union Cabinet has approved the establishment of a new semiconductor unit near Jewar airport in Uttar Pradesh under the India Semiconductor Mission. This sixth plant, a joint venture between HCL and Foxconn, marks further progress in India鈥檚 semiconductor journey. The project will see an investment of Rs 37 billion.The facility will produce display driver chips for mobile phones, laptops, automobiles, PCs, and other digital devices. It is designed for a monthly capacity of 20,000 wafers and an output of 36 million units.Five semiconductor units are already in advanced stages of constructi..
Next Story
Brigade acquires Velachery land for Rs 16-billion project
Brigade Enterprises has acquired a 5.41-acre land parcel on Velachery Road, Chennai, through an outright purchase for Rs 4.417 billion. Located next to Phoenix Market City, the site will be developed into a premium residential project with a gross development value of approximately Rs 16 billion and a development potential of 0.8 million square feet.The project offers strategic access to both the OMR IT Corridor and Chennai鈥檚 Central Business District, promising strong connectivity and premium lifestyle offerings. Brigade plans to create signature residences focused on aesthetics, functional..
Next Story
Liebherr marks 10,000th XPower wheel loader milestone
Liebherr-Werk Bischofshofen has rolled out its 10,000th XPower wheel loader, marking a major production milestone. The anniversary L 580 XPower model, featuring a power-split travel drive developed with ZF Friedrichshafen AG, was handed over to the BERGER Group in Passau.鈥淭he transmission from our partner ZF is a key component of the drivetrain in our XPower wheel loaders,鈥� said Gerhard Pirnbacher, Head of Quality Management at Liebherr. 鈥淲ith an impressive total of around 64 million operating hours already clocked up by XPower models, this transmission has proven its exceptional robustn..