BMC Ropes in New Contractors to Speed Up Mithi River Desilting Work
WATER & WASTE

BMC Ropes in New Contractors to Speed Up Mithi River Desilting Work

The BMC has appointed two new contractors to complete the Mithi River desilting project after missing the deadline twice. The project had experienced significant delays due to an ongoing police investigation into alleged irregularities with previous contractors. The Mithi River, a key stormwater drain in Mumbai, plays a crucial role in mitigating urban flooding. Desilting began in April as part of the city's pre-monsoon disaster preparedness.

Following the 2005 floods, the BMC prioritised regular maintenance of the river as part of its flood mitigation strategy. The desilting project is divided into three phases, with a total estimated cost of Rs 1 billion between 2025 and 2027.

The project, however, faced substantial setbacks due to the police probe into a contractor scam and the blacklisting of another firm for malpractice. Additionally, heavy rainfall on May 26 further delayed progress as machinery could not access water bodies for several days. Consequently, the BMC extended the deadline to June 7 and appointed two new contractors to accelerate the completion within the next 15 days.

Out of the 2.14 lakh metric tonnes (MT) of silt targeted for removal from the Mithi River, 1.36 lakh MT has been cleared so far. In total, 8.24 lakh MT has been removed from a target of 9.69 lakh MT. Desilting in the island city and the eastern and western suburbs is 100 per cent complete, while work on minor drains is 75.97 per cent complete, with 3.01 lakh MT removed out of a target of 3.96 lakh MT.


News source: The Free Press Journal

The BMC has appointed two new contractors to complete the Mithi River desilting project after missing the deadline twice. The project had experienced significant delays due to an ongoing police investigation into alleged irregularities with previous contractors. The Mithi River, a key stormwater drain in Mumbai, plays a crucial role in mitigating urban flooding. Desilting began in April as part of the city's pre-monsoon disaster preparedness.Following the 2005 floods, the BMC prioritised regular maintenance of the river as part of its flood mitigation strategy. The desilting project is divided into three phases, with a total estimated cost of Rs 1 billion between 2025 and 2027.The project, however, faced substantial setbacks due to the police probe into a contractor scam and the blacklisting of another firm for malpractice. Additionally, heavy rainfall on May 26 further delayed progress as machinery could not access water bodies for several days. Consequently, the BMC extended the deadline to June 7 and appointed two new contractors to accelerate the completion within the next 15 days.Out of the 2.14 lakh metric tonnes (MT) of silt targeted for removal from the Mithi River, 1.36 lakh MT has been cleared so far. In total, 8.24 lakh MT has been removed from a target of 9.69 lakh MT. Desilting in the island city and the eastern and western suburbs is 100 per cent complete, while work on minor drains is 75.97 per cent complete, with 3.01 lakh MT removed out of a target of 3.96 lakh MT.News source: The Free Press Journal

Next Story
Infrastructure Energy

South West Pinnacle Wins Rs 30 Cr Oman Mining Contract

South West Pinnacle Exploration Ltd has secured a Rs 30 crore contract from Minerals Development Oman (MDO) for mining exploration in concession areas 12B and 13.The two-year project will be carried out via Alara Resources LLC, a JV in Oman. MDO, backed by Oman鈥檚 investment authorities, focuses on monetising mineral wealth.The contract covers copper, gold, and chromite and highlights South West Pinnacle鈥檚 growing footprint in international exploration and mining services. ..

Next Story
Equipment

Godrej GEG Boosts Intralogistics with AI and Green Tech

Godrej Enterprises Group (GEG) is revolutionising warehouse and factory logistics through its Material Handling Equipment and Storage Solutions arms by integrating AI, IoT, and automation.With 20鈥�25% market share and 85% local sourcing, GEG champions Atmanirbhar Bharat and sustainability. The Chennai plant, a green manufacturing leader, uses RoHS-compliant materials and has slashed energy consumption by 60%.GEG serves e-commerce, FMCG, retail, and cold chains with high-performance racking and electric forklifts. Upcoming IoT-enabled forklifts and telematics solutions aim to improve speed, sa..

Next Story
Infrastructure Urban

Amit Shah Inaugurates Key Projects Across Gujarat

Union 亚博体育官网首页 Minister Amit Shah inaugurated and laid the foundation stone for various projects in Gujarat鈥檚 Panchmahal district and Ahmedabad.In Godhra, he inaugurated the Center of Excellence building, sports complex, reservoir, and Miyawaki plantation. In Ahmedabad, he unveiled a new cooperative complex in Adaroda village and a primary school in Juwal.These projects, under the Model Co-op Village scheme, aim to boost education, sustainability, and rural development across the state. ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement