Uttar Pradesh to Set Up 1,600 MW Power Plant in Anpara
22 Nov 2023
2 Min Read
CW Team
IIn order to improve the energy sector, the Yogi Adityanath government plans to build a 1,600 MW plant in Anpara. On Monday, the state-owned UP Rajya Vidyut Utpadan Nigam Limited (UPRVUNL) approved a proposal to establish Anpara E in the Sonbhadra district. Meja Utpadan Nigam Limited, a joint venture of UPRVUNL and NTPC, would put up the project.
The project will cost Rs 18,624 crore, according to UPRVUNL chairman Ashish Goel.
The corporation, on the other hand, provided no timetable for project implementation. The plan has now been forwarded to the state government for approval. The UPRVUNL owns the Anpara-A, B, and D units, which have a combined capacity of 2630 MW. Lanco's Anpara-C project has a capacity of 1200 MW.
The decision to build another power unit was made during a review meeting organized by UPRVUNL to analyze the status of the state's current coal-fired thermal power facilities.
UPRVUNL has completed continuing coal firing testing in the initial units of the new thermal projects, Obra C (2x660 MW) and Jawaharpur (2x660 MW), according to Goel. ?Instructions have been given to start regular power generation from these units soon,? he said.
On November 18, the corporation also completed the boiler light up experiment of the 660 MW Panki thermal project near Kanpur. According to Goel, instructions have been provided to begin power generation from the unit by next summer. Work on the Panki facility began in 2017, shortly after the BJP administration took power. The project, however, was significantly delayed, much to the chagrin of the energy department.
Attempts to restart other thermal power plants have failed in the past as well. Goel has asked officials to guarantee that the ongoing and planned unit overhauls at the Anpara, Parichha, and Obra thermal projects are finished on time by January 24.
The firm has also emphasized the importance of obtaining critical/insurance spares to keep the units operational in the long run. Goel stated that required steps should be taken to utilize the ash released by thermal power plants in conformity with the environment ministry's rules.
IIn order to improve the energy sector, the Yogi Adityanath government plans to build a 1,600 MW plant in Anpara. On Monday, the state-owned UP Rajya Vidyut Utpadan Nigam Limited (UPRVUNL) approved a proposal to establish Anpara E in the Sonbhadra district. Meja Utpadan Nigam Limited, a joint venture of UPRVUNL and NTPC, would put up the project.
The project will cost Rs 18,624 crore, according to UPRVUNL chairman Ashish Goel.
The corporation, on the other hand, provided no timetable for project implementation. The plan has now been forwarded to the state government for approval. The UPRVUNL owns the Anpara-A, B, and D units, which have a combined capacity of 2630 MW. Lanco's Anpara-C project has a capacity of 1200 MW.
The decision to build another power unit was made during a review meeting organized by UPRVUNL to analyze the status of the state's current coal-fired thermal power facilities.
UPRVUNL has completed continuing coal firing testing in the initial units of the new thermal projects, Obra C (2x660 MW) and Jawaharpur (2x660 MW), according to Goel. ?Instructions have been given to start regular power generation from these units soon,? he said.
On November 18, the corporation also completed the boiler light up experiment of the 660 MW Panki thermal project near Kanpur. According to Goel, instructions have been provided to begin power generation from the unit by next summer. Work on the Panki facility began in 2017, shortly after the BJP administration took power. The project, however, was significantly delayed, much to the chagrin of the energy department.
Attempts to restart other thermal power plants have failed in the past as well. Goel has asked officials to guarantee that the ongoing and planned unit overhauls at the Anpara, Parichha, and Obra thermal projects are finished on time by January 24.
The firm has also emphasized the importance of obtaining critical/insurance spares to keep the units operational in the long run. Goel stated that required steps should be taken to utilize the ash released by thermal power plants in conformity with the environment ministry's rules.
Next Story
Ganga Expressway Adopts AI for Real-Time Road Quality Checks
The Yogi Adityanath government has partnered with ETH Zurich and RTDT Laboratories AG to deploy artificial intelligence and sensor-based technology on the Ganga Expressway. This system enables real-time monitoring of construction quality, enhancing both safety and ride comfort.Spanning five hundred and ninety-four kilometres across twelve districts from Meerut to Prayagraj, the Ganga Expressway will be India鈥檚 longest. A specially designed Innova vehicle fitted with seven accelerometers now scans all six lanes for surface uniformity and elevation consistency.Unlike traditional methods conduc..
Next Story
Bihar Approves Rs 330 Billion Road Upgrade Plan for FY26
The Ministry of Road Transport and Highways has approved Bihar鈥檚 Rs 330 Bn road development plan for financial year twenty twenty-six. The announcement was made by Road Construction Minister Nitin Naveen, outlining projects aimed at boosting infrastructure and economic growth.Detailed Project Reports have been prepared for works worth Rs 180 to 190 Bn, with construction expected to begin before 15 August upon central approval. Around Rs 199.81 Bn will be spent to upgrade five hundred and twenty-six kilometres of roads to two-lane and four-lane highways.Eight major roads have been approved, i..
Next Story
Reay Road Bridge Inaugurated to Ease South Mumbai Traffic
South Mumbai will unveil the Reay Road Bridge on 13 May 2025, marking a major milestone in the city鈥檚 infrastructure development. This is Mumbai鈥檚 first land-based cable-stayed road overbridge and spans three hundred and eighty-five metres, connecting Byculla and Mazgaon.The six-lane structure includes pedestrian pathways and aims to ease congestion while improving connectivity. The project began on 14 February 2022 after demolition of the earlier British-era bridge. Though construction was completed in December 2024, the formal inauguration is scheduled six months later.Built at an estima..